1 | A bill to be entitled |
2 | An act relating to prompt payment for construction |
3 | services; amending s. 218.70, F.S.; providing a popular |
4 | name; amending s. 218.72, F.S.; redefining terms used in |
5 | pt. VII of ch. 218, F.S.; amending s. 218.735, F.S.; |
6 | revising provisions relating to timely payment for |
7 | purchases of construction services; revising deadlines for |
8 | payment; providing procedures for project closeout and |
9 | payment of retainage; providing requirements for local |
10 | government construction retainage; providing exceptions; |
11 | creating s. 255.0705, F.S.; providing a popular name; |
12 | amending s. 255.071, F.S.; revising deadlines for the |
13 | payment of subcontractors, sub-subcontractors, |
14 | materialmen, and suppliers on construction contracts for |
15 | public projects; creating ss. 255.072, 255.073, 255.074, |
16 | 255.075, 255.076, 255.077, and 255.078, F.S.; providing |
17 | definitions; providing for timely payment for purchases of |
18 | construction services by a public entity; providing |
19 | procedures for calculating payment due dates; authorizing |
20 | the collection of interest under certain circumstances; |
21 | providing for an award of court costs and attorney's fees; |
22 | providing for project closeout and payment of retainage; |
23 | providing exceptions; amending s. 255.05, F.S.; providing |
24 | requirements for certain notices of nonpayment served by a |
25 | claimant who is not in privity with the contractor; |
26 | providing limitations on a claimant's institution of |
27 | certain actions against a contractor or surety; amending |
28 | s. 287.0585, F.S.; providing an exemption for contractors |
29 | making late payment to subcontractors when the contract is |
30 | subject to the "Prompt Payment Act"; amending s. 95.11, |
31 | F.S., to conform a cross reference; providing that |
32 | specified sections of the act do not apply to certain |
33 | pending contracts and projects; providing an effective |
34 | date. |
35 |
|
36 | Be It Enacted by the Legislature of the State of Florida: |
37 |
|
38 | Section 1. Section 218.70, Florida Statutes, is amended to |
39 | read: |
40 | 218.70 Popular name Short title.--This part may be cited |
41 | as the "Local Government Florida Prompt Payment Act." |
42 | Section 2. Subsections (2), (6), and (7) of section |
43 | 218.72, Florida Statutes, are amended, and subsection (10) is |
44 | added to said section, to read: |
45 | 218.72 Definitions.--As used in this part: |
46 | (2) "Local governmental entity" means a county or |
47 | municipal government, school board, school district, authority, |
48 | special taxing district, other political subdivision, or any |
49 | office, board, bureau, commission, department, branch, division, |
50 | or institution thereof or any project supported by county or |
51 | municipal funds. |
52 | (6) "Vendor" means any person who sells goods or services, |
53 | sells or leases personal property, or leases real property |
54 | directly to a local governmental entity. The term includes any |
55 | person who provides waste-hauling services to residents or |
56 | businesses located within the boundaries of a local government |
57 | pursuant to a contract or local ordinance. |
58 | (7) "Construction services" means all labor, services, and |
59 | materials provided in connection with the construction, |
60 | alteration, repair, demolition, reconstruction, or any other |
61 | improvements to real property that require a license under parts |
62 | I and II of chapter 489. |
63 | (10) "Contractor" or "provider of construction services" |
64 | means any person who contracts directly with a local |
65 | governmental entity to provide construction services. |
66 | Section 3. Subsection (6) of section 218.735, Florida |
67 | Statutes, is amended, present subsection (7) of said section is |
68 | redesignated as subsection (9), and new subsections (7) and (8) |
69 | are added to said section, to read: |
70 | 218.735 Timely payment for purchases of construction |
71 | services.-- |
72 | (6) When a contractor receives payment from a local |
73 | governmental entity for labor, services, or materials furnished |
74 | by subcontractors and suppliers hired by the contractor, the |
75 | contractor shall remit payment due to those subcontractors and |
76 | suppliers within 10 15 days after the contractor's receipt of |
77 | payment. When a subcontractor receives payment from a contractor |
78 | for labor, services, or materials furnished by subcontractors |
79 | and suppliers hired by the subcontractor, the subcontractor |
80 | shall remit payment due to those subcontractors and suppliers |
81 | within 7 15 days after the subcontractor's receipt of payment. |
82 | Nothing herein shall prohibit a contractor or subcontractor from |
83 | disputing, pursuant to the terms of the relevant contract, all |
84 | or any portion of a payment alleged to be due to another party. |
85 | In the event of such a dispute, the contractor or subcontractor |
86 | may withhold the disputed portion of any such payment if the |
87 | contractor or subcontractor notifies the party whose payment is |
88 | disputed, in writing, of the amount in dispute and the actions |
89 | required to cure the dispute. The contractor or subcontractor |
90 | must pay all undisputed amounts due within the time limits |
91 | imposed by this section. |
92 | (7)(a) Each contract for construction services between a |
93 | local governmental entity and a contractor must provide for the |
94 | development of a list of items required to render complete, |
95 | satisfactory, and acceptable the construction services purchased |
96 | by the local governmental entity. The contract must specify the |
97 | process for the development of the list, including |
98 | responsibilities of the local governmental entity and the |
99 | contractor in developing and reviewing the list and a reasonable |
100 | time for developing the list, as follows: |
101 | 1. For construction projects having an estimated cost of |
102 | less than $10 million, within 30 calendar days after reaching |
103 | substantial completion of the construction services purchased as |
104 | defined in the contract, or, if not defined in the contract, |
105 | upon reaching beneficial occupancy or use; or |
106 | 2. For construction projects having an estimated cost of |
107 | $10 million or more, within 30 calendar days, unless otherwise |
108 | extended by contract not to exceed 60 calendar days, after |
109 | reaching substantial completion of the construction services |
110 | purchased as defined in the contract, or, if not defined in the |
111 | contract, upon reaching beneficial occupancy or use. |
112 | (b) If the contract between the local governmental entity |
113 | and the contractor relates to the purchase of construction |
114 | services on more than one building or structure, or involves a |
115 | multiphased project, the contract must provide for the |
116 | development of a list of items required to render complete, |
117 | satisfactory, and acceptable all the construction services |
118 | purchased pursuant to the contract for each building, structure, |
119 | or phase of the project within the time limitations provided in |
120 | paragraph (a). |
121 | (c) The failure to include any corrective work or pending |
122 | items not yet completed on the list developed pursuant to this |
123 | subsection does not alter the responsibility of the contractor |
124 | to complete all the construction services purchased pursuant to |
125 | the contract. |
126 | (d) Upon completion of all items on the list, the |
127 | contractor may submit a payment request for all remaining |
128 | retainage withheld by the local governmental entity pursuant to |
129 | this section. If a good-faith dispute exists as to whether one |
130 | or more items identified on the list have been completed |
131 | pursuant to the contract, the local governmental entity may |
132 | continue to withhold an amount not to exceed 150 percent of the |
133 | total costs to complete such items. |
134 | (e) All items that require correction under the contract |
135 | and that are identified after the preparation and delivery of |
136 | the list remain the obligation of the contractor as defined by |
137 | the contract. |
138 | (f) Warranty items may not affect the final payment of |
139 | retainage as provided in this section or as provided in the |
140 | contract between the contractor and its subcontractors and |
141 | suppliers. |
142 | (g) Retainage may not be held by a local governmental |
143 | entity or a contractor to secure payment of insurance premiums |
144 | under a consolidated insurance program or series of insurance |
145 | policies issued to a local governmental entity or a contractor |
146 | for a project or group of projects, and the final payment of |
147 | retainage as provided in this section may not be delayed pending |
148 | a final audit by the local governmental entity's or contractor's |
149 | insurance provider. |
150 | (h) If a local governmental entity fails to comply with |
151 | its responsibilities to develop the list required under |
152 | paragraph (a) or paragraph (b), as defined in the contract, |
153 | within the time limitations provided in paragraph (a), the |
154 | contractor may submit a payment request for all remaining |
155 | retainage withheld by the local governmental entity pursuant to |
156 | this section. The local governmental entity need not pay or |
157 | process any payment request for retainage if the contractor has, |
158 | in whole or in part, failed to cooperate with the local |
159 | governmental entity in the development of the list or failed to |
160 | perform its contractual responsibilities, if any, with regard to |
161 | the development of the list or if paragraph (8)(f) applies. |
162 | (8)(a) With regard to any contract for construction |
163 | services, a local governmental entity may withhold from each |
164 | progress payment made to the contractor an amount not exceeding |
165 | 10 percent of the payment as retainage until 50-percent |
166 | completion of such services. |
167 | (b) After 50-percent completion of the construction |
168 | services purchased pursuant to the contract, the local |
169 | governmental entity must reduce to 5 percent the amount of |
170 | retainage withheld from each subsequent progress payment made to |
171 | the contractor. For purposes of this subsection, the term "50- |
172 | percent completion" has the meaning set forth in the contract |
173 | between the local governmental entity and the contractor or, if |
174 | not defined in the contract, the point at which the local |
175 | governmental entity has expended 50 percent of the total cost of |
176 | the construction services purchased as identified in the |
177 | contract together with all costs associated with existing change |
178 | orders and other additions or modifications to the construction |
179 | services provided for in the contract. However, notwithstanding |
180 | this subsection, a municipality having a population of 25,000 or |
181 | fewer, or a county having a population of 100,000 or fewer, may |
182 | withhold retainage in an amount not exceeding 10 percent of each |
183 | progress payment made to the contractor until final completion |
184 | and acceptance of the project by the local governmental entity. |
185 | (c) After 50-percent completion of the construction |
186 | services purchased pursuant to the contract, the contractor may |
187 | elect to withhold retainage from payments to its subcontractors |
188 | at a rate higher than 5 percent. The specific amount to be |
189 | withheld must be determined on a case-by-case basis and must be |
190 | based on the contractor's assessment of the subcontractor's past |
191 | performance, the likelihood that such performance will continue, |
192 | and the contractor's ability to rely on other safeguards. The |
193 | contractor shall notify the subcontractor, in writing, of its |
194 | determination to withhold more than 5 percent of the progress |
195 | payment and the reasons for making that determination, and the |
196 | contractor may not request the release of such retained funds |
197 | from the local governmental entity. |
198 | (d) After 50-percent completion of the construction |
199 | services purchased pursuant to the contract, the contractor may |
200 | present to the local governmental entity a payment request for |
201 | up to one-half of the retainage held by the local governmental |
202 | entity. The local governmental entity shall promptly make |
203 | payment to the contractor, unless the local governmental entity |
204 | has grounds, pursuant to paragraph (f), for withholding the |
205 | payment of retainage. If the local governmental entity makes |
206 | payment of retainage to the contractor under this paragraph |
207 | which is attributable to the labor, services, or materials |
208 | supplied by one or more subcontractors or suppliers, the |
209 | contractor shall timely remit payment of such retainage to those |
210 | subcontractors and suppliers. |
211 | (e) This section does not prohibit a local governmental |
212 | entity from withholding retainage at a rate less than 10 percent |
213 | of each progress payment, from incrementally reducing the rate |
214 | of retainage pursuant to a schedule provided for in the |
215 | contract, or from releasing at any point all or a portion of any |
216 | retainage withheld by the local governmental entity which is |
217 | attributable to the labor, services, or materials supplied by |
218 | the contractor or by one or more subcontractors or suppliers. If |
219 | a local governmental entity makes any payment of retainage to |
220 | the contractor which is attributable to the labor, services, or |
221 | materials supplied by one or more subcontractors or suppliers, |
222 | the contractor shall timely remit payment of such retainage to |
223 | those subcontractors and suppliers. |
224 | (f) This section does not require the local governmental |
225 | entity to pay or release any amounts that are the subject of a |
226 | good-faith dispute, the subject of a claim brought pursuant to |
227 | s. 255.05, or otherwise the subject of a claim or demand by the |
228 | local governmental entity or contractor. |
229 | (g) The time limitations set forth in this section for |
230 | payment of payment requests apply to any payment request for |
231 | retainage made pursuant to this section. |
232 | (h) Paragraphs (a)-(d) do not apply to construction |
233 | services purchased by a local governmental entity which are paid |
234 | for, in whole or in part, with federal funds and are subject to |
235 | federal grantor laws and regulations or requirements that are |
236 | contrary to any provision of the Local Government Prompt Payment |
237 | Act. |
238 | (i) This subsection does not apply to any construction |
239 | services purchased by a local governmental entity if the total |
240 | cost of the construction services purchased as identified in the |
241 | contract is $200,000 or less. |
242 | Section 4. Section 255.0705, Florida Statutes, is created |
243 | to read: |
244 | 255.0705 Popular name.--Sections 255.0705-255.078 may be |
245 | cited as the "Florida Prompt Payment Act." |
246 | Section 5. Subsections (2) and (3) of section 255.071, |
247 | Florida Statutes, are amended to read: |
248 | 255.071 Payment of subcontractors, sub-subcontractors, |
249 | materialmen, and suppliers on construction contracts for public |
250 | projects.-- |
251 | (2) The failure to pay any undisputed obligations for such |
252 | labor, services, or materials within 30 days after the date the |
253 | labor, services, or materials were furnished and payment for |
254 | such labor, services, or materials became due, or within the |
255 | time limitations set forth in s. 255.073(3) 30 days after the |
256 | date payment for such labor, services, or materials is received, |
257 | whichever last occurs, shall entitle any person providing such |
258 | labor, services, or materials to the procedures specified in |
259 | subsection (3) and the remedies provided in subsection (4). |
260 | (3) Any person providing labor, services, or materials for |
261 | the construction of a public building, for the prosecution and |
262 | completion of a public work, or for repairs upon a public |
263 | building or public work improvements to real property may file a |
264 | verified complaint alleging: |
265 | (a) The existence of a contract for providing such labor, |
266 | services, or materials to improve real property. |
267 | (b) A description of the labor, services, or materials |
268 | provided and alleging that the labor, services, or materials |
269 | were provided in accordance with the contract. |
270 | (c) The amount of the contract price. |
271 | (d) The amount, if any, paid pursuant to the contract. |
272 | (e) The amount that remains unpaid pursuant to the |
273 | contract and the amount thereof that is undisputed. |
274 | (f) That the undisputed amount has remained due and |
275 | payable pursuant to the contract for more than 30 days after the |
276 | date the labor or services were accepted or the materials were |
277 | received. |
278 | (g) That the person against whom the complaint was filed |
279 | has received payment on account of the labor, services, or |
280 | materials described in the complaint and, as of the date the |
281 | complaint was filed, has failed to make payment within the time |
282 | limitations set forth in s. 255.073(3) more than 30 days prior |
283 | to the date the complaint was filed. |
284 | Section 6. Section 255.072, Florida Statutes, is created |
285 | to read: |
286 | 255.072 Definitions.--As used in ss. 255.073-255.078, the |
287 | term: |
288 | (1) "Agent" means project architect, project engineer, or |
289 | any other agency or person acting on behalf of a public entity. |
290 | (2) "Construction services" means all labor, services, and |
291 | materials provided in connection with the construction, |
292 | alteration, repair, demolition, reconstruction, or any other |
293 | improvements to real property. The term "construction services" |
294 | does not include contracts or work performed for the Department |
295 | of Transportation. |
296 | (3) "Contractor" means any person who contracts directly |
297 | with a public entity to provide construction services. |
298 | (4) "Payment request" means a request for payment for |
299 | construction services which conforms with all statutory |
300 | requirements and with all requirements specified by the public |
301 | entity to which the payment request is submitted. |
302 | (5) "Public entity" means the state, or any office, board, |
303 | bureau, commission, department, branch, division, or institution |
304 | thereof, but does not include a local governmental entity as |
305 | defined in s. 218.72. |
306 | (6) "Purchase" means the purchase of construction |
307 | services. |
308 | Section 7. Section 255.073, Florida Statutes, is created |
309 | to read: |
310 | 255.073 Timely payment for purchases of construction |
311 | services.-- |
312 | (1) Except as otherwise provided in ss. 255.072-255.078, |
313 | s. 215.422 governs the timely payment for construction services |
314 | by a public entity. |
315 | (2) If a public entity disputes a portion of a payment |
316 | request, the undisputed portion must be timely paid. |
317 | (3) When a contractor receives payment from a public |
318 | entity for labor, services, or materials furnished by |
319 | subcontractors and suppliers hired by the contractor, the |
320 | contractor shall remit payment due to those subcontractors and |
321 | suppliers within 10 days after the contractor's receipt of |
322 | payment. When a subcontractor receives payment from a contractor |
323 | for labor, services, or materials furnished by subcontractors |
324 | and suppliers hired by the subcontractor, the subcontractor |
325 | shall remit payment due to those subcontractors and suppliers |
326 | within 7 days after the subcontractor's receipt of payment. This |
327 | subsection does not prohibit a contractor or subcontractor from |
328 | disputing, pursuant to the terms of the relevant contract, all |
329 | or any portion of a payment alleged to be due to another party |
330 | if the contractor or subcontractor notifies the party whose |
331 | payment is disputed, in writing, of the amount in dispute and |
332 | the actions required to cure the dispute. The contractor or |
333 | subcontractor must pay all undisputed amounts due within the |
334 | time limits imposed by this subsection. |
335 | (4) All payments due for the purchase of construction |
336 | services and not made within the applicable time limits shall |
337 | bear interest at the rate specified in s. 215.422. After July 1, |
338 | 2006, such payments shall bear interest at the rate of 1 percent |
339 | per month, to the extent that the Chief Financial Officer's |
340 | replacement project for the state's accounting and cash |
341 | management systems is operational for the particular affected |
342 | public entity. After January 1, 2007, all such payments due from |
343 | public entity shall bear interest at the rate of 1 percent per |
344 | month. |
345 | Section 8. Section 255.074, Florida Statutes, is created |
346 | to read: |
347 | 255.074 Procedures for calculation of payment due dates.-- |
348 | (1) Each public entity shall establish procedures whereby |
349 | each payment request received by the public entity is marked as |
350 | received on the date on which it is delivered to an agent or |
351 | employee of the public entity or of a facility or office of the |
352 | public entity. |
353 | (2) If the terms under which a purchase is made allow for |
354 | partial deliveries and a payment request is submitted for a |
355 | partial delivery, the time for payment for the partial delivery |
356 | must be calculated from the time of the partial delivery and the |
357 | submission of the payment request. |
358 | (3) A public entity must submit a payment request to the |
359 | Chief Financial Officer for payment no more than 20 days after |
360 | receipt of the payment request. |
361 | Section 9. Section 255.075, Florida Statutes, is created |
362 | to read: |
363 | 255.075 Mandatory interest.--A contract between a public |
364 | entity and a contractor may not prohibit the collection of late |
365 | payment interest charges authorized under s. 255.073(4). |
366 | Section 10. Section 255.076, Florida Statutes, is created |
367 | to read: |
368 | 255.076 Award of court costs and attorney's fees.--In an |
369 | action to recover amounts due for construction services |
370 | purchased by a public entity, the court shall award court costs |
371 | and reasonable attorney's fees, including fees incurred through |
372 | any appeal, to the prevailing party, if the court finds that the |
373 | nonprevailing party withheld any portion of the payment that is |
374 | the subject of the action without any reasonable basis in law or |
375 | fact to dispute the prevailing party's claim to those amounts. |
376 | Section 11. Section 255.077, Florida Statutes, is created |
377 | to read: |
378 | 255.077 Project closeout and payment of retainage.-- |
379 | (1) Each contract for construction services between a |
380 | public entity and a contractor must provide for the development |
381 | of a list of items required to render complete, satisfactory, |
382 | and acceptable the construction services purchased by the public |
383 | entity. The contract must specify the process for the |
384 | development of the list, including responsibilities of the |
385 | public entity and the contractor in developing and reviewing the |
386 | list and a reasonable time for developing the list, as follows: |
387 | (a) For construction projects having an estimated cost of |
388 | less than $10 million, within 30 calendar days after reaching |
389 | substantial completion of the construction services purchased as |
390 | defined in the contract, or, if not defined in the contract, |
391 | upon reaching beneficial occupancy or use; or |
392 | (b) For construction projects having an estimated cost of |
393 | $10 million or more, within 30 calendar days, unless otherwise |
394 | extended by contract not to exceed 60 calendar days, after |
395 | reaching substantial completion of the construction services |
396 | purchased as defined in the contract, or, if not defined in the |
397 | contract, upon reaching beneficial occupancy or use. |
398 | (2) If the contract between the public entity and the |
399 | contractor relates to the purchase of construction services on |
400 | more than one building or structure, or involves a multiphased |
401 | project, the contract must provide for the development of a list |
402 | of items required to render complete, satisfactory, and |
403 | acceptable all the construction services purchased pursuant to |
404 | the contract for each building, structure, or phase of the |
405 | project within the time limitations provided in subsection (1). |
406 | (3) The failure to include any corrective work or pending |
407 | items not yet completed on the list developed pursuant to |
408 | subsection (1) or subsection (2) does not alter the |
409 | responsibility of the contractor to complete all the |
410 | construction services purchased pursuant to the contract. |
411 | (4) Upon completion of all items on the list, the |
412 | contractor may submit a payment request for all remaining |
413 | retainage withheld by the public entity pursuant to s. 255.078. |
414 | If a good-faith dispute exists as to whether one or more items |
415 | identified on the list have been completed pursuant to the |
416 | contract, the public entity may continue to withhold an amount |
417 | not to exceed 150 percent of the total costs to complete such |
418 | items. |
419 | (5) All items that require correction under the contract |
420 | and that are identified after the preparation and delivery of |
421 | the list remain the obligation of the contractor as defined by |
422 | the contract. |
423 | (6) Warranty items may not affect the final payment of |
424 | retainage as provided in this section or as provided in the |
425 | contract between the contractor and its subcontractors and |
426 | suppliers. |
427 | (7) Retainage may not be held by a public entity or a |
428 | contractor to secure payment of insurance premiums under a |
429 | consolidated insurance program or series of insurance policies |
430 | issued to a public entity or a contractor for a project or group |
431 | of projects, and the final payment of retainage as provided in |
432 | this section may not be delayed pending a final audit by the |
433 | public entity's or contractor's insurance provider. |
434 | (8) If a public entity fails to comply with its |
435 | responsibilities to develop the list required under subsection |
436 | (1) or subsection (2), as defined in the contract, within the |
437 | time limitations provided in subsection (1), the contractor may |
438 | submit a payment request for all remaining retainage withheld by |
439 | the public entity pursuant to s. 255.078. The public entity need |
440 | not pay or process any payment request for retainage if the |
441 | contractor has, in whole or in part, failed to cooperate with |
442 | the public entity in the development of the list or failed to |
443 | perform its contractual responsibilities, if any, with regard to |
444 | the development of the list or if s. 255.078(6) applies. |
445 | Section 12. Section 255.078, Florida Statutes, is created |
446 | to read: |
447 | 255.078 Public construction retainage.-- |
448 | (1) With regard to any contract for construction services, |
449 | a public entity may withhold from each progress payment made to |
450 | the contractor an amount not exceeding 10 percent of the payment |
451 | as retainage until 50-percent completion of such services. |
452 | (2) After 50-percent completion of the construction |
453 | services purchased pursuant to the contract, the public entity |
454 | must reduce to 5 percent the amount of retainage withheld from |
455 | each subsequent progress payment made to the contractor. For |
456 | purposes of this section, the term "50-percent completion" has |
457 | the meaning set forth in the contract between the public entity |
458 | and the contractor or, if not defined in the contract, the point |
459 | at which the public entity has expended 50 percent of the total |
460 | cost of the construction services purchased as identified in the |
461 | contract together with all costs associated with existing change |
462 | orders and other additions or modifications to the construction |
463 | services provided for in the contract. |
464 | (3) After 50-percent completion of the construction |
465 | services purchased pursuant to the contract, the contractor may |
466 | elect to withhold retainage from payments to its subcontractors |
467 | at a rate higher than 5 percent. The specific amount to be |
468 | withheld must be determined on a case-by-case basis and must be |
469 | based on the contractor's assessment of the subcontractor's past |
470 | performance, the likelihood that such performance will continue, |
471 | and the contractor's ability to rely on other safeguards. The |
472 | contractor shall notify the subcontractor, in writing, of its |
473 | determination to withhold more than 5 percent of the progress |
474 | payment and the reasons for making that determination, and the |
475 | contractor may not request the release of such retained funds |
476 | from the public entity. |
477 | (4) After 50-percent completion of the construction |
478 | services purchased pursuant to the contract, the contractor may |
479 | present to the public entity a payment request for up to one- |
480 | half of the retainage held by the public entity. The public |
481 | entity shall promptly make payment to the contractor, unless the |
482 | public entity has grounds, pursuant to subsection (6), for |
483 | withholding the payment of retainage. If the public entity makes |
484 | payment of retainage to the contractor under this subsection |
485 | which is attributable to the labor, services, or materials |
486 | supplied by one or more subcontractors or suppliers, the |
487 | contractor shall timely remit payment of such retainage to those |
488 | subcontractors and suppliers. |
489 | (5) Neither this section nor s. 255.077 prohibits a public |
490 | entity from withholding retainage at a rate less than 10 percent |
491 | of each progress payment, from incrementally reducing the rate |
492 | of retainage pursuant to a schedule provided for in the |
493 | contract, or from releasing at any point all or a portion of any |
494 | retainage withheld by the public entity which is attributable to |
495 | the labor, services, or materials supplied by the contractor or |
496 | by one or more subcontractors or suppliers. If a public entity |
497 | makes any payment of retainage to the contractor which is |
498 | attributable to the labor, services, or materials supplied by |
499 | one or more subcontractors or suppliers, the contractor shall |
500 | timely remit payment of such retainage to those subcontractors |
501 | and suppliers. |
502 | (6) Neither this section nor s. 255.077 requires the |
503 | public entity to pay or release any amounts that are the subject |
504 | of a good-faith dispute, the subject of a claim brought pursuant |
505 | to s. 255.05, or otherwise the subject of a claim or demand by |
506 | the public entity or contractor. |
507 | (7) The same time limits for payment of a payment request |
508 | apply regardless of whether the payment request is for, or |
509 | includes, retainage. |
510 | (8) Subsections (1)-(4) do not apply to construction |
511 | services purchased by a public entity which are paid for, in |
512 | whole or in part, with federal funds and are subject to federal |
513 | grantor laws and regulations or requirements that are contrary |
514 | to any provision of the Florida Prompt Payment Act. |
515 | (9) This section does not apply to any construction |
516 | services purchased by a public entity if the total cost of the |
517 | construction services purchased as identified in the contract is |
518 | $200,000 or less. |
519 | Section 13. Paragraph (a) of subsection (2) of section |
520 | 255.05, Florida Statutes, is amended, and subsection (10) is |
521 | added to said section, to read: |
522 | 255.05 Bond of contractor constructing public buildings; |
523 | form; action by materialmen.-- |
524 | (2)(a)1. If a claimant is no longer furnishing labor, |
525 | services, or materials on a project, a contractor or the |
526 | contractor's agent or attorney may elect to shorten the |
527 | prescribed time in this paragraph within which an action to |
528 | enforce any claim against a payment bond provided pursuant to |
529 | this section may be commenced by recording in the clerk's office |
530 | a notice in substantially the following form: |
531 |
|
532 | NOTICE OF CONTEST OF CLAIM |
533 | AGAINST PAYMENT BOND |
534 |
|
535 | To: . . . (Name and address of claimant) . . . |
536 |
|
537 | You are notified that the undersigned contests your notice |
538 | of nonpayment, dated ____________, ________, and served on the |
539 | undersigned on ____________, ________, and that the time within |
540 | which you may file suit to enforce your claim is limited to 60 |
541 | days after the date of service of this notice. |
542 |
|
543 | DATED on ____________, ________. |
544 |
|
545 | Signed: . . . (Contractor or Attorney) . . . |
546 |
|
547 | The claim of any claimant upon whom such notice is served and |
548 | who fails to institute a suit to enforce his or her claim |
549 | against the payment bond within 60 days after service of such |
550 | notice shall be extinguished automatically. The clerk shall mail |
551 | a copy of the notice of contest to the claimant at the address |
552 | shown in the notice of nonpayment or most recent amendment |
553 | thereto and shall certify to such service on the face of such |
554 | notice and record the notice. Service is complete upon mailing. |
555 | 2. A claimant, except a laborer, who is not in privity |
556 | with the contractor shall, before commencing or not later than |
557 | 45 days after commencing to furnish labor, materials, or |
558 | supplies for the prosecution of the work, furnish the contractor |
559 | with a notice that he or she intends to look to the bond for |
560 | protection. A claimant who is not in privity with the contractor |
561 | and who has not received payment for his or her labor, |
562 | materials, or supplies shall deliver to the contractor and to |
563 | the surety written notice of the performance of the labor or |
564 | delivery of the materials or supplies and of the nonpayment. The |
565 | notice of nonpayment may be served at any time during the |
566 | progress of the work or thereafter but not before 45 days after |
567 | the first furnishing of labor, services, or materials, and not |
568 | later than 90 days after the final furnishing of the labor, |
569 | services, or materials by the claimant or, with respect to |
570 | rental equipment, not later than 90 days after the date that the |
571 | rental equipment was last on the job site available for use. Any |
572 | notice of nonpayment served by a claimant who is not in privity |
573 | with the contractor which includes sums for retainage must |
574 | specify the portion of the amount claimed for retainage. No |
575 | action for the labor, materials, or supplies may be instituted |
576 | against the contractor or the surety unless both notices have |
577 | been given. Notices required or permitted under this section may |
578 | be served in accordance with s. 713.18. An action, except for an |
579 | action exclusively for recovery of retainage, must be instituted |
580 | against the contractor or the surety on the payment bond or the |
581 | payment provisions of a combined payment and performance bond |
582 | within 1 year after the performance of the labor or completion |
583 | of delivery of the materials or supplies. An action exclusively |
584 | for recovery of retainage must be instituted against the |
585 | contractor or the surety within 1 year after the performance of |
586 | the labor or completion of delivery of the materials or |
587 | supplies, or within 90 days after receipt of final payment (or |
588 | the payment estimate containing the owner's final reconciliation |
589 | of quantities if no further payment is earned and due as a |
590 | result of deductive adjustments) by the contractor or surety, |
591 | whichever comes last. A claimant may not waive in advance his or |
592 | her right to bring an action under the bond against the surety. |
593 | In any action brought to enforce a claim against a payment bond |
594 | under this section, the prevailing party is entitled to recover |
595 | a reasonable fee for the services of his or her attorney for |
596 | trial and appeal or for arbitration, in an amount to be |
597 | determined by the court, which fee must be taxed as part of the |
598 | prevailing party's costs, as allowed in equitable actions. The |
599 | time periods for service of a notice of nonpayment or for |
600 | bringing an action against a contractor or a surety shall be |
601 | measured from the last day of furnishing labor, services, or |
602 | materials by the claimant and shall not be measured by other |
603 | standards, such as the issuance of a certificate of occupancy or |
604 | the issuance of a certificate of substantial completion. |
605 | (10) An action, except an action for recovery of |
606 | retainage, must be instituted against the contractor or the |
607 | surety on the payment bond or the payment provisions of a |
608 | combined payment and performance bond within 1 year after the |
609 | performance of the labor or completion of delivery of the |
610 | materials or supplies. An action for recovery of retainage must |
611 | be instituted against the contractor or the surety within 1 year |
612 | after the performance of the labor or completion of delivery of |
613 | the materials or supplies; however, such an action may not be |
614 | instituted until one of the following conditions is satisfied: |
615 | (a) The public entity has paid out the claimant's |
616 | retainage to the contractor, and the time provided under s. |
617 | 218.735 or s. 255.073(3) for payment of that retainage to the |
618 | claimant has expired; |
619 | (b) The claimant has completed all work required under its |
620 | contract and 70 days have passed since the contractor sent its |
621 | final payment request to the public entity; or |
622 | (c) At least 160 days have passed since reaching |
623 | substantial completion of the construction services purchased, |
624 | as defined in the contract, or if not defined in the contract, |
625 | since reaching beneficial occupancy or use of the project. |
626 | (d) The claimant has asked the contractor, in writing, for |
627 | any of the following information and the contractor has failed |
628 | to respond to the claimant's request, in writing, within 10 days |
629 | after receipt of the request: |
630 | 1. Whether the project has reached substantial completion, |
631 | as that term is defined in the contract, or if not defined in |
632 | the contract, if beneficial occupancy or use of the project has |
633 | occurred. |
634 | 2. Whether the contractor has received payment of the |
635 | claimant's retainage, and if so, the date the retainage was |
636 | received by the contractor. |
637 | 3. Whether the contractor has sent its final payment |
638 | request to the public entity, and if so, the date on which the |
639 | final payment request was sent. |
640 |
|
641 | If none of the conditions described in paragraph (a), paragraph |
642 | (b), paragraph (c), or paragraph (d) is satisfied and an action |
643 | for recovery of retainage cannot be instituted within the 1-year |
644 | limitation period set forth in this subsection, this limitation |
645 | period shall be extended until 120 days after one of these |
646 | conditions is satisfied. |
647 | Section 14. Subsection (2) of section 287.0585, Florida |
648 | Statutes, is amended to read: |
649 | 287.0585 Late payments by contractors to subcontractors |
650 | and suppliers; penalty.-- |
651 | (2) This section shall not apply when the contract between |
652 | the contractor and subcontractors or subvendors provides |
653 | otherwise, or when payments under the contract are otherwise |
654 | governed by ss. 255.0705-255.078. |
655 | Section 15. Paragraph (b) of subsection (2) of section |
656 | 95.11, Florida Statutes, is amended to read: |
657 | 95.11 Limitations other than for the recovery of real |
658 | property.--Actions other than for recovery of real property |
659 | shall be commenced as follows: |
660 | (2) WITHIN FIVE YEARS.-- |
661 | (b) A legal or equitable action on a contract, obligation, |
662 | or liability founded on a written instrument, except for an |
663 | action to enforce a claim against a payment bond, which shall be |
664 | governed by the applicable provisions of ss. 255.05(10) |
665 | 255.05(2)(a)2. and 713.23(1)(e). |
666 | Section 16. Neither the amendments to sections 95.11, |
667 | 218.70, 218.72, 218.735, and 255.071, Florida Statutes, and |
668 | subsection (2) of section 255.05, Florida Statutes, as provided |
669 | in this act, nor subsection (10) of section 255.05, Florida |
670 | Statutes, and section 255.078, Florida Statutes, as created by |
671 | this act, apply to any existing construction contract pending |
672 | approval by a local governmental entity or public entity, or to |
673 | any project advertised for bid by the local governmental entity |
674 | or public entity, on or before October 1, 2005. |
675 | Section 17. This act shall take effect October 1, 2005. |