HB 0689CS

CHAMBER ACTION




1The Committee on Natural Resources recommends the following:
2
3     Committee Substitute
4     Remove the entire bill and insert:
5
A bill to be entitled
6An act relating to electric transmission line siting;
7amending s. 403.52, F.S.; changing the short title to the
8"Florida Electric Transmission Line Siting Act"; amending
9s. 403.521, F.S.; revising legislative intent; amending s.
10403.522, F.S.; revising definitions; defining "licensee";
11amending s. 403.523, F.S.; revising powers and duties of
12the Department of Environmental Protection; requiring the
13department to collect and process fees, to prepare a
14project impact analysis, to act as clerk for the siting
15board, and to administer and manage the terms and
16conditions of the certification order and supporting
17documents and records; amending s. 403.524, F.S.; revising
18provisions for applicability, certification, and
19exemptions under the act; requiring the application to
20contain the starting point and ending point of a
21transmission line specifically defined by the applicant
22and verified by the commission; revising provisions for
23notice by an electric utility of its intent to construct
24an exempted transmission line; amending s. 403.525, F.S.;
25providing for powers and duties of the administrative law
26judge designated by the Division of Administrative
27Hearings to conduct the required hearings; amending s.
28403.5251, F.S.; revising application procedures and
29schedules; providing for the formal date of certification
30application filing and commencement of the certification
31review process; requiring the department to prepare a
32proposed schedule of dates for determination of
33completeness and other significant dates to be followed
34during the certification process; providing for the formal
35date of application distribution; requiring the applicant
36to file notice of distribution and notice of filing of the
37application; amending s. 403.5252, F.S.; revising
38timeframes and procedures for determination of
39completeness of the application; requiring the department
40to consult with affected agencies; revising requirements
41for the department to file a statement of its
42determination of completeness with the Division of
43Administrative Hearings, the applicant, and all parties
44within a certain time after distribution of the
45application; revising requirements for the applicant to
46file a statement with the department, the division, and
47all parties, if the department determines the application
48is not complete; providing for that statement to notify
49the department that the information will not be provided;
50revising timeframes and procedures for contests of the
51determination by the department; providing for parties to
52a hearing on the issue of completeness; repealing s.
53403.5253, F.S., relating to determination of sufficiency
54of application or amendment to the application; amending
55s. 403.526, F.S.; revising criteria and procedures for
56preliminary statements of issues, reports, and studies;
57revising timeframes; requiring the preliminary statement
58of issues from each affected agency be submitted to all
59parties; revising criteria for the Department of Community
60Affairs' report; requiring the Department of
61Transportation to prepare an impact report; providing for
62project impact reports from other agencies; revising
63required content of the reports; providing for notice of
64any agency nonprocedural requirements not listed in the
65application; providing for failure to provide such
66notification; providing for a recommendation for approval
67or denial of the application; providing for receipt of an
68affirmative determination of need to be a condition
69precedent to further processing of the application;
70requiring the department to prepare a project impact
71analysis to be filed with the administrative law judge and
72served on all parties within a certain timeframe; amending
73s. 403.527, F.S.; revising procedures and timeframes for
74the certification hearing conducted by the administrative
75law judge; revising provisions for notices and publication
76of notices, public hearings held by local governments,
77testimony at the public hearing portion of the
78certification hearing, the order of presentations at the
79hearing, consideration of certain communications by the
80administrative law judge, requiring the applicant to pay
81certain expenses and costs, and requiring the
82administrative law judge to issue a recommended order
83disposing of the application; requiring certain notices be
84made in accordance with specified requirements and within
85a certain timeframe; specifying the Department of
86Transportation as a party to the proceedings; providing
87for the administrative law judge to cancel the
88certification hearing and relinquish jurisdiction to the
89department upon request by the applicant or the
90department; requiring the department and the applicant to
91publish notice of such cancellation; providing for parties
92to submit proposed recommended orders to the department
93when the certification hearing has been canceled;
94providing for the department to prepare a recommended
95order for final action by the siting board when the
96hearing has been canceled; amending s. 403.5271, F.S.;
97revising procedures and timeframes for consideration of
98proposed alternate corridors; revising notice
99requirements; providing for notice of the filing of the
100alternate corridor and revised time schedules; providing
101for notice to agencies newly affected by the proposed
102alternate corridor; requiring the person proposing the
103alternate corridor to provide all data to the agencies
104within a certain timeframe; providing for determination by
105the department that the data is not complete; providing
106for withdrawal of the proposed alternate corridor upon
107such determination; providing for agencies to file reports
108with the applicant and department that address the
109proposed alternate corridor; providing for the department
110to file with the administrative law judge, the applicant,
111and all parties a project impact analysis of the proposed
112alternate corridor; providing that the party proposing an
113alternate corridor shall have the burden of proof on the
114certifiability of the alternate corridor; amending s.
115403.5272, F.S.; revising procedures for informational
116public meetings; providing for informational public
117meetings held by regional planning councils; revising
118timeframes; amending s. 403.5275, F.S.; revising
119provisions for amendment to the application prior to
120certification; amending s. 403.529, F.S.; revising
121provisions for final disposition of the application by the
122siting board; providing for the administrative law judge's
123or department's recommended order; amending s. 403.531,
124F.S.; revising provisions for conditions of certification;
125amending s. 403.5312, F.S.; requiring the applicant to
126file notice of a certified corridor route with the
127department; creating s. 403.5317, F.S.; providing
128procedures for changes proposed by the licensee after
129certification; requiring the department to determine
130within a certain time if the proposed change requires
131modification of the conditions of certification; requiring
132notice to the licensee, all agencies, and all parties of
133changes that are approved as not requiring modification of
134the conditions of certification; creating s. 403.5363,
135F.S.; requiring publication of certain notices by the
136applicant, the proponent of an alternate corridor, and the
137department; requiring the department to adopt rules
138specifying the content of such notices; amending s.
139403.5365, F.S.; revising application fees and the
140distribution of fees collected; revising procedures for
141reimbursement of local governments and regional planning
142organizations; repealing s. 403.5369, F.S., relating to
143application of the act to applications prior to a certain
144date; amending s. 403.537, F.S.; revising the schedule for
145notice of a public hearing by the Public Service
146Commission to determine the need for a transmission line;
147amending ss. 373.441, 403.061, 403.0876, and 403.809,
148F.S.; conforming terminology; providing an effective date.
149
150Be It Enacted by the Legislature of the State of Florida:
151
152     Section 1.  Section 403.52, Florida Statutes, is amended to
153read:
154     403.52  Popular name Short title.--Sections 403.52-403.5365
155may be known by the popular name cited as the "Florida Electric
156Transmission Line Siting Act."
157     Section 2.  Section 403.521, Florida Statutes, is amended
158to read:
159     403.521  Legislative intent.--The legislative intent of
160this act is to establish a centralized and coordinated licensing
161permitting process for the location of electric transmission
162line corridors and the construction and maintenance of electric
163transmission lines, which necessarily involves several broad
164interests of the public addressed through the subject matter
165jurisdiction of several agencies. The Legislature recognizes
166that electric transmission lines will have an effect upon
167electric power system reliability, the environment, land use,
168and the welfare of the population. Recognizing the need to
169ensure electric power system reliability and integrity, and in
170order to meet electric electrical energy needs in an orderly and
171timely fashion, the centralized and coordinated licensing
172permitting process established by this act is intended to
173further the legislative goal of ensuring through available and
174reasonable methods that the location of transmission line
175corridors and the construction and maintenance of transmission
176lines produce minimal adverse effects on the environment and
177public health, safety, and welfare while not unduly conflicting
178with the goals established by the applicable local comprehensive
179plan. It is the intent of this act to fully balance the need for
180transmission lines with the broad interests of the public in
181order to effect a reasonable balance between the need for the
182facility as a means of providing reliable, economically
183efficient electric abundant low-cost electrical energy and the
184impact on the public and the environment resulting from the
185location of the transmission line corridor and the construction
186and maintenance of the transmission lines. The Legislature
187intends that the provisions of chapter 120 apply to this act and
188to proceedings pursuant to it except as otherwise expressly
189exempted by other provisions of this act.
190     Section 3.  Section 403.522, Florida Statutes, is amended
191to read:
192     403.522  Definitions relating to the Florida Electric
193Transmission Line Siting Act.--As used in this act:
194     (1)  "Act" means the Florida Electric Transmission Line
195Siting Act.
196     (2)  "Agency," as the context requires, means an official,
197officer, commission, authority, council, committee, department,
198division, bureau, board, section, or other unit or entity of
199government, including a county, municipality, or other regional
200or local governmental entity.
201     (3)  "Amendment" means a material change in information
202provided by the applicant to the application for certification
203made after the initial application filing.
204     (4)  "Applicant" means any electric utility which applies
205for certification pursuant to the provisions of this act.
206     (5)  "Application" means the documents required by the
207department to be filed to initiate and support a certification
208review and evaluation, including the initial document filing,
209amendments, and responses to requests from the department for
210additional data and information proceeding. An electric utility
211may file a comprehensive application encompassing all or a part
212of one or more proposed transmission lines.
213     (6)  "Board" means the Governor and Cabinet sitting as the
214siting board.
215     (7)  "Certification" means the approval by the board of a
216corridor proper for certification pursuant to subsection (10)
217and the construction and maintenance of transmission lines
218within such corridor with such changes or conditions as the
219board deems appropriate. Certification shall be evidenced by a
220written order of the board.
221     (8)  "Commission" means the Florida Public Service
222Commission.
223     (9)  "Completeness" means that the application has
224addressed all applicable sections of the prescribed application
225format and, but does not mean that those sections are sufficient
226in comprehensiveness of data or in quality of information
227provided to allow the department to determine whether the
228application provides the reviewing agencies adequate information
229to prepare the reports required by s. 403.526.
230     (10)  "Corridor" means the proposed area within which a
231transmission line right-of-way, including maintenance and access
232roads, is to be located. The width of the corridor proposed for
233certification by an applicant or other party, at the option of
234the applicant, may be the width of the transmission line right-
235of-way, or a wider boundary, not to exceed a width of one-half 1
236mile. The area within the corridor in which a right-of-way may
237be located may be further restricted by a condition of
238certification. After all property interests required for the
239transmission line right-of-way have been acquired by the
240applicant, the boundaries of the area certified shall narrow to
241only that land within the boundaries of the transmission line
242right-of-way, maintenance roads, and access roads. The corridors
243proper for certification shall be those addressed in the
244application, in amendments to the application filed pursuant to
245s. 403.5275, and in notices of acceptance of proposed alternate
246corridors filed by an applicant and the department pursuant to
247s. 403.5271 for which the required sufficient information for
248the preparation of agency supplemental reports was filed.
249     (11)  "Department" means the Department of Environmental
250Protection.
251     (12)  "Electric utility" means cities and towns, counties,
252public utility districts, regulated electric companies, electric
253cooperatives, regional transmission organizations, independent
254transmission system operators, or similar entities created and
255approved pursuant to the Federal Energy Regulatory Commission's
256Order 2000, and joint operating agencies, or combinations
257thereof, engaged in, or authorized to engage in, the business of
258generating, transmitting, or distributing electric energy.
259     (13)  "License" means a franchise, permit, certification,
260registration, charter, comprehensive plan amendment, development
261order, or permit as defined in chapters 163 and 380, or similar
262form of authorization required by law, but it does not include a
263license required primarily for revenue purposes when issuance of
264the license is merely a ministerial act.
265     (14)  "Licensee" means an applicant that has obtained a
266certification order for the subject project.
267     (15)(14)  "Local government" means a municipality or county
268in the jurisdiction of which the project is proposed to be
269located.
270     (16)(15)  "Modification" means any change in the
271certification order after issuance, including a change in the
272conditions of certification.
273     (17)(16)  "Nonprocedural requirements of agencies" means
274any agency's regulatory requirements established by statute,
275rule, ordinance, or comprehensive plan, excluding any provisions
276prescribing forms, fees, procedures, or time limits for the
277review or processing of information submitted to demonstrate
278compliance with such regulatory requirements.
279     (18)(17)  "Person" means an individual, partnership, joint
280venture, private or public corporation, association, firm,
281public service company, political subdivision, municipal
282corporation, government agency, public utility district, or any
283other entity, public or private, however organized.
284     (19)(18)  "Preliminary statement of issues" means a listing
285and explanation of those issues within the agency's jurisdiction
286which are of major concern to the agency in relation to the
287proposed electric electrical transmission line corridor.
288     (20)(19)  "Regional planning council" means a regional
289planning council as defined in s. 186.503(4) in the jurisdiction
290of which the project is proposed to be located.
291     (20)  "Sufficiency" means that the application is not only
292complete but that all sections are adequate in the
293comprehensiveness of data and in the quality of information
294provided to allow the department to determine whether the
295application provides the reviewing agencies adequate information
296to prepare the reports authorized by s. 403.526.
297     (21)  "Transmission line" means all structures, all
298maintenance and access roads, and all other facilities that need
299to be constructed, operated, or maintained for the purpose of
300conveying electric power any electrical transmission line
301extending from, but not including, an existing or proposed
302substation or power plant to, but not including, an existing or
303proposed transmission network or rights-of-way or substation to
304which the applicant intends to connect which defines the end of
305the proposed project and which is designed to operate at 230
306kilovolts or more. The starting point and ending point of a
307transmission line must be specifically defined by the applicant
308and must be verified by the commission in its determination of
309need. A transmission line includes structures and maintenance
310and access roads that need to be constructed for the project to
311become operational. The transmission line may include, at the
312applicant's option, any proposed terminal or intermediate
313substations or substation expansions necessary to serve the
314transmission line.
315     (22)  "Transmission line right-of-way" means land necessary
316for the construction and maintenance of a transmission line. The
317typical width of the right-of-way shall be identified in the
318application. The right-of-way shall be located within the
319certified corridor and shall be identified by the applicant
320subsequent to certification in documents filed with the
321department prior to construction.
322     (23)  "Water management district" means a water management
323district created pursuant to chapter 373 in the jurisdiction of
324which the project is proposed to be located.
325     Section 4.  Section 403.523, Florida Statutes, is amended
326to read:
327     403.523  Department of Environmental Protection; powers and
328duties.--The department shall have the following powers and
329duties:
330     (1)  To adopt procedural rules pursuant to ss. 120.536(1)
331and 120.54 to implement the provisions of this act and to adopt
332or amend rules to implement the provisions of subsection (10).
333     (2)  To prescribe the form and content of the public
334notices and the form, content, and necessary supporting
335documentation, and any required studies, for certification
336applications. All such data and studies shall be related to the
337jurisdiction of the agencies relevant to the application.
338     (3)  To receive applications for transmission line and
339corridor certifications and initially determine the completeness
340and sufficiency thereof.
341     (4)  To make or contract for studies of certification
342applications. All such studies shall be related to the
343jurisdiction of the agencies relevant to the application. For
344studies in areas outside the jurisdiction of the department and
345in the jurisdiction of another agency, the department may
346initiate such studies, but only with the consent of such agency.
347     (5)  To administer the processing of applications for
348certification and ensure that the applications are processed as
349expeditiously as possible.
350     (6)  To collect and process require such fees as allowed by
351this act.
352     (7)  To prepare a report and a project impact written
353analysis as required by s. 403.526.
354     (8)  To prescribe the means for monitoring the effects
355arising from the location of the transmission line corridor and
356the construction and maintenance of the transmission lines to
357assure continued compliance with the terms of the certification.
358     (9)  To make a determination of acceptability of any
359alternate corridor proposed for consideration pursuant to s.
360403.5271.
361     (10)  To set requirements that reasonably protect the
362public health and welfare from the electric and magnetic fields
363of transmission lines for which an application is filed pursuant
364to after the effective date of this act.
365     (11)  To act as clerk for the siting board.
366     (12)  To administer and manage the terms and conditions of
367the certification order and supporting documents and records for
368the life of the facility.
369     (11)  To present rebuttal evidence on any issue properly
370raised at the certification hearing.
371     Section 5.  Section 403.524, Florida Statutes, is amended
372to read:
373     403.524  Applicability; and certification; exemptions.--
374     (1)  The provisions of this act apply to each transmission
375line as defined herein, except a transmission line certified
376pursuant to the Florida Electrical Power Plant Siting Act. In
377the application, the starting point and ending point of a
378transmission line must be specifically defined by the applicant
379and must be verified by the commission in its determination of
380need.
381     (2)  Except as provided in subsection (1), no construction
382of any transmission line may be undertaken without first
383obtaining certification under this act, but the provisions of
384this act do not apply to:
385     (a)  Transmission lines for which development approval has
386been obtained pursuant to chapter 380.
387     (b)  Transmission lines which have been exempted by a
388binding letter of interpretation issued under s. 380.06(4), or
389in which the Department of Community Affairs or its predecessor
390agency has determined the utility to have vested development
391rights within the meaning of s. 380.05(18) or s. 380.06(20).
392     (c)  Transmission line development in which all
393construction is limited to established rights-of-way.
394Established rights-of-way include such rights-of-way established
395at any time for roads, highways, railroads, gas, water, oil,
396electricity, or sewage and any other public purpose rights-of-
397way. If an established transmission line right-of-way is used to
398qualify for this exemption from the act, the transmission line
399right-of-way must have been established at least 5 years prior
400to the start of construction of the proposed transmission line.
401If an established transmission line right-of-way is relocated to
402accommodate a public project, the date of establishment of the
403original transmission line right-of-way shall apply to the
404relocated transmission line right-of-way for purposes of this
405exemption. Except for transmission line rights-of-way,
406established rights-of-way include rights-of-way created before
407or after October 1, 1983. For transmission line rights-of-way,
408established rights-of-way include rights-of-way created before
409October 1, 1983.
410     (d)  Transmission lines which are less than 15 miles in
411length or which do not cross a county line, unless the applicant
412has elected to apply for certification under the act.
413     (3)  The exemption of a transmission line under this act
414does not constitute an exemption for the transmission line from
415other applicable permitting processes under other provisions of
416law or local government ordinances.
417     (4)  A utility shall notify the department in writing,
418prior to the start of construction, of the electric utility's
419its intent to construct a transmission line exempted pursuant to
420this section. Such notice shall be only for information
421purposes, and no action by the department shall be required
422pursuant to such notice. Notice may be included in any
423demonstration filed with the department prior to the start of
424construction that a new transmission line complies with the
425applicable electric and magnetic field standards.
426     Section 6.  Section 403.525, Florida Statutes, is amended
427to read:
428     403.525  Administrative law judge; appointment; powers and
429duties of administrative law judge.--
430     (1)  Within 7 days after receipt of an application, whether
431complete or not, the department shall request the Division of
432Administrative Hearings to designate an administrative law judge
433to conduct the hearings required by this act. The division
434director shall designate an administrative law judge to conduct
435the hearings required by this act within 7 days after receipt of
436the request from the department. Whenever practicable, the
437division director shall assign an administrative law judge who
438has had prior experience or training in this type of
439certification proceeding. Upon being advised that an
440administrative law judge has been designated, the department
441shall immediately file a copy of the application and all
442supporting documents with the administrative law judge, who
443shall docket the application.
444     (2)  The administrative law judge shall have all powers and
445duties granted to administrative law judges by chapter 120 and
446by the laws and rules of the department.
447     Section 7.  Section 403.5251, Florida Statutes, is amended
448to read:
449     403.5251  Distribution of application; schedules.--
450     (1)  The formal date of certification application filing
451and commencement of the certification review process shall be
452the date on which the applicant has submitted to the department
453copies of the certification application in a quantity identified
454by rule and the certification application fee specified under s.
455403.5365. One copy of the application shall be submitted in
456electronic format.
457     (2)  Within 7 days after the filing of an application, the
458department shall provide the applicant and the Division of
459Administrative Hearings the names and addresses of those
460affected or other agencies entitled to notice and copies of the
461application and any amendments.
462     (3)(2)  Within 15 7 days after the formal date of the
463application filing completeness has been determined, the
464department shall prepare a proposed schedule of dates for
465determination of completeness, submission of statements of
466issues, determination of sufficiency, and submittal of final
467reports, from affected and other agencies and other significant
468dates to be followed during the certification process, including
469dates for filing notices of appearances to be a party pursuant
470to s. 403.527(3)(4). This schedule shall be provided by the
471department to the applicant, the administrative law judge, and
472the agencies identified pursuant to subsection (2) (1).
473     (4)(3)  Within 15 7 days after the filing of the
474application completeness has been determined, the applicant
475shall distribute copies of the application to all agencies
476identified by the department pursuant to subsection (2) (1). The
477applicant shall file a notice that the application has been
478distributed to the administrative law judge and the department.
479The formal date of the distribution of the application shall be
480the date on which such notice is filed. Copies of changes and
481amendments to the application shall be timely distributed by the
482applicant to all agencies and parties who have received a copy
483of the application.
484     (5)  Notice of the filing of the application shall be made
485in accordance with the requirements of s. 403.5363 by the
486applicant no later than 21 days after the application filing.
487     Section 8.  Section 403.5252, Florida Statutes, is amended
488to read:
489     403.5252  Determination of completeness.--
490     (1)(a)  The department shall consult with the affected
491agencies and may include their recommendations on the
492completeness of the application. Such agencies shall submit to
493the department recommendations on the completeness of the
494application within 30 days after the distribution of the
495application.
496     (b)  Within 45 15 days after distribution receipt of an
497application, the department shall file a statement with the
498Division of Administrative Hearings, and with the applicant, and
499with all parties declaring its position with regard to the
500completeness, not the sufficiency, of the application.
501     (2)(1)  If the department declares the application to be
502incomplete, the applicant, within 15 days after the filing of
503the statement by the department, shall file with the Division of
504Administrative Hearings, and with the department, and with all
505parties a statement:
506     (a)  Agreeing with the statement of the department and
507withdrawing the application;
508     (b)  Agreeing with the statement of the department and
509agreeing to render amend the application complete without
510withdrawing it by filing additional information necessary to
511make the application complete. The time schedules shall be
512tolled as of the date of the determination that the application
513is not complete, referencing a complete application under this
514act shall not commence until the application is determined
515complete; or
516     (c)  Notifying the department that the information will not
517be supplied, in which case the application shall be processed as
518filed; or
519     (d)(c)  Contesting the statement of the department.
520     (3)(a)(2)  If the applicant contests the determination by
521the department that an application is incomplete, the
522administrative law judge shall schedule a hearing on the
523statement of completeness. The hearing shall be held as
524expeditiously as possible, but not later than 30 days after the
525filing of the statement by the department. The administrative
526law judge shall render a decision within 10 days after the
527hearing.
528     (b)  Parties to a hearing on the issue of completeness
529shall include the applicant, the department, and any agency that
530has jurisdiction over the matter in dispute. Any substantially
531affected person who wishes to become a party to the completeness
532hearing shall file a motion no later than 10 days prior to the
533date of the hearing.
534     (c)(a)  If the administrative law judge determines that the
535application was not complete as filed, the applicant shall
536withdraw the application or make such additional submittals as
537necessary to complete it. The time schedules referencing a
538complete application under this act shall not commence until the
539application is determined complete.
540     (d)(b)  If the administrative law judge determines that the
541application was complete at the time it was declared incomplete
542filed, the time schedules referencing a complete application
543under this act shall commence upon such determination.
544     Section 9.  Section 403.5253, Florida Statutes, is
545repealed.
546     Section 10.  Section 403.526, Florida Statutes, is amended
547to read:
548     403.526  Preliminary statements of issues, reports, project
549impact analyses, and studies.--
550     (1)  Each affected agency which received an application in
551accordance with s. 403.5251(4)(3) shall submit a preliminary
552statement of issues to the department and all parties the
553applicant no later than 15 60 days after the certification
554application has been determined to be complete distribution of
555the complete application. Such statements of issues shall be
556made available to each local government for use as information
557for public meetings pursuant to s. 403.5272. The failure to
558raise an issue in this preliminary statement of issues shall not
559preclude the issue from being raised in the agency's report.
560     (2)(a)  The following affected agencies shall prepare
561reports as provided below and shall submit them to the
562department and the applicant no later than 60 within 90 days
563after the certification application has been determined to be
564complete distribution of the complete application:
565     1.  The department shall prepare a report as to the impact
566of each proposed transmission line or corridor as it relates to
567matters within its jurisdiction.
568     2.  Each water management district in the jurisdiction of
569which a proposed transmission line or corridor is to be located
570shall prepare a report as to the impact on water resources and
571other matters within its jurisdiction.
572     3.  The Department of Community Affairs shall prepare a
573report containing recommendations which address the impact upon
574the public of the proposed transmission line or corridor, based
575on the degree to which the proposed transmission line or
576corridor is consistent with the applicable portions of the state
577comprehensive plan, emergency management, and other matters
578within its jurisdiction. The Department of Community Affairs may
579also comment on the consistency of the proposed transmission
580line or corridor with applicable strategic regional policy plans
581or local comprehensive plans and land development regulations.
582     4.  The Fish and Wildlife Conservation Commission shall
583prepare a report as to the impact of each proposed transmission
584line or corridor on fish and wildlife resources and other
585matters within its jurisdiction.
586     5.  Each local government shall prepare a report as to the
587impact of each proposed transmission line or corridor on matters
588within its jurisdiction, including the consistency of the
589proposed transmission line or corridor with all applicable local
590ordinances, regulations, standards, or criteria that apply to
591the proposed transmission line or corridor, including local
592comprehensive plans, zoning regulations, land development
593regulations, and any applicable local environmental regulations
594adopted pursuant to s. 403.182 or by other means. No change by
595the responsible local government or local agency in local
596comprehensive plans, zoning ordinances, or other regulations
597made after the date required for the filing of the local
598government's report required by this section shall be applicable
599to the certification of the proposed transmission line or
600corridor unless the certification is denied or the application
601is withdrawn.
602     6.  Each regional planning council shall present a report
603containing recommendations that address the impact upon the
604public of the proposed transmission line or corridor based on
605the degree to which the transmission line or corridor is
606consistent with the applicable provisions of the strategic
607regional policy plan adopted pursuant to chapter 186 and other
608impacts of each proposed transmission line or corridor on
609matters within its jurisdiction.
610     7.  The Department of Transportation shall prepare a report
611as to the impact of the proposed transmission line or corridor
612on roads, railroads, airports, aeronautics, seaports, and other
613matters within its jurisdiction.
614     8.  Any other agency within the jurisdiction of which the
615proposed transmission line and corridor would be located may
616prepare a report addressing the impact of the proposed
617transmission line or corridor on matters within that agency?s
618jurisdiction.
619     (b)  Each report shall contain:
620     1.  A notice of any nonprocedural requirements not
621specifically listed in the application from which a variance,
622exemption, exception, or other relief is necessary in order for
623the board to certify any corridor proposed for certification.
624Failure of such notification shall be treated as a waiver from
625the nonprocedural requirements of that agency.
626     2.  A recommendation for approval or denial of the
627application.
628     3.  the information on variances required by s. 403.531(2)
629and Proposed conditions of certification on matters within the
630jurisdiction of each agency. For each condition proposed by an
631agency, the agency shall list the specific statute, rule, or
632ordinance, as applicable, which authorizes the proposed
633condition.
634     (c)  Each reviewing agency shall initiate the activities
635required by this section no later than 15 days after the
636complete application is distributed. Each agency shall keep the
637applicant and the department informed as to the progress of its
638studies and any issues raised thereby.
639     (d)  Receipt of an affirmative determination of need by the
640submittal deadline for agency reports under paragraph (a) shall
641be a condition precedent to further processing of the
642application.
643     (3)  The department shall prepare a project impact written
644analysis which contains a compilation of agency reports and
645summaries of the material contained therein which shall be filed
646with the administrative law judge and served on all parties no
647later than 90 135 days after the determination that the
648application is complete application has been distributed to the
649affected agencies, and which shall include:
650     (a)  The studies and reports required by this section and
651s. 403.537.
652     (b)  Comments received from any other agency or person.
653     (c)  The recommendation of the department as to the
654disposition of the application, of variances, exemptions,
655exceptions, or other relief identified by any party, and of any
656proposed conditions of certification which the department
657believes should be imposed.
658     (4)  The failure of any agency to submit a preliminary
659statement of issues or a report, or to submit its preliminary
660statement of issues or report within the allowed time, shall not
661be grounds for the alteration of any time limitation in this act
662pursuant to s. 403.528. Neither the failure to submit a
663preliminary statement of issues or a report nor the inadequacy
664of the preliminary statement of issues or report shall be
665grounds to deny or condition certification.
666     Section 11.  Section 403.527, Florida Statutes, is amended
667to read:
668     403.527  Certification hearing; Notice, proceedings,
669parties, participants.--
670     (1)(a)  No later than 15 days after an application has been
671determined complete, the applicant shall arrange for publication
672of a notice of the application and of the proceedings required
673by this act. Such notice shall give notice of the provisions of
674s. 403.531(1) and (2).
675     (b)  The applicant shall arrange for publication of a
676notice of the certification hearing and other public hearings
677provided for in this section and notice of the deadline for
678filing of notice of intent to be a party. Such notices shall be
679published at least 80 days before the date set for the hearing.
680     (c)  The applicant shall arrange for publication of a
681reminder notice in the newspapers specified in paragraph (d) no
682more than 10 days prior to the certification hearing, reminding
683the public of the date and location of the hearing. This notice
684shall not constitute a point of entry for intervention in the
685proceeding.
686     (d)  Notices to be published by the applicant shall be
687published in newspapers of general circulation within counties
688crossed by the transmission line corridors proper for
689certification. The required newspaper notices, other than the
690reminder notice, shall be one-half page in size in a standard
691size newspaper or a full page in a tabloid size newspaper and
692published in a section of the newspaper other than the legal
693notices section. These notices shall include a map generally
694depicting all transmission corridors proper for certification. A
695newspaper of general circulation shall be the newspaper within a
696county crossed by a transmission line corridor proper for
697certification which newspaper has the largest daily circulation
698in that county and has its principal office in that county. If
699the newspaper with the largest daily circulation has its
700principal office outside the county, then the notices shall
701appear in both the newspaper having the largest circulation in
702that county and in a newspaper authorized to publish legal
703notices in that county.
704     (e)  The department shall publish in the Florida
705Administrative Weekly notices of the application; of the
706certification hearing; of the hearing before the board; and of
707stipulations, proposed agency action, or petitions for
708modification.
709     (f)  The department shall adopt rules specifying the
710content of notices required by this section. All notices
711published by the applicant shall be paid for by the applicant
712and shall be in addition to the application fee.
713     (1)(a)(2)  No later than 125 185 days after the application
714has been determined complete receipt of a complete application
715by the department, the administrative law judge shall conduct a
716certification hearing pursuant to ss. 120.569 and 120.57 at a
717central location in proximity to the proposed transmission line
718or corridor.
719     (b)  One public hearing where members of the public who are
720not parties to the certification hearing may testify shall be
721held within the boundaries of each county, at the option of any
722local government.
723     1.  The local government shall notify the administrative
724law judge and all parties not later than 40 50 days after the
725application has been determined receipt of a complete
726application as to whether the local government wishes to have
727such a public hearing. The local government shall be responsible
728for determining the location of the public hearing.
729     2.  Within 5 days after of such notification, the
730administrative law judge shall determine the date of such public
731hearing, which shall be held before or during the certification
732hearing. In the event two or more local governments within one
733county request such a public hearing, the hearing shall be
734consolidated so that only one such public hearing is held in any
735county. The location of a consolidated hearing shall be
736determined by the administrative law judge.
737     3.  If a local government does not request a public hearing
738within 40 50 days after the application has been determined
739receipt of a complete application, persons residing within the
740jurisdiction of such local government may testify at the public
741hearing portion of the certification hearing.
742     (c)  The order of presentation at the certification
743hearing, unless otherwise changed by the administrative law
744judge to ensure the orderly presentation of witnesses and
745evidence, shall be:
746     1.  The applicant.
747     2.  The department.
748     3.  State agencies.
749     4.  Regional agencies, including regional planning councils
750and water management districts.
751     5.  Local governments.
752     6.  Other parties.
753     (d)  When appropriate, any person may be given an
754opportunity to present oral or written communications to the
755administrative law judge. If the administrative law judge
756proposes to consider such communications, all parties shall be
757given an opportunity to cross-examine, challenge, or rebut such
758communications.
759     (e)  The applicant shall pay those expenses and costs
760associated with the conduct of the hearings and the recording
761and transcription of the proceedings.
762     (2)  Notice of the certification hearing and other public
763hearings provided for in this section and notice of the deadline
764for filing of notice of intent to be a party shall be made in
765accordance with the requirements of s. 403.5363. Such notices
766shall be published at least 65 days before the date set for the
767certification hearing.
768     (3)(a)  At the conclusion of the certification hearing, the
769administrative law judge shall, after consideration of all
770evidence of record, issue a recommended order disposing of the
771application no later than 60 days after the transcript of the
772certification hearing and the public hearings is filed with the
773Division of Administrative Hearings.
774     (b)  In the event the administrative law judge fails to
775issue a recommended order within 60 days after the filing of the
776hearing transcript, the administrative law judge shall submit a
777report to the board with a copy to all parties within 60 days
778after the filing of the hearing transcript to advise the board
779of the reason for the delay in the issuance of the recommended
780order and of the date by which the recommended order will be
781issued.
782     (3)(4)(a)  Parties to the proceeding shall be:
783     1.  The applicant.
784     2.  The department.
785     3.  The commission.
786     4.  The Department of Community Affairs.
787     5.  The Fish and Wildlife Conservation Commission.
788     6.  The Department of Transportation.
789     7.6.  Each water management district in the jurisdiction of
790which the proposed transmission line or corridor is to be
791located.
792     8.7.  The local government.
793     9.8.  The regional planning council.
794     (b)  Any party listed in paragraph (a), other than the
795department or the applicant, may waive its right to participate
796in these proceedings. If any listed party fails to file a notice
797of its intent to be a party on or before the 30th day prior to
798the certification hearing, such party shall be deemed to have
799waived its right to be a party unless its participation would
800not prejudice the rights of any party to the proceeding.
801     (c)  Notwithstanding the provisions of chapter 120 to the
802contrary, upon the filing with the administrative law judge of a
803notice of intent to be a party by an agency or corporation or
804association described in subparagraphs 1. and 2. or a petition
805for intervention by a person described in subparagraph 3. no
806later than 30 days prior to the date set for the certification
807hearing, the following shall also be parties to the proceeding:
808     1.  Any agency not listed in paragraph (a) as to matters
809within its jurisdiction.
810     2.  Any domestic nonprofit corporation or association
811formed, in whole or in part, to promote conservation of natural
812beauty; to protect the environment, personal health, or other
813biological values; to preserve historical sites; to promote
814consumer interests; to represent labor, commercial, or
815industrial groups; or to promote comprehensive planning or
816orderly development of the area in which the proposed
817transmission line or corridor is to be located.
818     3.  Any person whose substantial interests are affected and
819being determined by the proceeding.
820     (d)  Any agency whose properties or works may be affected
821shall be made a party upon the request of the agency or any
822party to this proceeding.
823     (4)(a)  At the conclusion of the certification hearing, the
824administrative law judge shall, after consideration of all
825evidence of record, issue a recommended order disposing of the
826application no later than 45 days after the transcript of the
827certification hearing and the public hearings is filed with the
828Division of Administrative Hearings.
829     (b)  In the event the administrative law judge fails to
830issue a recommended order within 45 days after the filing of the
831hearing transcript, the administrative law judge shall submit a
832report to the siting board with a copy to all parties within 60
833days after the filing of the hearing transcript to advise the
834siting board of the reason for the delay in the issuance of the
835recommended order and of the date by which the recommended order
836will be issued.
837     (5)(a)  No later than 25 days prior to the conduct of the
838certification hearing, the department or the applicant may
839request that the administrative law judge cancel the
840certification hearing and relinquish jurisdiction to the
841department if all parties to the proceeding stipulate that there
842are no disputed issues of fact to be raised at the certification
843hearing.
844     (b)  The administrative law judge shall issue an order
845granting or denying the request within 5 days.
846     (c)  If the administrative law judge grants the request, no
847later than 7 days prior to the date of the originally scheduled
848certification hearing, the department and the applicant shall
849publish notices of the cancellation of the certification hearing
850in accordance with s. 403.5363.
851     (d)  If the administrative law judge grants the request,
852within 30 days after the administrative law judge's order
853relinquishing jurisdiction, the department shall prepare a
854recommended order, including proposed conditions of
855certification, for final action by the siting board. Parties may
856submit proposed recommended orders to the department no later
857than 10 days after the administrative law judge issues his or
858her order relinquishing jurisdiction.
859     (5)  When appropriate, any person may be given an
860opportunity to present oral or written communications to the
861administrative law judge. If the administrative law judge
862proposes to consider such communications, all parties shall be
863given an opportunity to cross-examine or challenge or rebut such
864communications.
865     (6)  The administrative law judge shall have all powers and
866duties granted to administrative law judges by chapter 120 and
867by the laws and rules of the department, including the authority
868to resolve disputes over the completeness or sufficiency of an
869application for certification.
870     (7)  The order of presentation at the certification
871hearing, unless otherwise changed by the administrative law
872judge to ensure the orderly presentation of witnesses and
873evidence, shall be:
874     (a)  The applicant.
875     (b)  The department.
876     (c)  State agencies.
877     (d)  Regional agencies, including regional planning
878councils and water management districts.
879     (e)  Local governments.
880     (f)  Other parties.
881     (8)  The applicant shall pay those expenses and costs
882associated with the conduct of the hearings and the recording
883and transcription of the proceedings.
884     Section 12.  Subsections (1) and (3) of section 403.5271,
885Florida Statutes, are amended to read:
886     403.5271  Alternate corridors.--
887     (1)  No later than 50 days prior to the originally
888scheduled certification hearing, any party may propose alternate
889transmission line corridor routes for consideration pursuant to
890the provisions of this act.
891     (a)  A notice of any such proposed alternate corridor shall
892be filed with the administrative law judge, all parties, and any
893local governments in whose jurisdiction the alternate corridor
894is proposed. Such filing shall include the most recent United
895States Geological Survey 1:24,000 quadrangle maps specifically
896delineating the corridor boundaries, a description of the
897proposed corridor, and a statement of the reasons the proposed
898alternate corridor should be certified.
899     (b)1.  Within 7 days after receipt of such notice, the
900applicant and the department shall file with the administrative
901law judge and all parties a notice of acceptance or rejection of
902a proposed alternate corridor for consideration. If the
903alternate corridor is rejected either by the applicant or the
904department, the certification hearing and the public hearings
905shall be held as scheduled. If both the applicant and the
906department accept a proposed alternate corridor for
907consideration, the certification hearing and the public hearings
908shall be rescheduled, if necessary.
909     2.  If rescheduled, the certification hearing shall be held
910no more than 100 90 days after the previously scheduled
911certification hearing, unless additional time is needed due to
912the alternate corridor crossing a local government jurisdiction
913not previously affected, in which case the remainder of the
914schedule listed below shall be appropriately adjusted by the
915administrative law judge to allow that local government to
916prepare a report pursuant to s. 403.526(2)(a)5.
917     (c)  Notice of the filing of the alternate, of the revised
918time schedules, of the deadline for newly affected persons and
919agencies to file notice of intent to become a party, of the
920rescheduled hearing date, and of the proceedings pursuant to s.
921403.527(1)(b) and (c) shall be published in accordance with the
922requirements of s. 403.5363 at least 65 days prior to the
923rescheduled hearing.
924     (d)  Within 21 25 days after acceptance of an alternate
925corridor by the department and the applicant, the party
926proposing an alternate corridor shall have the burden of
927providing all additional data to the agencies listed in s.
928403.526(2), and newly affected agencies, necessary for the
929preparation of a supplementary report on the proposed alternate
930corridor.
931     (e)1.  Reviewing agencies shall advise the department of
932their completeness issues no later than 12 days after the
933submittal of the data required by paragraph (d). If the
934department determines Within 15 days after receipt of such data,
935the department shall issue a determination of completeness.
936     2.  If the department determines that the this additional
937data required by paragraph (d) is not complete insufficient, the
938party proposing the alternate corridor shall file such
939additional data that corrects the incompleteness. This
940additional data must be submitted insufficiency within 15 days
941after the filing of the department's determination.
942     3.  If such additional information data is determined by
943the department within 15 days after receipt to be incomplete
944insufficient, such incompleteness insufficiency of data shall be
945deemed a withdrawal of the proposed alternate corridor. The
946party proposing an alternate corridor shall have the burden of
947proof on the certifiability of the alternate corridor at the
948certification hearing pursuant to s. 403.529(4). Nothing in this
949act shall be construed as requiring the applicant or agencies
950not proposing the alternate corridor to submit data in support
951of such alternate corridor.
952     (f)  The agencies listed in s. 403.526(2) and any newly
953affected agencies shall file supplementary reports with the
954applicant and department that address addressing the proposed
955alternate corridors no later than 30 60 days after the
956additional data is submitted pursuant to paragraph (d) (e) is
957determined to be complete.
958     (g)  The agency reports on alternate corridors shall
959include all information required by s. 403.526(2) agencies shall
960submit supplementary notice pursuant to s. 403.531(2) at the
961time of filing of their supplemental report.
962     (h)  The department shall file with the administrative law
963judge, the applicant, and all parties a project impact prepare a
964written analysis consistent with s. 403.526(3) at least 29 days
965prior to the rescheduled certification hearing addressing the
966proposed alternate corridor.
967     (3)(a)  Notwithstanding the rejection of a proposed
968alternate corridor by the applicant or the department, any party
969may present evidence at the certification hearing to show that a
970corridor proper for certification does not satisfy the criteria
971listed in s. 403.529 or that a rejected alternate corridor would
972meet the criteria set forth in s. 403.529. No evidence shall be
973admitted at the certification hearing on any alternate corridor,
974unless the alternate corridor was proposed by the filing of a
975notice at least 50 days prior to the originally scheduled
976certification hearing pursuant to this section. Rejected
977alternate corridors shall be considered by the board as provided
978in s. 403.529(4) and (5).
979     (b)  The party proposing an alternate corridor shall have
980the burden of proof on the certifiability of the alternate
981corridor at the certification hearing pursuant to s. 403.529(4).
982Nothing in this act shall be construed as requiring the
983applicant or agencies not proposing the alternate corridor to
984submit data in support of such alternate corridor.
985     Section 13.  Section 403.5272, Florida Statutes, is amended
986to read:
987     403.5272  Local governments; Informational public
988meetings.--
989     (1)  Local governments or regional planning councils may
990hold informational public meetings in addition to the hearings
991specifically authorized by this act on any matter associated
992with the transmission line proceeding. Such informational public
993meetings should be held no later than 30 80 days after the
994application has been determined complete is filed. The purpose
995of an informational public meeting is for the local government
996or regional planning council to further inform the general
997public about the transmission line proposed, obtain comments
998from the public, and formulate its recommendation with respect
999to the proposed transmission line.
1000     (2)  Informational public meetings shall be held solely at
1001the option of each local government or regional planning
1002council. It is the legislative intent that local governments or
1003regional planning councils attempt to hold such public meetings.
1004Parties to the proceedings under this act shall be encouraged to
1005attend; however, no party other than the applicant and the
1006department shall be required to attend such informational public
1007hearings.
1008     (3)  The failure to hold an informational public meeting or
1009the procedure used for the informational public meeting shall
1010not be grounds for the alteration of any time limitation in this
1011act pursuant to s. 403.528 or grounds to deny or condition
1012certification.
1013     Section 14.  Subsection (1) of section 403.5275, Florida
1014Statutes, is amended to read:
1015     403.5275  Amendment to the application.--
1016     (1)  Any amendment made to the application prior to
1017certification shall be sent by the applicant to the
1018administrative law judge and to all parties to the proceeding.
1019     Section 15.  Subsections (1) and (2) and paragraph (e) of
1020subsection (4) of section 403.529, Florida Statutes, are amended
1021to read:
1022     403.529  Final disposition of application.--
1023     (1)  Within 30 days after receipt of the administrative law
1024judge's or the department?s recommended order, the board shall
1025act upon the application by written order, approving in whole,
1026approving with such conditions as the board deems appropriate,
1027or denying the certification and stating the reasons for
1028issuance or denial.
1029     (2)  The issues that may be raised in any hearing before
1030the board shall be limited to matters raised in the
1031certification proceeding before the administrative law judge or
1032raised in the administrative law judge?s or department?s
1033recommended order. All parties, or their representatives, or
1034persons who appear before the board shall be subject to the
1035provisions of s. 120.66.
1036     (4)  In determining whether an application should be
1037approved in whole, approved with modifications or conditions, or
1038denied, the board shall consider whether, and the extent to
1039which, the location of the transmission line corridor and the
1040construction and maintenance of the transmission line will:
1041     (e)  Effect a reasonable balance between the need for the
1042transmission line as a means of providing reliable, economically
1043efficient electric abundant low-cost electrical energy and the
1044impact upon the public and the environment resulting from the
1045location of the transmission line corridor and maintenance of
1046the transmission lines.
1047     Section 16.  Subsections (2) and (3) of section 403.531,
1048Florida Statutes, are amended to read:
1049     403.531  Effect of certification.--
1050     (2)(a)  The certification shall authorize the licensee
1051applicant to locate the transmission line corridor and to
1052construct and maintain the transmission lines subject only to
1053the conditions of certification set forth in such certification.
1054     (b)  The certification may include conditions which
1055constitute variances and exemptions from nonprocedural standards
1056or regulations of the department or any other agency, which were
1057expressly considered during the certification review proceeding
1058unless waived by the agency as provided s. 403.526 below and
1059which otherwise would be applicable to the location of the
1060proposed transmission line corridor or the construction and
1061maintenance of the transmission lines. Each party shall notify
1062the applicant and other parties at the time scheduled for the
1063filing of the agency reports of any nonprocedural requirements
1064not specifically listed in the application from which a
1065variance, exemption, exception, or other relief is necessary in
1066order for the board to certify any corridor proposed for
1067certification. Failure of such notification shall be treated as
1068a waiver from the nonprocedural requirements of that agency.
1069     (3)(a)  The certification shall be in lieu of any license,
1070permit, certificate, or similar document required by any agency
1071pursuant to, but not limited to, chapter 125, chapter 161,
1072chapter 163, chapter 166, chapter 186, chapter 253, chapter 258,
1073chapter 298, chapter 370, chapter 373, chapter 376, chapter 380,
1074chapter 381, chapter 387, chapter 403, chapter 404, or the
1075Florida Transportation Code, or 33 U.S.C. s. 1341.
1076     (b)  On certification, any license, easement, or other
1077interest in state lands, except those the title of which is
1078vested in the Board of Trustees of the Internal Improvement
1079Trust Fund, shall be issued by the appropriate agency as a
1080ministerial act. The applicant shall be required to seek any
1081necessary interest in state lands the title to which is vested
1082in the Board of Trustees of the Internal Improvement Trust Fund
1083from the board of trustees before, during, or after the
1084certification proceeding, and certification may be made
1085contingent upon issuance of the appropriate interest in realty.
1086However, neither the applicant nor any party to the
1087certification proceeding may directly or indirectly raise or
1088relitigate any matter which was or could have been an issue in
1089the certification proceeding in any proceeding before the Board
1090of Trustees of the Internal Improvement Trust Fund wherein the
1091applicant is seeking a necessary interest in state lands, but
1092the information presented in the certification proceeding shall
1093be available for review by the board of trustees and its staff.
1094     Section 17.  Section 403.5312, Florida Statutes, is amended
1095to read:
1096     403.5312  Filing Recording of notice of certified corridor
1097route.--
1098     (1)  Within 60 days after certification of a directly
1099associated transmission line pursuant to ss. 403.501-403.518 or
1100a transmission line corridor pursuant to ss. 403.52-403.5365,
1101the applicant shall file, in accordance with s. 28.222, with the
1102department and the clerk of the circuit court for each county
1103through which the corridor will pass, a notice of the certified
1104route.
1105     (2)  The notice shall consist of maps or aerial photographs
1106in the scale of 1:24,000 which clearly show the location of the
1107certified route and shall state that the certification of the
1108corridor will result in the acquisition of rights-of-way within
1109the corridor. Each clerk shall record the filing in the official
1110record of the county for the duration of the certification or
1111until such time as the applicant certifies to the department and
1112the clerk that all lands required for the transmission line
1113rights-of-way within the corridor have been acquired within such
1114county, whichever is sooner.
1115     (3)  The recording of this notice shall not constitute a
1116lien, cloud, or encumbrance on real property.
1117     Section 18.  Section 403.5317, Florida Statutes, is created
1118to read:
1119     403.5317  Postcertification amendments.--
1120     (1)  If, subsequent to certification by the board, a
1121licensee proposes any material change to the application, and
1122revisions or amendments thereto, as certified, the licensee
1123shall submit to the department a written request for amendment
1124and description of the proposed change to the application. The
1125department shall, within 30 days after the receipt of the
1126request for the amendment, determine whether the proposed change
1127to the application requires a modification of the conditions of
1128certification.
1129     (2)  If the department concludes that the change would not
1130require a modification of the conditions of certification, the
1131department shall notify, in writing, the licensee, all agencies,
1132and all parties of the approval of the proposed amendment.
1133     (3)  If the department concludes that the change would
1134require a modification of the conditions of certification, the
1135department shall notify the licensee that the proposed change to
1136the application requires a request for modification pursuant to
1137s. 403.5315.
1138     Section 19.  Section 403.5363, Florida Statutes, is created
1139to read:
1140     403.5363  Public notices, requirements.--
1141     (1)(a)  The applicant shall arrange for the publication of
1142the following notices. Such notices shall be published in
1143newspapers of general circulation within counties crossed by the
1144transmission line corridors proper for certification:
1145     1.  Notice of the submittal of the application, which shall
1146include a description of the proceedings required by this act.
1147Such notice shall give notice of the provisions of s. 403.531(1)
1148and (2) and the notice of the deadline for filing of notice of
1149intent to be a party.
1150     2.  Notice of the certification hearing.
1151     3.  Notice of the cancellation of the certification
1152hearing, if applicable.
1153     4.  Notice of filing of a modification proposal submitted
1154pursuant to s. 403.5315, if the department determines that the
1155modification would require relocation or expansion of the
1156transmission line right-of-way or a certified substation.
1157     (b)  The proponent of an alternate corridor shall arrange
1158for the publication of the filing of the alternate, of the
1159revised time schedules, of the deadline for newly affected
1160persons and agencies to file notice of intent to become a party,
1161and of the rescheduled hearing dates. Such notices shall be
1162published in newspapers of general circulation within counties
1163crossed by the proposed alternate corridor.
1164     (c)  The department shall arrange for publication of the
1165following notices in the manner specified by chapter 120:
1166     1.  Notice of the submittal of the application and the
1167deadline to become a party.
1168     2.  Notice of any administrative hearings on certification.
1169     3.  Notice of the cancellation of the certification
1170hearings, if applicable.
1171     4.  Notice of the hearing before the siting board.
1172     5.  Notice of stipulations, proposed agency action, or
1173petitions for modification.
1174     (2)  The department shall adopt rules specifying the
1175content of notices required by this section. All notices
1176published by the applicant shall be paid for by the applicant
1177and shall be in addition to the application fee.
1178     Section 20.  Section 403.5365, Florida Statutes, is amended
1179to read:
1180     403.5365  Fees; disposition.--The department shall charge
1181the applicant the following fees, as appropriate, which, unless
1182otherwise specified, shall be paid into the Florida Permit Fee
1183Trust Fund:
1184     (1)  An application fee of $150,000 $100,000, plus $750 per
1185mile for each mile of corridor in which the transmission line
1186right-of-way is proposed to be located within an existing
1187electric electrical transmission line right-of-way or within any
1188existing right-of-way for any road, highway, railroad, or other
1189aboveground linear facility, or $1,000 per mile for each mile of
1190electric transmission line corridor proposed to be located
1191outside such existing right-of-way.
1192     (a)  Fifty Sixty percent of the fee shall go to the
1193department to cover any costs associated with coordinating the
1194review of reviewing and acting upon the application and any
1195costs for field services associated with monitoring construction
1196and operation of the electric transmission line facility.
1197     (b)  The following sums Twenty percent of the fees
1198specified under this section, except postcertification fees,
1199shall be transferred to the Administrative Trust Fund of the
1200Division of Administrative Hearings of the Department of
1201Management Services:
1202     1.  Five percent to compensate for expenses from the
1203initial exercise of duties associated with the filing of an
1204application.
1205     2.  An additional 10 percent if an administrative hearing
1206pursuant to s. 403.527 is held.
1207     (c)  Upon written request with proper itemized accounting
1208within 90 days after final agency action by the board or
1209withdrawal of the application, the agencies that prepared
1210reports pursuant to s. 403.526 or s. 403.5271 or participated in
1211a hearing pursuant to s. 403.527 or s. 403.5271 may submit a
1212written request to the department for reimbursement of expenses
1213incurred during the certification proceedings. The request shall
1214contain an accounting of expenses incurred, which may include
1215time spent reviewing the application, department shall reimburse
1216the expenses and costs of the Department of Community Affairs,
1217the Fish and Wildlife Conservation Commission, the water
1218management district, regional planning council, and local
1219government in the jurisdiction of which the transmission line is
1220to be located. Such reimbursement shall be authorized for the
1221preparation of any studies required of the agencies by this act,
1222and for agency travel and per diem to attend any hearing held
1223pursuant to this act, and for the local government's or regional
1224planning council's provision of additional notice of the
1225informational public meetings government to participate in the
1226proceedings. The department shall review the request and verify
1227that the expenses are valid. Valid expenses shall be reimbursed;
1228however, in the event the amount of funds available for
1229reimbursement allocation is insufficient to provide for full
1230compensation complete reimbursement to the agencies requesting
1231reimbursement, reimbursement shall be on a prorated basis.
1232     (d)  If any sums are remaining, the department shall retain
1233them for its use in the same manner as is otherwise authorized
1234by this section; provided, however, that if the certification
1235application is withdrawn prior to the initial determination on
1236completeness, one-half of the application fee the remaining sums
1237shall be refunded to the applicant within 90 days after
1238withdrawal.
1239     (2)  An amendment fee.
1240     (a)  If no corridor alignment change is proposed by the
1241amendment, no amendment fee shall be charged.
1242     (b)  If a corridor alignment change pursuant to s.
1243403.5275(2) is proposed by the applicant, an additional fee of a
1244minimum of $2,000 and $750 per mile shall be submitted to the
1245department for use in accordance with this act.
1246     (c)  If an amendment is required to address issues,
1247including alternate corridors pursuant to s. 403.5271, raised by
1248the department or other parties, no fee for such amendment shall
1249be charged.
1250     (3)  A certification modification fee.
1251     (a)  If no corridor alignment change is proposed by the
1252licensee applicant, the modification fee shall be $4,000.
1253     (b)  If a corridor alignment change is proposed by the
1254licensee applicant, the fee shall be $1,000 for each mile of
1255realignment plus an amount not to exceed $10,000 to be fixed by
1256rule on a sliding scale based on the load-carrying capability
1257and configuration of the transmission line for use in accordance
1258with subsection (2).
1259     Section 21.  Section 403.5369, Florida Statutes, is
1260repealed.
1261     Section 22.  Paragraphs (a) and (c) of subsection (1) of
1262section 403.537, Florida Statutes, are amended to read:
1263     403.537  Determination of need for transmission line;
1264powers and duties.--
1265     (1)(a)  Upon request by an applicant or upon its own
1266motion, the Florida Public Service Commission shall schedule a
1267public hearing, after notice, to determine the need for a
1268transmission line regulated by the Florida Electric Transmission
1269Line Siting Act, ss. 403.52-403.5365. Such notice shall be
1270published at least 21 45 days before the date set for the
1271hearing and shall be published in at least one-quarter page size
1272notice in newspapers of general circulation, in the Florida
1273Administrative Weekly, by giving notice to counties and regional
1274planning councils in whose jurisdiction the transmission line
1275could be placed, and by giving notice to any persons who have
1276requested to be placed on the mailing list of the commission for
1277this purpose. Within 21 days after receipt of a request for
1278determination by an applicant, the commission shall set a date
1279for the hearing. The hearing shall be held pursuant to s. 350.01
1280within 45 days after the filing of the request, and a decision
1281shall be rendered within 60 days after such filing.
1282     (c)  The determination by the commission of the need for
1283the transmission line, as defined in s. 403.522(21), is binding
1284on all parties to any certification proceeding pursuant to the
1285Florida Electric Transmission Line Siting Act and is a condition
1286precedent to the conduct of the certification hearing prescribed
1287therein. An order entered pursuant to this section constitutes
1288final agency action.
1289     Section 23.  Subsection (3) of section 373.441, Florida
1290Statutes, is amended to read:
1291     373.441  Role of counties, municipalities, and local
1292pollution control programs in permit processing.--
1293     (3)  The department shall review environmental resource
1294permit applications for electrical distribution and transmission
1295lines and other facilities related to the production,
1296transmission, and distribution of electricity which are not
1297certified under ss. 403.52-403.5365, the Florida Electric
1298Transmission Line Siting Act, regulated under this part.
1299     Section 24.  Subsection (30) of section 403.061, Florida
1300Statutes, is amended to read:
1301     403.061  Department; powers and duties.--The department
1302shall have the power and the duty to control and prohibit
1303pollution of air and water in accordance with the law and rules
1304adopted and promulgated by it and, for this purpose, to:
1305     (30)  Establish requirements by rule that reasonably
1306protect the public health and welfare from electric and magnetic
1307fields associated with existing 230 kV or greater electrical
1308transmission lines, new 230 kV and greater electrical
1309transmission lines for which an application for certification
1310under the Florida Electric Transmission Line Siting Act, ss.
1311403.52-403.5365, is not filed, new or existing electrical
1312transmission or distribution lines with voltage less than 230
1313kV, and substation facilities. Notwithstanding any other
1314provision in this chapter or any other law of this state or
1315political subdivision thereof, the department shall have
1316exclusive jurisdiction in the regulation of electric and
1317magnetic fields associated with all electrical transmission and
1318distribution lines and substation facilities. However, nothing
1319herein shall be construed as superseding or repealing the
1320provisions of s. 403.523(1) and (10).
1321
1322The department shall implement such programs in conjunction with
1323its other powers and duties and shall place special emphasis on
1324reducing and eliminating contamination that presents a threat to
1325humans, animals or plants, or to the environment.
1326     Section 25.  Paragraph (a) of subsection (3) of section
1327403.0876, Florida Statutes, is amended to read:
1328     403.0876  Permits; processing.--
1329     (3)(a)  The department shall establish a special unit for
1330permit coordination and processing to provide expeditious
1331processing of department permits which the district offices are
1332unable to process expeditiously and to provide accelerated
1333processing of certain permits or renewals for economic and
1334operating stability. The ability of the department to process
1335applications pursuant to this subsection in a more timely manner
1336than allowed by subsections (1) and (2) is dependent upon the
1337timely exchange of information between the applicant and the
1338department and the intervention of outside parties as allowed by
1339law. An applicant may request the processing of its permit
1340application by the special unit if the application is from an
1341area of high unemployment or low per capita income, is from a
1342business or industry that is the primary employer within an
1343area's labor market, or is in an industry with respect to which
1344the complexities involved in the review of the application
1345require special skills uniquely available in the headquarters
1346office. The department may require the applicant to waive the
134790-day time limitation for department issuance or denial of the
1348permit once for a period not to exceed 90 days. The department
1349may require a special fee to cover the direct cost of processing
1350special applications in addition to normal permit fees and
1351costs. The special fee may not exceed $10,000 per permit
1352required. Applications for renewal permits, but not applications
1353for initial permits, required for facilities pursuant to the
1354Electrical Power Plant Siting Act or the Florida Electric
1355Transmission Line Siting Act may be processed under this
1356subsection. Personnel staffing the special unit shall have
1357lengthy experience in permit processing.
1358     Section 26.  Paragraph (b) of subsection (3) of section
1359403.809, Florida Statutes, is amended to read:
1360     403.809  Environmental districts; establishment; managers;
1361functions.--
1362     (3)
1363     (b)  The processing of all applications for permits,
1364licenses, certificates, and exemptions shall be accomplished at
1365the district center or the branch office, except for those
1366applications specifically assigned elsewhere in the department
1367under s. 403.805 or to the water management districts under s.
1368403.812 and those applications assigned by interagency agreement
1369as provided in this act. However, the secretary, as head of the
1370department, may not delegate to district or subdistrict
1371managers, water management districts, or any unit of local
1372government the authority to act on the following types of permit
1373applications:
1374     1.  Permits issued under s. 403.0885, except such permit
1375issuance may be delegated to district managers.
1376     2.  Construction of major air pollution sources.
1377     3.  Certifications under the Florida Electrical Power Plant
1378Siting Act or the Florida Electric Transmission Line Siting Act
1379and the associated permit issued under s. 403.0885, if
1380applicable.
1381     4.  Permits issued under s. 403.0885 to steam electric
1382generating facilities regulated pursuant to 40 C.F.R. part 423.
1383     5.  Permits issued under s. 378.901.
1384     Section 27.  This act shall take effect upon becoming a
1385law.


CODING: Words stricken are deletions; words underlined are additions.