1
|
A bill to be entitled |
2
|
An act relating to construction services; amending s. |
3
|
218.70, F.S.; revising a popular name; amending s. 218.72, |
4
|
F.S.; redefining terms used in pt. VII of ch. 218, F.S.; |
5
|
amending s. 218.735, F.S.; revising provisions relating to |
6
|
timely payment for purchases of construction services; |
7
|
revising deadlines for payment; providing procedures for |
8
|
project closeout and payment of retainage; providing |
9
|
requirements for local government construction retainage; |
10
|
providing that s. 218.735, F.S., applies to the payment of |
11
|
any payment request for retainage; creating s. 255.0705, |
12
|
F.S.; providing a popular name; amending s. 255.071, F.S.; |
13
|
revising deadlines for the payment of subcontractors, sub- |
14
|
subcontractors, materialmen, and suppliers on construction |
15
|
contracts for public projects; creating ss. 255.072, |
16
|
255.073, 255.074, 255.075, 255.076, 255.077, and 255.078, |
17
|
F.S.; providing definitions; providing for timely payment |
18
|
for purchases of construction services by a public entity; |
19
|
providing procedures for calculating payment due dates; |
20
|
authorizing the collection of interest under certain |
21
|
circumstances; providing procedures for handling improper |
22
|
payment requests; providing for the resolution of |
23
|
disputes; providing for payment of court costs and |
24
|
attorney's fees; providing for project closeout and |
25
|
payment of retainage; providing for public construction |
26
|
retainage; providing that ss. 255.072-255.078, F.S., apply |
27
|
to the payment of any payment request for retainage; |
28
|
amending s. 255.05, F.S.; providing requirements for |
29
|
certain notices of nonpayment served by a claimant who is |
30
|
not in privity with the contractor; providing limitations |
31
|
on a claimant's institution of certain actions against a |
32
|
contractor or surety; providing for certain notices to the |
33
|
claimant; creating s. 725.09, F.S.; prohibiting the |
34
|
inclusion in a contract for the purchase of construction |
35
|
materials or services a provision that conditions payment |
36
|
for such materials or services on the receipt of payment |
37
|
from any other entity; providing an effective date. |
38
|
|
39
|
Be It Enacted by the Legislature of the State of Florida: |
40
|
|
41
|
Section 1. Section 218.70, Florida Statutes, is amended to |
42
|
read: |
43
|
218.70 Popular name Short title.--This part may be cited |
44
|
by the popular name as the "Local Government FloridaPrompt |
45
|
Payment Act." |
46
|
Section 2. Subsections (2), (6), and (7) of section |
47
|
218.72, Florida Statutes, are amended to read: |
48
|
218.72 Definitions.--As used in this part: |
49
|
(2) "Local governmental entity" means a county or |
50
|
municipal government, school board, school district, authority, |
51
|
special taxing district, other political subdivision, community |
52
|
college,or any office, board, bureau, commission, department, |
53
|
branch, division, or institution thereof or any project |
54
|
supported by county or municipal funds. |
55
|
(6) "Vendor" means any person who sells goods or services, |
56
|
sells or leases personal property, or leases real property |
57
|
directly to a local governmental entity. The term includes any |
58
|
person who provides waste-hauling services to residents or |
59
|
businesses located within the boundaries of a local government |
60
|
pursuant to a contract or local ordinance. |
61
|
(7) "Construction services" means all labor, services, and |
62
|
materials provided in connection with the construction, |
63
|
alteration, repair, demolition, reconstruction, or any other |
64
|
improvements to real property that require a license under parts |
65
|
I and II of chapter 489. |
66
|
Section 3. Subsection (6) of section 218.735, Florida |
67
|
Statutes, is amended, present subsection (7) is renumbered as |
68
|
subsection (9), and new subsections (7) and (8) are added to |
69
|
said section, to read: |
70
|
218.735 Timely payment for purchases of construction |
71
|
services.-- |
72
|
(6) When a contractor receives payment from a local |
73
|
governmental entity for labor, services, or materials furnished |
74
|
by subcontractors and suppliers hired by the contractor, the |
75
|
contractor shall remit payment due to those subcontractors and |
76
|
suppliers within 10 15days after the contractor's receipt of |
77
|
payment. When a subcontractor receives payment from a contractor |
78
|
for labor, services, or materials furnished by subcontractors |
79
|
and suppliers hired by the subcontractor, the subcontractor |
80
|
shall remit payment due to those subcontractors and suppliers |
81
|
within 10 15days after the subcontractor's receipt of payment. |
82
|
Nothing herein shall prohibit a contractor or subcontractor from |
83
|
disputing, pursuant to the terms of the relevant contract, all |
84
|
or any portion of a payment alleged to be due to another party. |
85
|
In the event of such a dispute, the contractor or subcontractor |
86
|
may withhold the disputed portion of any such payment if the |
87
|
contractor or subcontractor notifies the party whose payment is |
88
|
disputed, in writing, of the amount in dispute and the actions |
89
|
required to cure the dispute. The contractor or subcontractor |
90
|
must pay all undisputed amounts due within the time limits |
91
|
imposed by this section. |
92
|
(7)(a) Each contract for construction services between a |
93
|
local governmental entity and a vendor must provide for the |
94
|
development of a list of items required to render complete, |
95
|
satisfactory, and acceptable the construction services purchased |
96
|
by the local government. The contract must specify the process |
97
|
for the development of the list, including the respective |
98
|
responsibilities of the local government and the vendor in |
99
|
developing and reviewing the list and a reasonable timeframe for |
100
|
developing the list as follows: |
101
|
1. For construction projects with an estimated cost of |
102
|
less than $10 million, within 30 days after reaching substantial |
103
|
completion of the construction services purchased as defined in |
104
|
the contract or, if not defined in the contract, upon reaching |
105
|
beneficial occupancy or use; or |
106
|
2. For construction projects with an estimated cost of $10 |
107
|
million or more, within 30 days, unless otherwise extended by |
108
|
contract not to exceed 90 days, after reaching substantial |
109
|
completion of the construction services purchased as defined in |
110
|
the contract or, if not defined in the contract, upon reaching |
111
|
beneficial occupancy or use. |
112
|
(b) If the contract between the local governmental entity |
113
|
and the vendor relates to the purchase of construction services |
114
|
on more than one building or structure or involves a multiphased |
115
|
project, the contract must provide for the development of a list |
116
|
of items required to render complete, satisfactory, and |
117
|
acceptable the construction services purchased for each |
118
|
building, structure, or phase of the project in accordance with |
119
|
the timeframes specified in subparagraph (a)1. or subparagraph |
120
|
(a)2. |
121
|
(c) The failure to include any corrective work or pending |
122
|
items not yet completed on the list developed pursuant to this |
123
|
subsection does not alter the responsibility of the vendor to |
124
|
complete all the purchased construction services as defined in |
125
|
the contract. |
126
|
(d) Upon completion of all items on the list, or at such |
127
|
other time as defined in the contract, the vendor may submit a |
128
|
payment request for the appropriate amount of retainage. The |
129
|
local government may withhold an amount not to exceed 150 |
130
|
percent of the total costs to complete any incomplete items on |
131
|
the list. |
132
|
(e) All items that require correction under the contract |
133
|
and that are identified after the preparation and delivery of |
134
|
the list remain the obligation of the vendor as defined by the |
135
|
contract. |
136
|
(f) Warranty items may not affect the final payment of |
137
|
retainage as provided in this section or as provided in the |
138
|
contract between the vendor and its subcontractors and |
139
|
suppliers. |
140
|
(g) Retainage may not be held by a local governmental |
141
|
entity or a vendor to secure payment of insurance premiums under |
142
|
a consolidated insurance program or series of insurance policies |
143
|
issued to a public agency or a contractor for a project or group |
144
|
of projects, and the final payment of retainage as provided in |
145
|
this section may not be delayed pending a final audit by the |
146
|
local governmental entity's or the vendor's insurance provider. |
147
|
(h) If a local governmental entity fails to comply with |
148
|
its responsibilities to develop the list required under |
149
|
paragraph (a) or paragraph (b) as defined in the contract, and |
150
|
the timeframes provided in subparagraph(a)1. or subparagraph |
151
|
(a)2., the vendor may submit a payment request for the |
152
|
appropriate amount of retainage. The local governmental entity |
153
|
need not pay or process any request for payment of retainage if |
154
|
the vendor has, in whole or in part, failed to cooperate with |
155
|
the local government in the development of the list or failed to |
156
|
perform its contractual responsibilities, if any, with regard to |
157
|
the development of the list or if paragraph (8)(d) applies. |
158
|
(8)(a) In any public construction project that is subject |
159
|
to ss. 218.72-218.78, a local governmental entity may withhold |
160
|
an amount not exceeding 10 percent of each progress payment made |
161
|
to the vendor until the local governmental project has reached |
162
|
50-percent completion. After the project has reached 50-percent |
163
|
completion, the local government must reduce to 5 percent the |
164
|
amount of retainage withheld from each subsequent progress |
165
|
payment made to the vendor. However, notwithstanding the |
166
|
provisions of this subsection, a municipality with a population |
167
|
of 25,000 or fewer, or a county with a population of 100,000 or |
168
|
fewer, may withhold retainage in an amount not exceeding 10 |
169
|
percent of each progress payment made to the vendor until final |
170
|
completion and acceptance of the project by the local |
171
|
government. For purposes of this subsection, the term "50- |
172
|
percent completion" means as defined in the contract between the |
173
|
local governmental entity and the vendor or, if not defined in |
174
|
the contract, the point at which the local government has |
175
|
expended 50 percent of the total project costs identified in the |
176
|
contract, plus all change orders and other additions issued |
177
|
subsequent to the approval of the contract by the governing body |
178
|
of the local government, and the level of actual project |
179
|
construction is equivalent to such expenditure of funds. |
180
|
(b) After the project has reached 50-percent completion, |
181
|
the vendor may present to the local governmental entity a |
182
|
payment request for up to one-half of the retainage amount held |
183
|
by the local government. The local governmental entity shall |
184
|
promptly make payment to the vendor, unless the local government |
185
|
has grounds, pursuant to the contract or as provided in |
186
|
paragraph (d), for withholding the payment of retainage. If the |
187
|
local government makes payment of retainage to the vendor under |
188
|
this paragraph, the vendor shall timely remit payment of such |
189
|
retainage to the appropriate subcontractors and suppliers. |
190
|
(c) After the project has reached 50-percent completion, |
191
|
the vendor may elect to withhold retainage from payments to its |
192
|
subcontractors at a rate higher than 5 percent. The specific |
193
|
amount to be withheld must be determined on a case-by-case basis |
194
|
and must be based on the vendor's assessment of the |
195
|
subcontractor's past performance, the likelihood that such |
196
|
performance will continue, and the vendor's ability to rely on |
197
|
other safeguards. The vendor shall notify the subcontractor, in |
198
|
writing, of its determination to withhold more than 5 percent of |
199
|
the progress payment and the reasons for making that |
200
|
determination, and the vendor may not request the release of |
201
|
such retained funds from the local government. |
202
|
(d) This section does not require the local government to |
203
|
pay or release any amounts that are the subject of a good faith |
204
|
dispute, the subject of an action brought under s. 255.05, or |
205
|
otherwise the subject of a claim or demand by the local |
206
|
government or vendor. |
207
|
(e) The timeframes set forth in this section for payment |
208
|
of payment requests apply to any payment request for retainage |
209
|
made pursuant to this subsection. |
210
|
Section 4. Section 255.0705, Florida Statutes, is created |
211
|
to read: |
212
|
255.0705 Popular name.--Sections 255.0705-255.078 may be |
213
|
cited by the popular name the "Florida Prompt Payment Act." |
214
|
Section 5. Subsections (2) and (3) of section 255.071, |
215
|
Florida Statutes, are amended to read: |
216
|
255.071 Payment of subcontractors, sub-subcontractors, |
217
|
materialmen, and suppliers on construction contracts for public |
218
|
projects.-- |
219
|
(2) The failure to pay any undisputed obligations for such |
220
|
labor, services, or materials within 30 days after the date the |
221
|
labor, services, or materials were furnished and payment for |
222
|
such labor, services, or materials became due, or within 10 30 |
223
|
days after the date payment for such labor, services, or |
224
|
materials is received, whichever last occurs, shall entitle any |
225
|
person providing such labor, services, or materials to the |
226
|
procedures specified in subsection (3) and the remedies provided |
227
|
in subsection (4). |
228
|
(3) Any person providing labor, services, or materials for |
229
|
the construction of a public building, for the prosecution and |
230
|
completion of a public work, or for repairs upon a public |
231
|
building or public work improvements to real property may file a |
232
|
verified complaint alleging: |
233
|
(a) The existence of a contract for providing such labor, |
234
|
services, or materials to improve real property. |
235
|
(b) A description of the labor, services, or materials |
236
|
provided and alleging that the labor, services, or materials |
237
|
were provided in accordance with the contract. |
238
|
(c) The amount of the contract price. |
239
|
(d) The amount, if any, paid pursuant to the contract. |
240
|
(e) The amount that remains unpaid pursuant to the |
241
|
contract and the amount thereof that is undisputed. |
242
|
(f) That the undisputed amount has remained due and |
243
|
payable pursuant to the contract for more than 30 days after the |
244
|
date the labor or services were accepted or the materials were |
245
|
received. |
246
|
(g) That the person against whom the complaint was filed |
247
|
has received payment on account of the labor, services, or |
248
|
materials described in the complaint more than 10 30days prior |
249
|
to the date the complaint was filed. |
250
|
Section 6. Section 255.072, Florida Statutes, is created |
251
|
to read: |
252
|
255.072 Definitions.--As used in ss. 255.073-255.078, the |
253
|
term: |
254
|
(1) "Agent" means project architect, project engineer, or |
255
|
any other agency or person acting on behalf of a public entity. |
256
|
(2) "Construction services" means all labor, services, and |
257
|
materials provided in connection with the construction, |
258
|
alteration, repair, demolition, reconstruction, or any other |
259
|
improvement to real property. The term "construction services" |
260
|
does not include contracts or work performed for the Department |
261
|
of Transportation. |
262
|
(3) "Payment request" means an invoice or request for |
263
|
payment for construction services which conforms with all |
264
|
statutory requirements and with all requirements specified by |
265
|
the public entity to which the payment request is submitted. |
266
|
(4) "Public entity" means the state, a state university, |
267
|
or any office, board, bureau, commission, department, branch, |
268
|
division, or institution thereof, or any project supported by |
269
|
state funds, but does not include a local governmental entity as |
270
|
defined in s. 218.72. |
271
|
(5) "Purchase" means the purchase of construction |
272
|
services. |
273
|
(6) "Vendor" means any person providing construction |
274
|
services directly to a public entity. |
275
|
Section 7. Section 255.073, Florida Statutes, is created |
276
|
to read: |
277
|
255.073 Timely payment for purchases of construction |
278
|
services.-- |
279
|
(1) Except as otherwise provided in ss. 255.072-255.078, |
280
|
s. 215.422 governs the timely payment for construction services |
281
|
by a public entity under this act. |
282
|
(2) If a public entity disputes a portion of a payment |
283
|
request, the undisputed portion must be timely paid in |
284
|
accordance with subsection (1). |
285
|
(3) When a vendor receives payment from a public entity |
286
|
for labor, services, or materials furnished by subcontractors |
287
|
and suppliers hired by the vendor, the vendor shall remit |
288
|
payment due to those subcontractors and suppliers within 10 days |
289
|
after the vendor's receipt of payment. When a subcontractor |
290
|
receives payment from a vendor for labor, services, or materials |
291
|
furnished by subcontractors and suppliers hired by the |
292
|
subcontractor, the subcontractor shall remit payment due to |
293
|
those subcontractors and suppliers within 10 days after the |
294
|
subcontractor's receipt of payment. This subsection does not |
295
|
prohibit a vendor or subcontractor from disputing, pursuant to |
296
|
the terms of the relevant contract, all or any portion of a |
297
|
payment alleged to be due to another party. If such a dispute |
298
|
occurs, the vendor or subcontractor may withhold the disputed |
299
|
portion of any such payment if the vendor or subcontractor |
300
|
notifies the party whose payment is disputed, in writing, of the |
301
|
amount in dispute and the actions required to cure the dispute. |
302
|
The vendor or subcontractor must pay all undisputed amounts due |
303
|
within the time limits imposed by this section. |
304
|
(4) All payments due under this section and not made |
305
|
within the time periods specified by this section shall bear |
306
|
interest at the rate of 1 percent per month, or the rate |
307
|
specified by contract, whichever is greater. |
308
|
Section 8. Section 255.074, Florida Statutes, is created |
309
|
to read: |
310
|
255.074 Procedures for calculation of payment due dates.-- |
311
|
(1) Each public entity shall establish procedures whereby |
312
|
each payment request received by the public entity is marked as |
313
|
received on the date on which it is delivered to an agent or |
314
|
employee of the public entity or of a facility or office of the |
315
|
public entity. |
316
|
(2) If the terms under which a purchase is made allow for |
317
|
partial deliveries and a payment request is submitted for a |
318
|
partial delivery, the time for payment for the partial delivery |
319
|
must be calculated from the time of the partial delivery and the |
320
|
submission of the payment request in the same manner as provided |
321
|
in s. 255.073. |
322
|
(3) The public entity must submit a payment request to the |
323
|
Chief Financial Officer for payment no more than 25 days after |
324
|
receipt of the payment request. |
325
|
Section 9. Section 255.075, Florida Statutes, is created |
326
|
to read: |
327
|
255.075 Mandatory interest.--A contract between a public |
328
|
entity and a vendor or a provider of construction services may |
329
|
not prohibit the collection of late payment interest charges |
330
|
allowable under ss. 255.072-255.078. |
331
|
Section 10. Section 255.076, Florida Statutes, is created |
332
|
to read: |
333
|
255.076 Improper payment request; resolution of |
334
|
disputes.-- |
335
|
(1) If a vendor submits an improper payment request, the |
336
|
public entity shall, within 10 days after receiving the improper |
337
|
payment request, notify the vendor that the payment request is |
338
|
improper and indicate what corrective action on the part of the |
339
|
vendor is needed to make the payment request proper. |
340
|
(2) If a dispute occurs between a vendor and a public |
341
|
entity concerning payment of a payment request, the dispute must |
342
|
be resolved as provided in this section. Each public entity |
343
|
shall establish a dispute resolution procedure to be followed by |
344
|
the public entity if such a dispute occurs. The procedure must |
345
|
provide that proceedings to resolve the dispute must commence |
346
|
not later than 45 days after the date on which the public entity |
347
|
received the payment request and must conclude by final decision |
348
|
of the public entity not later than 60 days after the date on |
349
|
which the public entity received the payment request. Such |
350
|
procedures are not subject to chapter 120 and do not constitute |
351
|
an administrative proceeding that prohibits a court from |
352
|
deciding de novo any action arising out of the dispute. If the |
353
|
dispute is resolved in favor of the public entity, interest |
354
|
charges begin to accrue 15 days after the public entity's final |
355
|
decision. If the dispute is resolved in favor of the vendor, |
356
|
interest begins to accrue as of the original date the payment |
357
|
became due. |
358
|
(3) In an action to recover amounts due under ss. 255.072- |
359
|
255.078, the court shall award court costs and reasonable |
360
|
attorney's fees, including fees incurred through any appeal, to |
361
|
the prevailing party if the court finds that the nonprevailing |
362
|
party withheld any portion of the payment that is the subject of |
363
|
the action without any reasonable basis in law or fact to |
364
|
dispute the prevailing party's claim to those amounts. |
365
|
Section 11. Section 255.077, Florida Statutes, is created |
366
|
to read: |
367
|
255.077 Project closeout and payment of retainage.-- |
368
|
(1) Each contract for construction services between a |
369
|
public entity and a vendor must provide for the development of a |
370
|
list of items required to render complete, satisfactory, and |
371
|
acceptable the construction services purchased by the public |
372
|
entity. The contract must specify the process for the |
373
|
development of the list, including the respective |
374
|
responsibilities of the public entity and the vendor in |
375
|
developing and reviewing the list. The list must be developed |
376
|
within 30 days after substantial completion of the construction |
377
|
services purchased as defined in the contract or, if not defined |
378
|
in the contract, within 30 days after beneficial occupancy or |
379
|
use of the project. |
380
|
(2) If the contract between the public entity and the |
381
|
vendor relates to the purchase of construction services on more |
382
|
than one building or structure or involves a multiphased |
383
|
project, the contract must provide for the development of a list |
384
|
of items required to render complete, satisfactory, and |
385
|
acceptable the construction services purchased for each |
386
|
building, structure, or phase of the project. Each list must be |
387
|
developed within 30 days after substantial completion of the |
388
|
construction services purchased as defined in the contract for |
389
|
each building, structure, or phase of the project or, if not |
390
|
defined in the contract, within 30 days after beneficial |
391
|
occupancy or use of each building, structure, or phase of the |
392
|
project. |
393
|
(3) The failure to include any corrective work or pending |
394
|
items not yet completed on the list developed under this section |
395
|
does not alter the responsibility of the vendor to complete all |
396
|
the purchased construction services as defined in the contract. |
397
|
(4) Upon completion of all items on the list, or at such |
398
|
other time as defined in the contract, the vendor may submit a |
399
|
payment request for the appropriate amount of retainage. The |
400
|
public entity may withhold an amount not to exceed 150 percent |
401
|
of the total costs to complete any incomplete items on the list. |
402
|
(5) All items that require correction under the contract |
403
|
and that are identified after the preparation and delivery of |
404
|
the list remain the obligation of the vendor as defined by the |
405
|
contract. |
406
|
(6) Warranty items may not affect the final payment of |
407
|
retainage as provided in this section or as provided in the |
408
|
contract between the vendor and its subcontractors and |
409
|
suppliers. |
410
|
(7) Retainage may not be held by a public entity or a |
411
|
vendor to secure payment of insurance premiums under a |
412
|
consolidated insurance program or series of insurance policies |
413
|
issued to a public agency or a contractor for a project or group |
414
|
of projects, and the final payment of retainage as provided in |
415
|
this section may not be delayed pending a final audit by the |
416
|
public entity's or the vendor's insurance provider. |
417
|
(8) If a public entity fails to comply with its |
418
|
responsibilities to develop the list required under subsection |
419
|
(1) or subsection (2), the vendor may submit a payment request |
420
|
for the appropriate amount of retainage. The public entity need |
421
|
not pay or process any request for payment of retainage if the |
422
|
vendor has, in whole or in part, failed to cooperate with the |
423
|
public entity in the development of the list or failed to |
424
|
perform its contractual responsibilities, if any, with regard to |
425
|
the development of the list. |
426
|
Section 12. Section 255.078, Florida Statutes, is created |
427
|
to read: |
428
|
255.078 Public construction retainage.-- |
429
|
(1) In any public construction project that is subject to |
430
|
ss. 255.072-255.078, a public entity may withhold an amount not |
431
|
exceeding 10 percent of each progress payment made to the vendor |
432
|
until the project has reached 50-percent completion. After the |
433
|
project has reached 50-percent completion, the public entity |
434
|
must reduce to 5 percent the amount of retainage withheld from |
435
|
each subsequent progress payment made to the vendor. As used in |
436
|
this section, the term "50-percent completion" means as defined |
437
|
in the contract between the public entity and the vendor or, if |
438
|
not defined in the contract, the point at which the public |
439
|
entity has expended 50 percent of the amount of the total |
440
|
project costs identified in the contract, plus all change orders |
441
|
and other additions issued after the approval of the contract by |
442
|
the public entity, and the level of actual project construction |
443
|
is equivalent to such expenditure of funds. |
444
|
(2) After the project has reached 50-percent completion, |
445
|
the vendor may present to the public entity a payment request |
446
|
for up to one-half of the retainage amount held by the public |
447
|
entity. The public entity shall promptly make payment to the |
448
|
vendor unless the public entity has grounds, under the contract |
449
|
or as provided in subsection (4), for withholding the payment of |
450
|
retainage. If the public entity makes payment of retainage to |
451
|
the vendor under this subsection, the vendor shall timely remit |
452
|
payment of such retainage to the appropriate subcontractors and |
453
|
suppliers. |
454
|
(3) After the project has reached 50-percent completion, |
455
|
the vendor may elect to withhold retainage from payments to its |
456
|
subcontractors at a rate higher than 5 percent. The specific |
457
|
amount to be withheld must be determined on a case-by-case basis |
458
|
and must be based on the vendor's assessment of the |
459
|
subcontractor's past performance, the likelihood that such |
460
|
performance will continue, and the vendor's ability to rely on |
461
|
other safeguards. The vendor shall notify the subcontractor, in |
462
|
writing, of its determination to withhold more than 5 percent of |
463
|
the progress payment and the reasons for making that |
464
|
determination, and the vendor may not request the release of |
465
|
such withheld funds from the public entity. |
466
|
(4) This section does not require the public entity to pay |
467
|
or release any amounts that are the subject of a good faith |
468
|
dispute, the subject of an action brought under s. 255.05, or |
469
|
otherwise the subject of a claim or demand by the public entity |
470
|
or vendor. |
471
|
(5) The timeframes set forth in ss. 255.072-255.078 for |
472
|
payment of payment requests apply to any payment request for |
473
|
retainage made pursuant to this section. |
474
|
Section 13. Paragraph (a) of subsection (2) of section |
475
|
255.05, Florida Statutes, is amended, and subsections (10) and |
476
|
(11) are added to said section, to read: |
477
|
255.05 Bond of contractor constructing public buildings; |
478
|
form; action by materialmen.-- |
479
|
(2)(a)1. If a claimant is no longer furnishing labor, |
480
|
services, or materials on a project, a contractor or the |
481
|
contractor's agent or attorney may elect to shorten the |
482
|
prescribed time in this paragraph within which an action to |
483
|
enforce any claim against a payment bond provided pursuant to |
484
|
this section may be commenced by recording in the clerk's office |
485
|
a notice in substantially the following form: |
486
|
|
487
|
NOTICE OF CONTEST OF CLAIM |
488
|
AGAINST PAYMENT BOND |
489
|
|
490
|
To: . . . (Name and address of claimant) . . . |
491
|
|
492
|
You are notified that the undersigned contests your notice |
493
|
of nonpayment, dated ____________, ________, and served on the |
494
|
undersigned on ____________, ________, and that the time within |
495
|
which you may file suit to enforce your claim is limited to 60 |
496
|
days after the date of service of this notice. |
497
|
|
498
|
DATED on ____________, ________. |
499
|
|
500
|
|
501
|
Signed: . . . (Contractor or Attorney) . . . |
502
|
|
503
|
The claim of any claimant upon whom such notice is served and |
504
|
who fails to institute a suit to enforce his or her claim |
505
|
against the payment bond within 60 days after service of such |
506
|
notice shall be extinguished automatically. The clerk shall mail |
507
|
a copy of the notice of contest to the claimant at the address |
508
|
shown in the notice of nonpayment or most recent amendment |
509
|
thereto and shall certify to such service on the face of such |
510
|
notice and record the notice. Service is complete upon mailing. |
511
|
2. A claimant, except a laborer, who is not in privity |
512
|
with the contractor shall, before commencing or not later than |
513
|
45 days after commencing to furnish labor, materials, or |
514
|
supplies for the prosecution of the work, furnish the contractor |
515
|
with a notice that he or she intends to look to the bond for |
516
|
protection. A claimant who is not in privity with the contractor |
517
|
and who has not received payment for his or her labor, |
518
|
materials, or supplies shall deliver to the contractor and to |
519
|
the surety written notice of the performance of the labor or |
520
|
delivery of the materials or supplies and of the nonpayment. The |
521
|
notice of nonpayment may be served at any time during the |
522
|
progress of the work or thereafter but not before 45 days after |
523
|
the first furnishing of labor, services, or materials, and not |
524
|
later than 90 days after the final furnishing of the labor, |
525
|
services, or materials by the claimant or, with respect to |
526
|
rental equipment, not later than 90 days after the date that the |
527
|
rental equipment was last on the job site available for use. Any |
528
|
notice of nonpayment served by a claimant who is not in privity |
529
|
with the contractor which includes sums for retainage must |
530
|
specify the portion of the amount claimed for retainage.No |
531
|
action for the labor, materials, or supplies may be instituted |
532
|
against the contractor or the surety unless both notices have |
533
|
been given. Notices required or permitted under this section may |
534
|
be served in accordance with s. 713.18. An action, except for an |
535
|
action exclusively for recovery of retainage, must be instituted |
536
|
against the contractor or the surety on the payment bond or the |
537
|
payment provisions of a combined payment and performance bond |
538
|
within 1 year after the performance of the labor or completion |
539
|
of delivery of the materials or supplies. An action exclusively |
540
|
for recovery of retainage must be instituted against the |
541
|
contractor or the surety within 1 year after the performance of |
542
|
the labor or completion of delivery of the materials or |
543
|
supplies, or within 90 days after receipt of final payment (or |
544
|
the payment estimate containing the owner's final reconciliation |
545
|
of quantities if no further payment is earned and due as a |
546
|
result of deductive adjustments) by the contractor or surety, |
547
|
whichever comes last. A claimant may not waive in advance his or |
548
|
her right to bring an action under the bond against the surety. |
549
|
In any action brought to enforce a claim against a payment bond |
550
|
under this section, the prevailing party is entitled to recover |
551
|
a reasonable fee for the services of his or her attorney for |
552
|
trial and appeal or for arbitration, in an amount to be |
553
|
determined by the court, which fee must be taxed as part of the |
554
|
prevailing party's costs, as allowed in equitable actions. The |
555
|
time periods for service of a notice of nonpayment or for |
556
|
bringing an action against a contractor or a surety shall be |
557
|
measured from the last day of furnishing labor, services, or |
558
|
materials by the claimant and shall not be measured by other |
559
|
standards, such as the issuance of a certificate of occupancy or |
560
|
the issuance of a certificate of substantial completion. |
561
|
(10) Notwithstanding any other provision of law to the |
562
|
contrary, a claimant may not institute an action for the sole |
563
|
purpose of recovery of retainage against the contractor or |
564
|
against the surety issuing a payment or performance bond |
565
|
pursuant to this section until: |
566
|
(a) The public entity has paid out that retainage to the |
567
|
contractor and the time provided under ss. 218.70-218.76 or ss. |
568
|
255.072-255.078 for payment of that retainage to the claimant |
569
|
has expired; |
570
|
(b) The claimant has completed all work required under its |
571
|
contract and 90 days have passed since the owner's receipt of |
572
|
the contractor's last payment request; or |
573
|
(c) The claimant has made the written request to the owner |
574
|
as provided in subsection (11) and has not timely received the |
575
|
requested information from the owner. |
576
|
(11) An owner shall furnish in writing to a claimant who |
577
|
has provided labor, services, or materials to a project, within |
578
|
5 business days after receipt of a written request from that |
579
|
claimant, the following information: |
580
|
(a) The dates of all payment requests received by the |
581
|
owner from the contractor. |
582
|
(b) The dates of all payments made by the owner to the |
583
|
contractor. |
584
|
(c) Whether the owner has received the contractor's final |
585
|
payment request and, if so, the date the final payment request |
586
|
was submitted by the contractor to the owner. |
587
|
Section 14. Section 725.09, Florida Statutes, is created |
588
|
to read: |
589
|
725.09 Construction contracts; contingent payment |
590
|
provisions.--An entity may not enter into a contract for the |
591
|
purchase of construction materials or services which conditions |
592
|
payment for such materials or services on the receipt of payment |
593
|
from any other entity. Any such conditional payment provision is |
594
|
void as a violation of the public policy of this state. |
595
|
Section 15. This act shall take effect July 1, 2004. |