Senate Bill sb0212c1
CODING: Words stricken are deletions; words underlined are additions.
Florida Senate - 2002 CS for SB 212
By the Committee on Commerce and Economic Opportunities; and
Senator Holzendorf
310-1748-02
1 A bill to be entitled
2 An act relating to construction contracts;
3 requiring a contract for construction of
4 certain dwellings to contain an occupancy date
5 and a penalty for delay of occupancy under
6 certain circumstances; specifying requirements
7 for the penalty; providing a minimum penalty
8 for a contract that does not contain a penalty;
9 providing an effective date.
10
11 Be It Enacted by the Legislature of the State of Florida:
12
13 Section 1. (1) Each contract for construction of a
14 one-family or two-family dwelling must contain a clause that
15 specifies the date by which a certificate of occupancy will be
16 issued and must contain an explicit penalty clause that
17 provides for liquidated damages for delay caused by the
18 builder and that specifies the amount of such damages for each
19 day that issuance of the certificate of occupancy is delayed
20 after the specified date.
21 (2) The penalty clause may provide for actual damages
22 for delay caused by the builder in lieu of providing for
23 liquidated damages if the provision for such damages is
24 explicitly stipulated in the contract.
25 (3) The amount of liquidated damages for delay caused
26 by the builder shall be $100 for each day that issuance of the
27 certificate of occupancy is delayed after the specified date
28 if either of the following apply:
29 (a) The contract does not contain a penalty clause; or
30
31
1
CODING: Words stricken are deletions; words underlined are additions.
Florida Senate - 2002 CS for SB 212
310-1748-02
1 (b) The penalty clause does not contain either the
2 amount of liquidated damages or a provision for actual damages
3 in lieu of liquidated damages.
4 (4) This section does not apply to a contract that is
5 entered into before the effective date of this section or a
6 renewal of such contract.
7 Section 2. This act shall take effect January 1, 2003.
8
9 STATEMENT OF SUBSTANTIAL CHANGES CONTAINED IN
COMMITTEE SUBSTITUTE FOR
10 Senate Bill 212
11
12 The committee substitute replaces the original bill and
requires construction contracts for one-family and two-family
13 dwellings to specify the date by which a certificate of
occupancy will be issued and to provide for liquidated damages
14 for each day that occupancy is delayed by the builder after
the contracted date. If a contract does not specify an amount
15 of liquidated damages, the committee substitute establishes a
default amount at $100 for each day that occupancy is delayed.
16 The committee substitute also allows contracts to provide
actual damages in lieu of liquidated damages.
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
2
CODING: Words stricken are deletions; words underlined are additions.