HB 1169 2003
   
1 A bill to be entitled
2          An act relating to prompt payment for construction
3    services; amending s. 218.70, F.S.; providing a popular
4    name; amending s. 218.72, F.S.; redefining the term "local
5    governmental entity," as used in pt. VII of ch. 218, F.S.,
6    to include community colleges; amending s. 218.735, F.S.;
7    revising provisions relating to timely payment for
8    purchases of construction services; revising deadlines for
9    payment; providing procedures for project closeout and
10    payment of retainage; providing requirements for local
11    government construction retainage; providing that ss.
12    218.72-218.76, F.S., apply to the payment of any payment
13    request for retainage; creating s. 255.0705, F.S.;
14    providing a popular name; amending s. 255.071, F.S.;
15    revising deadlines for the payment of subcontractors, sub-
16    subcontractors, materialmen, and suppliers on construction
17    contracts for public projects; creating ss. 255.072,
18    255.073, 255.074, 255.075, 255.076, 255.077, and 255.078,
19    F.S.; providing definitions; providing for timely payment
20    for purchases of construction services by a public entity;
21    providing procedures for calculating payment due dates;
22    allowing collection of interest; providing procedures for
23    handling improper payment requests; providing for the
24    resolution of disputes; providing for project closeout and
25    payment of retainage; providing for public construction
26    retainage; providing that ss. 255.072-255.076, F.S., apply
27    to the payment of any payment request for retainage;
28    amending s. 255.05, F.S.; providing requirements for
29    certain notices of nonpayment served by a claimant who is
30    not in privity with the contractor; providing limitations
31    on a claimant's institution of certain actions against a
32    contractor or surety; providing for the tolling of a
33    statute of limitations for bringing suit against a
34    contractor or surety; providing an effective date.
35         
36          Be It Enacted by the Legislature of the State of Florida:
37         
38          Section 1. Section 218.70, Florida Statutes, is amended to
39    read:
40          218.70 Popular nameShort title.--This part shall be known
41    by the popular namemay be cited as the "Local Government
42    FloridaPrompt Payment Act."
43          Section 2. Subsection (2) of section 218.72, Florida
44    Statutes, is amended to read:
45          218.72 Definitions.--As used in this part:
46          (2) "Local governmental entity" means a county or
47    municipal government, school board, school district, authority,
48    special taxing district, other political subdivision, community
49    college,or any office, board, bureau, commission, department,
50    branch, division, or institution thereof or any project
51    supported by county or municipal funds.
52          Section 3. Subsection (6) of section 218.735, Florida
53    Statutes, is amended, present subsection (7) is renumbered as
54    subsection (9), and new subsections (7) and (8) are added to
55    said section, to read:
56          218.735 Timely payment for purchases of construction
57    services.--
58          (6) When a contractor receives payment from a local
59    governmental entity for labor, services, or materials furnished
60    by subcontractors and suppliers hired by the contractor, the
61    contractor shall remit payment due to those subcontractors and
62    suppliers within 1015days after the contractor's receipt of
63    payment. When a subcontractor receives payment from a contractor
64    for labor, services, or materials furnished by subcontractors
65    and suppliers hired by the subcontractor, the subcontractor
66    shall remit payment due to those subcontractors and suppliers
67    within 1015days after the subcontractor's receipt of payment.
68    Nothing herein shall prohibit a contractor or subcontractor from
69    disputing, pursuant to the terms of the relevant contract, all
70    or any portion of a payment alleged to be due to another party.
71    In the event of such a dispute, the contractor or subcontractor
72    may withhold the disputed portion of any such payment if the
73    contractor or subcontractor notifies the party whose payment is
74    disputed, in writing, of the amount in dispute and the actions
75    required to cure the dispute. The contractor or subcontractor
76    must pay all undisputed amounts due within the time limits
77    imposed by this section.
78          (7)(a) A local governmental entity must present to the
79    vendor a final punch list of all items required to render
80    complete, satisfactory, and acceptable the construction services
81    purchased, within 30 days after the earliest of the following:
82          1. Issuance of a temporary or final certificate of
83    occupancy, if applicable;
84          2. Substantial completion of the construction services
85    purchased, as defined in the contract; or
86          3. Beneficial occupancy or use of the structure, building,
87    or facility that is the subject of the construction services
88    purchased, as defined in the contract.
89          (b) If the purchase relates to construction services on
90    more than one building or structure, the local governmental
91    entity shall prepare a final punch list for each building or
92    structure. The local governmental entity must present to the
93    vendor a final punch list with regard to each building or
94    structure within 30 days after the earliest of the following:
95          1. Issuance of a temporary or final certificate of
96    occupancy on the particular building or structure, if
97    applicable;
98          2. Substantial completion of the particular building or
99    structure, as defined in the contract; or
100          3. Beneficial occupancy or use of the particular
101    structure, building or facility, as defined in the contract.
102         
103          Unless the contract provides otherwise, the local governmental
104    entity shall pay out retainage to the vendor based upon the
105    value of the construction services rendered with regard to that
106    structure or building as compared to the total value of the
107    purchase.
108          (c) Upon completion of all items on the final punch list,
109    or within 30 days, whichever occurs sooner, the vendor shall
110    submit a payment request for the appropriate amount of
111    retainage. Thereafter, this act applies to the payment of any
112    payment request for retainage.
113          (d) If the local governmental entity fails to present to
114    the vendor a final punch list within the time periods provided
115    in paragraph (a) or paragraph (b), the project is considered to
116    be complete and the vendor shall submit a payment request for
117    the appropriate amount of retainage. Thereafter, this act
118    applies to the payment of any payment request for retainage.
119          (e) All items that require correction and that are
120    identified after the preparation and delivery of the final punch
121    list must be considered warranty items or make-good items, and
122    such items have no effect on the final payment of retainage
123    provided in this section.
124          (8)(a) From the commencement of a local government
125    construction project that is subject to this act until the
126    project is 50-percent complete, as defined in the contract
127    between the local governmental entity and the vendor, a local
128    governmental entity may not withhold as retainage more than 10
129    percent of each progress payment to the vendor. At 50-percent
130    completion, the vendor may submit a payment request to the local
131    governmental entity for up to one-half of the retainage withheld
132    up to that time.
133          (b) After 50-percent completion, as defined in the
134    contract between the local governmental entity and the vendor,
135    the local governmental entity may not withhold as retainage more
136    than 5 percent of each progress payment to the vendor. After 50-
137    percent completion, however, the vendor may withhold retainage
138    from payments to its subcontractors at a rate higher than 5
139    percent, upon showing good cause and providing written notice to
140    the subcontractor. The local governmental entity shall withhold
141    from each progress payment to the vendor the same dollar amount
142    of retainage which the vendor is withholding from that payment
143    from those subcontractors whose work was included in the
144    corresponding payment request.
145          (c) This section does not require the payment or release
146    of amounts that are the subject of a good-faith dispute.
147          (d) This act applies to the payment of any payment request
148    for retainage.
149          Section 4. Section 255.0705, Florida Statutes, is created
150    to read:
151          255.0705 Popular name.--Sections 255.0705-255.078 shall be
152    known by the popular name the "Florida Prompt Payment Act."
153          Section 5. Subsections (2) and (3) of section 255.071,
154    Florida Statutes, are amended to read:
155          255.071 Payment of subcontractors, sub-subcontractors,
156    materialmen, and suppliers on construction contracts for public
157    projects.--
158          (2) The failure to pay any undisputed obligations for such
159    labor, services, or materials within 30 days after the date the
160    labor, services, or materials were furnished and payment for
161    such labor, services, or materials became due, or within 1030
162    days after the date payment for such labor, services, or
163    materials is received, whichever last occurs, shall entitle any
164    person providing such labor, services, or materials to the
165    procedures specified in subsection (3) and the remedies provided
166    in subsection(4).
167          (3) Any person providing labor, services, or materials for
168    the construction of a public building, for the prosecution and
169    completion of a public work, or for repairs upon a public
170    building or public work improvements to real property may file a
171    verified complaint alleging:
172          (a) The existence of a contract for providing such labor,
173    services, or materials to improve real property.
174          (b) A description of the labor, services, or materials
175    provided and alleging that the labor, services, or materials
176    were provided in accordance with the contract.
177          (c) The amount of the contract price.
178          (d) The amount, if any, paid pursuant to the contract.
179          (e) The amount that remains unpaid pursuant to the
180    contract and the amount thereof that is undisputed.
181          (f) That the undisputed amount has remained due and
182    payable pursuant to the contract for more than 30 days after the
183    date the labor or services were accepted or the materials were
184    received.
185          (g) That the person against whom the complaint was filed
186    has received payment on account of the labor, services, or
187    materials described in the complaint more than 1030days prior
188    to the date the complaint was filed.
189          Section 6. Section 255.072, Florida Statutes, is created
190    to read:
191          255.072 Definitions.--As used in ss. 255.073-255.078, the
192    term:
193          (1) "Agent" means project architect, project engineer, or
194    any other agency or person acting on behalf of a public entity.
195          (2) "Construction services" means all labor, services, and
196    materials provided in connection with the construction,
197    alteration, repair, demolition, reconstruction, or any other
198    improvements to real property that require a license under part
199    I or part II of chapter 489.
200          (3) "Payment request" means an invoice or request for
201    payment for construction services which conforms with all
202    statutory requirements and with all requirements specified by
203    the public entity to which the payment request is submitted.
204          (4) "Public entity" means the state, a state university,
205    or any office, board, bureau, commission, department, branch,
206    division, or institution thereof, or any project supported by
207    state funds.
208          (5) "Purchase" means the purchase of construction
209    services.
210          (6) "Vendor" means any person providing construction
211    services to a public entity.
212          Section 7. Section 255.073, Florida Statutes, is created
213    to read:
214          255.073 Timely payment for purchases of construction
215    services.--
216          (1) Except as otherwise provided in ss. 255.072-255.078,
217    s. 215.422 governs the timely payment for construction services
218    by a public entity under this act.
219          (2) If a public entity disputes a portion of a payment
220    request, the undisputed portion must be timely paid, in
221    accordance with subsection (1).
222          (3) When a vendor receives payment from a public entity
223    for labor, services, or materials furnished by subcontractors
224    and suppliers hired by the vendor, the vendor shall remit
225    payment due to those subcontractors and suppliers within 10 days
226    after the vendor's receipt of payment. When a subcontractor
227    receives payment from a vendor for labor, services, or materials
228    furnished by subcontractors and suppliers hired by the
229    subcontractor, the subcontractor shall remit payment due to
230    those subcontractors and suppliers within 10 days after the
231    subcontractor's receipt of payment. This subsection does not
232    prohibit a vendor or subcontractor from disputing, pursuant to
233    the terms of the relevant contract, all or any portion of a
234    payment alleged to be due to another party. If such a dispute
235    occurs, the vendor or subcontractor may withhold the disputed
236    portion of any such payment if the vendor or subcontractor
237    notifies the party whose payment is disputed, in writing, of the
238    amount in dispute and the actions required to cure the dispute.
239    The vendor or subcontractor must pay all undisputed amounts due
240    within the time limits imposed by this section.
241          (4) All payments due under this section and not made
242    within the time periods specified by this section shall bear
243    interest at the rate of 1 percent per month, or the rate
244    specified by contract, whichever is greater.
245          Section 8. Section 255.074, Florida Statutes, is created
246    to read:
247          255.074 Procedures for calculation of payment due dates.--
248          (1) Each public entity shall establish procedures whereby
249    each payment request received by the public entity is marked as
250    received on the date on which it is delivered to an agent or
251    employee of the public entity or of a facility or office of the
252    public entity.
253          (2) If the terms under which a purchase is made allow for
254    partial deliveries and a payment request is submitted for a
255    partial delivery, the time for payment for the partial delivery
256    must be calculated from the time of the partial delivery and the
257    submission of the payment request in the same manner as provided
258    in s. 255.073.
259          (3) The public entity must submit a payment request to the
260    Chief Financial Officer for payment no more than 25 days after
261    receipt of the payment request.
262          Section 9. Section 255.075, Florida Statutes, is created
263    to read:
264          255.075 Mandatory interest.--A contract between a public
265    entity and a vendor or a provider of construction services may
266    not prohibit the collection of late payment interest charges
267    allowable under ss. 255.072-255.078.
268          Section 10. Section 255.076, Florida Statutes, is created
269    to read:
270          255.076 Improper payment request; resolution of
271    disputes.--
272          (1) If a vendor submits an improper payment request, the
273    public entity shall, within 10 days after receiving the improper
274    payment request, notify the vendor that the payment request is
275    improper and indicate what corrective action on the part of the
276    vendor is needed to make the payment request proper.
277          (2) If a dispute occurs between a vendor and a public
278    entity concerning payment of a payment request, the dispute must
279    be resolved as provided in this section. Each public entity
280    shall establish a dispute resolution procedure to be followed by
281    the public entity if such a dispute occurs. The procedure must
282    provide that proceedings to resolve the dispute must commence
283    not later than 45 days after the date on which the public entity
284    received the payment request and must conclude by final decision
285    of the public entity not later than 60 days after the date on
286    which the public entity received the payment request. Such
287    procedures are not subject to chapter 120 and do not constitute
288    an administrative proceeding that prohibits a court from
289    deciding de novo any action arising out of the dispute. If the
290    dispute is resolved in favor of the public entity, interest
291    charges begin to accrue 15 days after the public entity's final
292    decision. If the dispute is resolved in favor of the vendor,
293    interest begins to accrue as of the original date the payment
294    became due.
295          (3) In an action to recover amounts due under ss. 255.072-
296    255.078, the court shall award court costs and reasonable
297    attorney's fees, including fees incurred through any appeal, to
298    the prevailing party, if the court finds that the nonprevailing
299    party withheld any portion of the payment that is the subject of
300    the action without any reasonable basis in law or fact to
301    dispute the prevailing party's claim to those amounts.
302          Section 11. Section 255.077, Florida Statutes, is created
303    to read:
304          255.077 Project closeout and payment of retainage.--
305          (1) A public entity must present to the vendor a final
306    punch list of all items required to render complete,
307    satisfactory, and acceptable the construction services
308    purchased, within 30 days after the earliest of the following:
309          (a) Issuance of a temporary or final certificate of
310    occupancy, if applicable;
311          (b) Substantial completion of the construction services
312    purchased, as defined in the contract; or
313          (c) Beneficial occupancy or use of the structure,
314    building, or facility that is the subject of the construction
315    services purchased, as defined in the contract.
316          (2) If the purchase relates to construction services on
317    more than one building or structure, the public entity shall
318    prepare a final punch list for each building or structure. The
319    public entity must present to the vendor a final punch list with
320    regard to each building or structure within 30 days after the
321    earliest of the following:
322          (a) Issuance of a temporary or final certificate of
323    occupancy on the particular building or structure, if
324    applicable;
325          (b) Substantial completion of the particular building or
326    structure, as defined in the contract; or
327          (c) Beneficial occupancy or use of the particular
328    structure, building, or facility, as defined in the contract.
329         
330          Unless the contract provides otherwise, the public entity shall
331    pay out retainage to the vendor based upon the value of the
332    construction services rendered with regard to that structure or
333    building as compared to the total value of the purchase.
334          (3) Upon completion of all items on the final punch list
335    or within 30 days, whichever occurs sooner, the vendor shall
336    submit a payment request for the appropriate amount of
337    retainage. Thereafter, ss. 255.072-255.076 apply to the payment
338    of any payment request for retainage.
339          (4) If the public entity fails to present to the vendor a
340    final punch list within the time periods provided in subsection
341    (1) or subsection (2), the project is considered to be complete
342    and the vendor shall submit a payment request for the
343    appropriate amount of retainage. Thereafter, ss. 255.072-255.076
344    apply to the payment of any payment request for retainage.
345          (5) All items that require correction which are identified
346    subsequent to preparation and delivery of the final punch list
347    must be considered warranty items or make-good items, and such
348    items have no effect on the final payment of retainage provided
349    in this section.
350          Section 12. Section 255.078, Florida Statutes, is created
351    to read:
352          255.078 Public construction retainage.--
353          (1) From the commencement of a public construction project
354    that is subject to ss. 255.072-255.078 until the project is 50-
355    percent complete, as defined in the contract between the public
356    entity and the vendor, a public entity may not withhold as
357    retainage more than 10 percent of each progress payment to the
358    vendor. At 50-percent completion, the vendor may submit a
359    payment request to the public entity for up to one-half of the
360    retainage withheld up to that time.
361          (2) After 50-percent completion, as defined in the
362    contract between the public entity and the vendor, the public
363    entity may not withhold as retainage more than 5 percent of each
364    progress payment to the vendor. After 50-percent completion,
365    however, the vendor may withhold retainage from payments to its
366    subcontractors at a rate higher than 5 percent, upon showing
367    good cause and providing written notice to the subcontractor.
368    The public entity shall withhold from each progress payment to
369    the vendor the same dollar amount of retainage the vendor is
370    withholding from that payment from those subcontractors whose
371    work was included in the corresponding payment request.
372          (3) This section does not require the payment or release
373    of amounts that are the subject of a good-faith dispute.
374          (4) Sections 255.072-255.076 apply to the payment of any
375    payment request for retainage.
376          Section 13. Paragraph (a) of subsection (2) of section
377    255.05, Florida Statutes, is amended, and subsections (10) and
378    (11) are added to said section, to read:
379          255.05 Bond of contractor constructing public buildings;
380    form; action by materialmen.--
381          (2)(a)1. If a claimant is no longer furnishing labor,
382    services, or materials on a project, a contractor or the
383    contractor's agent or attorney may elect to shorten the
384    prescribed time in this paragraph within which an action to
385    enforce any claim against a payment bond provided pursuant to
386    this section may be commenced by recording in the clerk's office
387    a notice in substantially the following form:
388         
389 NOTICE OF CONTEST OF CLAIM
390 AGAINST PAYMENT BOND
391         
392          To: . . . (Name and address of claimant) . . .
393         
394          You are notified that the undersigned contests your notice
395    of nonpayment, dated ____________, ________, and served on the
396    undersigned on ____________, ________, and that the time within
397    which you may file suit to enforce your claim is limited to 60
398    days after the date of service of this notice.
399         
400          DATED on ____________, ________.
401         
402         
403          Signed: . . . (Contractor or Attorney) . . .
404         
405          The claim of any claimant upon whom such notice is served and
406    who fails to institute a suit to enforce his or her claim
407    against the payment bond within 60 days after service of such
408    notice shall be extinguished automatically. The clerk shall mail
409    a copy of the notice of contest to the claimant at the address
410    shown in the notice of nonpayment or most recent amendment
411    thereto and shall certify to such service on the face of such
412    notice and record the notice. Service is complete upon mailing.
413          2. A claimant, except a laborer, who is not in privity
414    with the contractor shall, before commencing or not later than
415    45 days after commencing to furnish labor, materials, or
416    supplies for the prosecution of the work, furnish the contractor
417    with a notice that he or she intends to look to the bond for
418    protection. A claimant who is not in privity with the contractor
419    and who has not received payment for his or her labor,
420    materials, or supplies shall deliver to the contractor and to
421    the surety written notice of the performance of the labor or
422    delivery of the materials or supplies and of the nonpayment. The
423    notice of nonpayment may be served at any time during the
424    progress of the work or thereafter but not before 45 days after
425    the first furnishing of labor, services, or materials, and not
426    later than 90 days after the final furnishing of the labor,
427    services, or materials by the claimant or, with respect to
428    rental equipment, not later than 90 days after the date that the
429    rental equipment was last on the job site available for use. Any
430    notice of nonpayment served by a claimant who is not in privity
431    with the contractor which includes sums for retainage must
432    specify the portion of the amount claimed for retainage.No
433    action for the labor, materials, or supplies may be instituted
434    against the contractor or the surety unless both notices have
435    been given. Notices required or permitted under this section may
436    be served in accordance with s. 713.18. An action, except for an
437    action exclusively for recovery of retainage, must be instituted
438    against the contractor or the surety on the payment bond or the
439    payment provisions of a combined payment and performance bond
440    within 1 year after the performance of the labor or completion
441    of delivery of the materials or supplies. An action exclusively
442    for recovery of retainage must be instituted against the
443    contractor or the surety within 1 year after the performance of
444    the labor or completion of delivery of the materials or
445    supplies, or within 90 days after receipt of final payment (or
446    the payment estimate containing the owner's final reconciliation
447    of quantities if no further payment is earned and due as a
448    result of deductive adjustments) by the contractor or surety,
449    whichever comes last. A claimant may not waive in advance his or
450    her right to bring an action under the bond against the surety.
451    In any action brought to enforce a claim against a payment bond
452    under this section, the prevailing party is entitled to recover
453    a reasonable fee for the services of his or her attorney for
454    trial and appeal or for arbitration, in an amount to be
455    determined by the court, which fee must be taxed as part of the
456    prevailing party's costs, as allowed in equitable actions. The
457    time periods for service of a notice of nonpayment or for
458    bringing an action against a contractor or a surety shall be
459    measured from the last day of furnishing labor, services, or
460    materials by the claimant and shall not be measured by other
461    standards, such as the issuance of a certificate of occupancy or
462    the issuance of a certificate of substantial completion.
463          (10) Notwithstanding any other provision of law to the
464    contrary, a claimant may not institute an action for the sole
465    purpose of recovery of retainage against the contractor or
466    against the surety issuing a payment or performance bond
467    pursuant to this section until:
468          (a) The public entity has paid out that retainage to the
469    contractor and the time provided under ss. 218.70-218.76 or ss.
470    255.072-255.078 for payment of that retainage to the claimant
471    has expired; or
472          (b) The claimant has completed all work under its
473    contract, including the items identified on the owner's final
474    punch list, and 60 days have passed since the owner's receipt of
475    the contractor's final payment request.
476          (11) Notwithstanding any other provision of law to the
477    contrary, the statute of limitations for bringing suit against a
478    contractor or a surety shall not run if the contractor has
479    failed to comply with the payment provisions set forth in ss.
480    255.072-255.078.
481          Section 14. This act shall take effect July 1, 2003.