Representative Jennings offered the following: |
13
|
|
14
|
Amendment (with directory and title amendments) |
15
|
Remove line(s) 8-82, and insert: |
16
|
Section 1. Paragraph (a) of subsection (1) and subsections |
17
|
(3) and (6) of section 255.05, Florida Statutes, are amended, |
18
|
and subsection (4) of said section is reenacted, to read: |
19
|
255.05 Bond of contractor constructing public buildings; |
20
|
form; action by materialmen.-- |
21
|
(1)(a) Any person entering into a formal contract with the |
22
|
state or any county, city, or political subdivision thereof, or |
23
|
other public authority, for the construction of a public |
24
|
building, for the prosecution and completion of a public work, |
25
|
or for repairs upon a public building or public work shall be |
26
|
required, before commencing the work or before recommencing the |
27
|
work after a default or abandonment, to execute, deliver to the |
28
|
public owner, and record in the public records of the county |
29
|
where the improvement is located, a payment bond and a |
30
|
performance bond with a surety insurer authorized to do business |
31
|
in this state as surety. A public entity may not require a |
32
|
contractor to secure a surety bond under this section from a |
33
|
specific agent or bonding company. EachThebond must state on |
34
|
its front page: the name, principal business address, and phone |
35
|
number of the contractor, the surety, the owner of the property |
36
|
being improved, and, if different from the owner, the |
37
|
contracting public entity; the contract number assigned by the |
38
|
contracting public entity; and a description of the project |
39
|
sufficient to identify it, such as a legal description or the |
40
|
street address of the property being improved, and a general |
41
|
description of the improvement. The performanceSuchbond shall |
42
|
be conditioned upon the contractor's performance of the |
43
|
construction work in the time and manner prescribed in the |
44
|
contract, and the payment bond shall be conditioned upon the |
45
|
contractorpromptly making payments to all persons defined in s. |
46
|
713.01 who furnish labor, services, or materials for the |
47
|
prosecution of the work provided for in the contract. Any |
48
|
claimant may apply to the governmental entity having charge of |
49
|
the work for copies of the contract and the paymentbond and |
50
|
shall thereupon be furnished with a certified copy of the |
51
|
contract and the paymentbond. The claimant shall have a right |
52
|
of action against the contractor and surety for the amount due |
53
|
him or her, including unpaid finance charges due under the |
54
|
claimant's contract. Such action shall not involve the public |
55
|
authority in any expense. When such work is done for the state |
56
|
and the contract is for $100,000 or less, no payment orand |
57
|
performance bond shall be required. At the discretion of the |
58
|
official or board awarding such contract when such work is done |
59
|
for any county, city, political subdivision, or public |
60
|
authority, any person entering into such a contract which is for |
61
|
$200,000 or less may be exempted from executing the payment and |
62
|
performance bonds required by this sectionbond. When such work |
63
|
is done for the state, the Secretary of the Department of |
64
|
Management Services may delegate to state agencies the authority |
65
|
to exempt any person entering into such a contract amounting to |
66
|
more than $100,000 but less than $200,000 from executing the |
67
|
payment and performance bonds required by this sectionbond. In |
68
|
the event such exemption is granted, the officer or officials |
69
|
shall not be personally liable to persons suffering loss because |
70
|
of granting such exemption. The Department of Management |
71
|
Services shall maintain information on the number of requests by |
72
|
state agencies for delegation of authority to waive the bond |
73
|
requirements by agency and project number and whether any |
74
|
request for delegation was denied and the justification for the |
75
|
denial. |
76
|
(3)(a) The performancebond required in subsection (1) may |
77
|
be in substantially the following form: |
78
|
|
79
|
PUBLIC CONSTRUCTION PERFORMANCEBOND |
80
|
|
81
|
Bond No. (enter bond number)
|
82
|
|
83
|
BY THIS BOND, We, _____(enter name, principal business |
84
|
address, and telephone number of contractor) , as Principal, |
85
|
and _____(enter name, principal business address, and telephone |
86
|
number of surety) , a corporation authorized to do business |
87
|
in Florida as a surety insurer, as Surety, are bound to |
88
|
_____(enter name, principal business address, and telephone |
89
|
number of public owner) , hereinafterhereincalled Owner, |
90
|
in the sum of $_____(enter contract amount as penal sum of bond) |
91
|
, for payment of which the Principal and each individually named |
92
|
surety binds itself and itswe bind ourselves, ourheirs, |
93
|
personal representatives, successors, and assigns, jointly and |
94
|
severally. |
95
|
|
96
|
WHEREAS, Principal has entered into a contract with Owner |
97
|
for ...(enter description of project sufficient to identify it, |
98
|
such as a legal description of property, the street address of |
99
|
property, and a general description of the improvement to be |
100
|
constructed)..., which is Owner's contract No. ...(enter |
101
|
contract number)... belonging to ...(enter name, principal |
102
|
business address, and telephone number of owner of property if |
103
|
different from the contracting public entity)...; and
|
104
|
|
105
|
WHEREAS, the Bond is given to meet the requirements of the |
106
|
contract and Section 255.05, Florida Statutes, and the |
107
|
respective rights and obligations of the Principal, Surety, and |
108
|
Owner shall be controlled by the contract and Section 255.05, |
109
|
Florida Statutes.
|
110
|
|
111
|
NOW, THEREFORE,THE CONDITION OF THIS BOND is that if |
112
|
Principal: |
113
|
1. Performs the contract dated _____(enter date of |
114
|
contract) , _____,between Principal and Owner for |
115
|
construction of ___the Project__, the contract being made a part |
116
|
of this bond by reference, at the times and in the manner |
117
|
prescribed in the contract; and |
118
|
2. Promptly makes payments to all claimants, as defined in |
119
|
Section 255.05(1), Florida Statutes, supplying Principal with |
120
|
labor, materials, or supplies, used directly or indirectly by |
121
|
Principal in the prosecution of the work provided for in the |
122
|
contract; and
|
123
|
2.3. Pays Owner all losses, damages as defined in the |
124
|
contract, expenses, costs, and attorney's fees, including |
125
|
appellate proceedings, that Owner sustains because of a default |
126
|
by Principal under the contract; and |
127
|
3.4.Performs the guarantee of all work and materials |
128
|
furnished under the contract for the time specified in the |
129
|
contract, then this bond is void; otherwise it remains in full |
130
|
force. |
131
|
|
132
|
NO RIGHT OF ACTION SHALL ACCRUE ON THIS BOND TO, OR FOR THE |
133
|
BENEFIT OR USE OF, ANY PERSON OR CORPORATION OTHER THAN . . . |
134
|
(enter the name of public owner) . . ., THE OWNER, ITS |
135
|
SUCCESSORS, AND ASSIGNS. |
136
|
|
137
|
Any changes in or under the contract documents and compliance or |
138
|
noncompliance with any formalities connected with the contract |
139
|
or the changes does not affect Surety's obligation under this |
140
|
bond. |
141
|
|
142
|
DATED ON _____, _____(enter date of bond) . |
143
|
|
144
|
... (entername of Principal) ... |
145
|
By ... (enter name of its authorized officer)(As Attorney in |
146
|
Fact)... |
147
|
... (enter name of Surety) ...
|
148
|
|
149
|
By ... (its authorized Attorney-in-Fact)
|
150
|
(b) The payment bond required in subsection (1) may be in |
151
|
substantially the following form:
|
152
|
|
153
|
PUBLIC CONSTRUCTION PAYMENT BOND
|
154
|
|
155
|
Bond No. (enter bond number)
|
156
|
|
157
|
BY THIS BOND, We, _____(enter name, principal business |
158
|
address, and telephone number of contractor) , as Principal, |
159
|
and _____(enter name, principal business address, and telephone |
160
|
number of surety) , a corporation authorized to do business |
161
|
in Florida as a surety insurer, as Surety, are bound to |
162
|
_____(enter name, principal business address, and telephone |
163
|
number of public owner) , hereinafter called Owner, in the |
164
|
sum of $_____(enter contract amount as penal sum of bond) , |
165
|
for payment of which the Principal and each individually named |
166
|
surety binds itself and its heirs, personal representatives, |
167
|
successors, and assigns, jointly and severally.
|
168
|
|
169
|
WHEREAS, Principal has entered into a contract with Owner |
170
|
for ...(enter description of project sufficient to identify it, |
171
|
such as a legal description of property, the street address of |
172
|
property, and a general description of the improvement to be |
173
|
constructed)..., which is Owner's contract No. ...(enter |
174
|
contract number)... belonging to ...(enter name, principal |
175
|
business address, and telephone number of owner of property if |
176
|
different from the contracting public entity)...; and
|
177
|
|
178
|
WHEREAS, the Bond is given to meet the requirements of the |
179
|
contract and Section 255.05, Florida Statutes, and the |
180
|
respective rights and obligations of the Principal, Surety, |
181
|
Owner, and any Claimant shall be controlled by Section 255.05, |
182
|
Florida Statutes, including specifically the notice and time |
183
|
limitation provisions of Section 255.05(2), Florida Statutes.
|
184
|
|
185
|
NOW, THEREFORE, THE CONDITION OF THIS BOND is that if |
186
|
Principal:
|
187
|
1. Performs the contract dated _____(enter date of |
188
|
contract) , between Principal and Owner for construction of |
189
|
___the Project__, the contract being made a part of this bond by |
190
|
reference, at the times and in the manner prescribed in the |
191
|
contract; and
|
192
|
2. Pays Owner all losses, damages as defined in the |
193
|
contract, expenses, costs, and attorney's fees, including |
194
|
appellate proceedings, that Owner sustains because of a default |
195
|
by Principal under the contract; and
|
196
|
3. Promptly makes payments to all claimants, as defined in |
197
|
Section 255.05(1), Florida Statutes, supplying Principal with |
198
|
labor, materials, or supplies, used directly or indirectly by |
199
|
Principal in the prosecution of the work provided for in the |
200
|
contract, then this bond is void; otherwise, it remains in full |
201
|
force, subject, however, to the following conditions:
|
202
|
a. No action for labor, materials, or supplies may be |
203
|
instituted against the Principal or the Surety unless the |
204
|
notices required under Section 255.05(2), Florida Statutes, have |
205
|
been given; and
|
206
|
b. Any action under this Bond must be instituted in |
207
|
accordance with the notice and time limitation provisions |
208
|
prescribed in Section 255.05(2), Florida Statutes.
|
209
|
|
210
|
Any changes in or under the contract documents and compliance or |
211
|
noncompliance with any formalities connected with the contract |
212
|
or the changes does not affect Surety's obligation under this |
213
|
bond.
|
214
|
|
215
|
DATED ON _____, _____(enter date of bond) .
|
216
|
|
217
|
... (enter name of Principal) ...
|
218
|
By ... (enter name of its authorized officer) ...
|
219
|
... (enter name of Surety) ...
|
220
|
|
221
|
By ... (its authorized Attorney-in-Fact)
|
222
|
(4) The payment provisions of all bonds furnished for |
223
|
public work contracts described in subsection (1) shall, |
224
|
regardless of form, be construed and deemed statutory bond |
225
|
provisions, subject to all requirements of subsection (2). |
226
|
(6) The notice and time limitation provisions of |
227
|
subsection (2) shall apply to all payment bonds furnished for |
228
|
public building and public work contracts described in |
229
|
subsection (1), and any deviation from such requirements |
230
|
contained in the bond form used by the public owner or furnished |
231
|
by the contractor shall be disregardedAll bonds executed |
232
|
pursuant to this section shall make reference to this section by |
233
|
number and shall contain reference to the notice and time |
234
|
limitation provisions of this section. |
235
|
|
236
|
================= T I T L E A M E N D M E N T ================= |
237
|
Remove line(s) 3-4, and insert: |
238
|
255.05, F.S.; providing for forms for public performance |
239
|
construction bonds and payment construction bonds for |
240
|
public work contracts; describing form of said public |
241
|
construction bonds; reenacting s. 255.05(4), F.S.; |
242
|
requiring payment bond provisions to be construed as |
243
|
statutory bonds; providing that deviations from the notice |
244
|
and time limitations in s. 255.05(2), F.S., in bond forms |
245
|
must be disregarded; providing an effective date. |