HB 1259

1
A bill to be entitled
2An act relating to the siting of electric transmission
3lines; amending s. 403.52, F.S.; changing the short title
4to the "Florida Electric Transmission Line Siting Act";
5amending s. 403.521, F.S.; revising legislative intent;
6amending s. 403.522, F.S.; revising definitions; defining
7the terms "licensee" and "maintenance and access roads";
8amending s. 403.523, F.S.; revising powers and duties of
9the Department of Environmental Protection; requiring the
10department to collect and process fees, to prepare a
11project analysis, to act as clerk for the siting board,
12and to administer and manage the terms and conditions of
13the certification order and supporting documents and
14records; amending s. 403.524, F.S.; revising provisions
15for applicability, certification, and exemptions under the
16act; revising provisions for notice by an electric utility
17of its intent to construct an exempt transmission line;
18amending s. 403.525, F.S.; providing for powers and duties
19of the administrative law judge designated by the Division
20of Administrative Hearings to conduct the required
21hearings; amending s. 403.5251, F.S.; revising application
22procedures and schedules; providing for the formal date of
23filing an application for certification and commencement
24of the certification review process; requiring the
25department to prepare a proposed schedule of dates for
26determination of completeness and other significant dates
27to be followed during the certification process; providing
28for the formal date of application distribution; requiring
29the applicant to provide notice of filing the application;
30amending s. 403.5252, F.S.; revising timeframes and
31procedures for determination of completeness of the
32application; requiring the department to consult with
33affected agencies; revising requirements for the
34department to file a statement of its determination of
35completeness with the Division of Administrative Hearings,
36the applicant, and all parties within a certain time after
37distribution of the application; revising requirements for
38the applicant to file a statement with the department, the
39division, and all parties, if the department determines
40the application is not complete; providing for the
41statement to notify the department whether the information
42will be provided; revising timeframes and procedures for
43contests of the determination by the department; providing
44for parties to a hearing on the issue of completeness;
45amending s. 403.526, F.S.; revising criteria and
46procedures for preliminary statements of issues, reports,
47and studies; revising timeframes; requiring that the
48preliminary statement of issues from each affected agency
49be submitted to the department and the applicant; revising
50criteria for the Department of Community Affairs' report;
51requiring the Department of Transportation, the Public
52Service Commission, and any other affected agency to
53prepare a project report; revising required content of the
54report; providing for notice of any nonprocedural
55requirements not listed in the application; providing for
56failure to provide such notification; providing for a
57recommendation for approval or denial of the application;
58providing that receipt of an affirmative determination of
59need is a condition precedent to further processing of the
60application; requiring that the department prepare a
61project analysis to be filed with the administrative law
62judge and served on all parties within a certain time;
63amending s. 403.527, F.S.; revising procedures and
64timeframes for the certification hearing conducted by the
65administrative law judge; revising provisions for notices
66and publication of notices, public hearings held by local
67governments, testimony at the public-hearing portion of
68the certification hearing, the order of presentations at
69the hearing, and consideration of certain communications
70by the administrative law judge; requiring the applicant
71to pay certain expenses and costs; requiring the
72administrative law judge to issue a recommended order
73disposing of the application; requiring that certain
74notices be made in accordance with specified requirements
75and within a certain time; requiring the Department of
76Transportation to be a party to the proceedings; providing
77for the administrative law judge to cancel the
78certification hearing and relinquish jurisdiction to the
79Department of Environmental Protection upon request by the
80applicant or the department; requiring the department and
81the applicant to publish notice of such cancellation;
82providing for parties to submit proposed recommended
83orders to the department when the certification hearing
84has been canceled; providing that the department prepare a
85recommended order for final action by the siting board
86when the hearing has been canceled; amending s. 403.5271,
87F.S.; revising procedures and timeframes for consideration
88of proposed alternate corridors; revising notice
89requirements; providing for notice of the filing of the
90alternate corridor and revised time schedules; providing
91for notice to agencies newly affected by the proposed
92alternate corridor; requiring the person proposing the
93alternate corridor to provide all data to the agencies
94within a certain time; providing for a determination by
95the department that the data is not complete; providing
96for withdrawal of the proposed alternate corridor upon
97such determination; requiring that agencies file reports
98with the applicant and the department which address the
99proposed alternate corridor; requiring that the department
100file with the administrative law judge, the applicant, and
101all parties a project analysis of the proposed alternate
102corridor; providing that the party proposing an alternate
103corridor has the burden of proof concerning the
104certifiability of the alternate corridor; amending s.
105403.5272, F.S.; revising procedures for informational
106public meetings; providing for informational public
107meetings held by regional planning councils; revising
108timeframes; amending s. 403.5275, F.S.; revising
109provisions for amendment to the application prior to
110certification; amending s. 403.528, F.S.; providing that a
111comprehensive application encompassing more than one
112proposed transmission line may be good cause for altering
113established time limits; amending s. 403.529, F.S.;
114revising provisions for final disposition of the
115application by the siting board; providing for the
116administrative law judge's or department's recommended
117order; amending s. 403.531, F.S.; revising provisions for
118conditions of certification; amending s. 403.5312, F.S.;
119requiring the applicant to file notice of a certified
120corridor route with the department; amending s. 403.5315,
121F.S.; revising the circumstances under which a
122certification may be modified after the certification has
123been issued; providing for procedures if objections are
124raised to the proposed modification; creating s. 403.5317,
125F.S.; providing procedures for changes proposed by the
126licensee after certification; requiring the department to
127determine within a certain time if the proposed change
128requires modification of the conditions of certification;
129requiring notice to the licensee, all agencies, and all
130parties of changes that are approved as not requiring
131modification of the conditions of certification; creating
132s. 403.5363, F.S.; requiring publication of certain
133notices by the applicant, the proponent of an alternate
134corridor, and the department; requiring the department to
135adopt rules specifying the content of such notices;
136amending s. 403.5365, F.S.; revising application fees and
137the distribution of fees collected; revising procedures
138for reimbursement of local governments and regional
139planning organizations; amending s. 403.537, F.S.;
140revising the schedule for notice of a public hearing by
141the Public Service Commission in order to determine the
142need for a transmission line; providing that the
143commission is the sole forum in which to determine the
144need for a transmission line; amending ss. 373.441,
145403.061, 403.0876, and 403.809, F.S.; conforming
146terminology to changes made by the act; repealing ss.
147403.5253 and 403.5369, F.S., relating to determination of
148sufficiency of application or amendment to the application
149and the application of the act to applications filed
150before a certain date; providing an effective date.
151
152Be It Enacted by the Legislature of the State of Florida:
153
154     Section 1.  Section 403.52, Florida Statutes, is amended to
155read:
156     403.52  Short title.--Sections 403.52-403.5365 may be cited
157as the "Florida Electric Transmission Line Siting Act."
158     Section 2.  Section 403.521, Florida Statutes, is amended
159to read:
160     403.521  Legislative intent.--The legislative intent of
161this act is to establish a centralized and coordinated licensing
162permitting process for the location of electric transmission
163line corridors and the construction, operation, and maintenance
164of electric transmission lines, which are critical
165infrastructure facilities. This necessarily involves several
166broad interests of the public addressed through the subject
167matter jurisdiction of several agencies. The Legislature
168recognizes that electric transmission lines will have an effect
169upon the reliability of the electric power system, the
170environment, land use, and the welfare of the population.
171Recognizing the need to ensure electric power system reliability
172and integrity, and in order to meet electric electrical energy
173needs in an orderly and timely fashion, the centralized and
174coordinated licensing permitting process established by this act
175is intended to further the legislative goal of ensuring through
176available and reasonable methods that the location of
177transmission line corridors and the construction, operation, and
178maintenance of electric transmission lines produce minimal
179adverse effects on the environment and public health, safety,
180and welfare while not unduly conflicting with the goals
181established by the applicable local comprehensive plan. It is
182the intent of this act to fully balance the need for
183transmission lines with the broad interests of the public in
184order to effect a reasonable balance between the need for the
185facility as a means of providing reliable, economical, and
186efficient electric abundant low-cost electrical energy and the
187impact on the public and the environment resulting from the
188location of the transmission line corridor and the construction,
189operation, and maintenance of the transmission lines. The
190Legislature intends that the provisions of chapter 120 apply to
191this act and to proceedings under pursuant to it except as
192otherwise expressly exempted by other provisions of this act.
193     Section 3.  Section 403.522, Florida Statutes, is amended
194to read:
195     403.522  Definitions relating to the Florida Electric
196Transmission Line Siting Act.--As used in this act:
197     (1)  "Act" means the Florida Electric Transmission Line
198Siting Act.
199     (2)  "Agency," as the context requires, means an official,
200officer, commission, authority, council, committee, department,
201division, bureau, board, section, or other unit or entity of
202government, including a county, municipality, or other regional
203or local governmental entity.
204     (3)  "Amendment" means a material change in information
205provided by the applicant to the application for certification
206made after the initial application filing.
207     (4)  "Applicant" means any electric utility that which
208applies for certification under pursuant to the provisions of
209this act.
210     (5)  "Application" means the documents required by the
211department to be filed to initiate and support a certification
212review and evaluation, including the initial document filing,
213amendments, and responses to requests from the department for
214additional data and information proceeding. An electric utility
215may file a comprehensive application encompassing all or a part
216of one or more proposed transmission lines.
217     (6)  "Board" means the Governor and Cabinet sitting as the
218siting board.
219     (7)  "Certification" means the approval by the board of the
220license for a corridor proper for certification pursuant to
221subsection (10) and the construction, operation, and maintenance
222of transmission lines within the such corridor with the such
223changes or conditions as the siting board deems appropriate.
224Certification shall be evidenced by a written order of the
225board.
226     (8)  "Commission" means the Florida Public Service
227Commission.
228     (9)  "Completeness" means that the application has
229addressed all applicable sections of the prescribed application
230format and, but does not mean that those sections are sufficient
231in comprehensiveness of data or in quality of information
232provided to allow the department to determine whether the
233application provides the reviewing agencies adequate information
234to prepare the reports required by s. 403.526.
235     (10)  "Corridor" means the proposed area within which a
236transmission line right-of-way, including maintenance and access
237roads, is to be located. The width of the corridor proposed for
238certification by an applicant or other party, at the option of
239the applicant, may be the width of the transmission line right-
240of-way, or a wider boundary, not to exceed a width of 1 mile.
241The area within the corridor in which a right-of-way may be
242located may be further restricted by a condition of
243certification. After all property interests required for the
244transmission line right-of-way and maintenance and access roads
245have been acquired by the applicant, the boundaries of the area
246certified shall narrow to only that land within the boundaries
247of the transmission line right-of-way. The corridors proper for
248certification shall be those addressed in the application, in
249amendments to the application filed under pursuant to s.
250403.5275, and in notices of acceptance of proposed alternate
251corridors filed by an applicant and the department pursuant to
252s. 403.5271 for which the required sufficient information for
253the preparation of agency supplemental reports was filed.
254     (11)  "Department" means the Department of Environmental
255Protection.
256     (12)  "Electric utility" means cities and towns, counties,
257public utility districts, regulated electric companies, electric
258cooperatives, regional transmission organizations, operators of
259independent transmission systems, or other transmission
260organizations approved by the Federal Energy Regulatory
261Commission or the commission for the operation of transmission
262facilities, and joint operating agencies, or combinations
263thereof, engaged in, or authorized to engage in, the business of
264generating, transmitting, or distributing electric energy.
265     (13)  "License" means a franchise, permit, certification,
266registration, charter, comprehensive plan amendment, development
267order, or permit as defined in chapters 163 and 380, or similar
268form of authorization required by law, but it does not include a
269license required primarily for revenue purposes when issuance of
270the license is merely a ministerial act.
271     (14)  "Licensee" means an applicant that has obtained a
272certification order for the subject project.
273     (15)(14)  "Local government" means a municipality or county
274in the jurisdiction of which the project is proposed to be
275located.
276     (16)  "Maintenance and access roads" mean roads constructed
277within the transmission line right-of-way. Nothing in this act
278prohibits an applicant from constructing a road to support
279construction, operation, or maintenance of the transmission line
280that lies outside the transmission line right-of-way.
281     (17)(15)  "Modification" means any change in the
282certification order after issuance, including a change in the
283conditions of certification.
284     (18)(16)  "Nonprocedural requirements of agencies" means
285any agency's regulatory requirements established by statute,
286rule, ordinance, or comprehensive plan, excluding any provisions
287prescribing forms, fees, procedures, or time limits for the
288review or processing of information submitted to demonstrate
289compliance with such regulatory requirements.
290     (19)(17)  "Person" means an individual, partnership, joint
291venture, private or public corporation, association, firm,
292public service company, political subdivision, municipal
293corporation, government agency, public utility district, or any
294other entity, public or private, however organized.
295     (20)(18)  "Preliminary statement of issues" means a listing
296and explanation of those issues within the agency's jurisdiction
297which are of major concern to the agency in relation to the
298proposed electric electrical transmission line corridor.
299     (21)(19)  "Regional planning council" means a regional
300planning council as defined in s. 186.503(4) in the jurisdiction
301of which the project is proposed to be located.
302     (20)  "Sufficiency" means that the application is not only
303complete but that all sections are adequate in the
304comprehensiveness of data and in the quality of information
305provided to allow the department to determine whether the
306application provides the reviewing agencies adequate information
307to prepare the reports authorized by s. 403.526.
308     (22)(21)  "Transmission line" or "electric transmission
309line" means structures, maintenance and access roads, and all
310other facilities that need to be constructed, operated, or
311maintained for the purpose of conveying electric power any
312electrical transmission line extending from, but not including,
313an existing or proposed substation or power plant to, but not
314including, an existing or proposed transmission network or
315rights-of-way or substation to which the applicant intends to
316connect which defines the end of the proposed project and which
317is designed to operate at 230 kilovolts or more. The starting
318point and ending point of a transmission line must be
319specifically defined by the applicant and must be verified by
320the commission in its determination of need. A transmission line
321includes structures and maintenance and access roads that need
322to be constructed for the project to become operational. The
323transmission line may include, at the applicant's option, any
324proposed terminal or intermediate substations or substation
325expansions necessary to serve the transmission line.
326     (23)(22)  "Transmission line right-of-way" means land
327necessary for the construction, operation, and maintenance of a
328transmission line. The typical width of the right-of-way shall
329be identified in the application. The right-of-way shall be
330located within the certified corridor and shall be identified by
331the applicant subsequent to certification in documents filed
332with the department before prior to construction.
333     (24)(23)  "Water management district" means a water
334management district created pursuant to chapter 373 in the
335jurisdiction of which the project is proposed to be located.
336     Section 4.  Section 403.523, Florida Statutes, is amended
337to read:
338     403.523  Department of Environmental Protection; powers and
339duties.--The department has shall have the following powers and
340duties:
341     (1)  To adopt procedural rules pursuant to ss. 120.536(1)
342and 120.54 to administer implement the provisions of this act
343and to adopt or amend rules to implement the provisions of
344subsection (10).
345     (2)  To prescribe the form and content of the public
346notices and the form, content, and necessary supporting
347documentation, and any required studies, for certification
348applications. All such data and studies shall be related to the
349jurisdiction of the agencies relevant to the application.
350     (3)  To receive applications for transmission line and
351corridor certifications and initially determine the completeness
352and sufficiency thereof.
353     (4)  To make or contract for studies of certification
354applications. All such studies shall be related to the
355jurisdiction of the agencies relevant to the application. For
356studies in areas outside the jurisdiction of the department and
357in the jurisdiction of another agency, the department may
358initiate such studies, but only with the consent of the such
359agency.
360     (5)  To administer the processing of applications for
361certification and ensure that the applications, including
362postcertification reviews, are processed on an expeditious and
363priority basis as expeditiously as possible.
364     (6)  To collect and process require such fees as allowed by
365this act.
366     (7)  To prepare a report and project written analysis as
367required by s. 403.526.
368     (8)  To prescribe the means for monitoring the effects
369arising from the location of the transmission line corridor and
370the construction, operation, and maintenance of the transmission
371lines to assure continued compliance with the terms of the
372certification.
373     (9)  To make a determination of acceptability of any
374alternate corridor proposed for consideration under pursuant to
375s. 403.5271.
376     (10)  To set requirements that reasonably protect the
377public health and welfare from the electric and magnetic fields
378of transmission lines for which an application is filed under
379after the effective date of this act.
380     (11)  To present rebuttal evidence on any issue properly
381raised at the certification hearing.
382     (12)  To issue final orders after receipt of the
383administrative law judge's order relinquishing jurisdiction
384pursuant to s. 403.527(6).
385     (13)  To act as clerk for the siting board.
386     (14)  To administer and manage the terms and conditions of
387the certification order and supporting documents and records for
388the life of the facility.
389     (15)  To issue emergency orders on behalf of the board for
390facilities licensed under this act.
391     Section 5.  Section 403.524, Florida Statutes, is amended
392to read:
393     403.524  Applicability; and certification; exemptions.--
394     (1)  The provisions of This act applies apply to each
395transmission line, except a transmission line certified under
396pursuant to the Florida Electrical Power Plant Siting Act.
397     (2)  Except as provided in subsection (1), no construction
398of a any transmission line may not be undertaken without first
399obtaining certification under this act, but the provisions of
400this act does do not apply to:
401     (a)  Transmission lines for which development approval has
402been obtained under pursuant to chapter 380.
403     (b)  Transmission lines that which have been exempted by a
404binding letter of interpretation issued under s. 380.06(4), or
405in which the Department of Community Affairs or its predecessor
406agency has determined the utility to have vested development
407rights within the meaning of s. 380.05(18) or s. 380.06(20).
408     (c)  Transmission line development in which all
409construction is limited to established rights-of-way.
410Established rights-of-way include such rights-of-way established
411at any time for roads, highways, railroads, gas, water, oil,
412electricity, or sewage and any other public purpose rights-of-
413way. If an established transmission line right-of-way is used to
414qualify for this exemption, the transmission line right-of-way
415must have been established at least 5 years before notice of the
416start of construction under subsection (4) of the proposed
417transmission line. If an established transmission line right-of-
418way is relocated to accommodate a public project, the date the
419original transmission line right-of-way was established applies
420to the relocated transmission line right-of-way for purposes of
421this exemption. Except for transmission line rights-of-way,
422established rights-of-way include rights-of-way created before
423or after October 1, 1983. For transmission line rights-of-way,
424established rights-of-way include rights-of-way created before
425October 1, 1983.
426     (d)  Unless the applicant has applied for certification
427under this act, transmission lines that which are less than 15
428miles in length or are located in a single which do not cross a
429county within the state line, unless the applicant has elected
430to apply for certification under the act.
431     (3)  The exemption of a transmission line under this act
432does not constitute an exemption for the transmission line from
433other applicable permitting processes under other provisions of
434law or local government ordinances.
435     (4)  An electric A utility shall notify the department in
436writing, before prior to the start of construction, of its
437intent to construct a transmission line exempted under pursuant
438to this section. The Such notice is shall be only for
439information purposes, and no action by the department is not
440shall be required pursuant to the such notice. This notice may
441be included in any submittal filed with the department before
442the start of construction demonstrating that a new transmission
443line complies with the applicable electric and magnetic field
444standards.
445     Section 6.  Section 403.525, Florida Statutes, is amended
446to read:
447     403.525  Appointment of Administrative law judge;
448appointment; powers and duties.--
449     (1)(a)  Within 7 days after receipt of an application,
450whether complete or not, the department shall request the
451Division of Administrative Hearings to designate an
452administrative law judge to conduct the hearings required by
453this act.
454     (b)  The division director shall designate an
455administrative law judge to conduct the hearings required by
456this act within 7 days after receipt of the request from the
457department. Whenever practicable, the division director shall
458assign an administrative law judge who has had prior experience
459or training in this type of certification proceeding.
460     (c)  Upon being advised that an administrative law judge
461has been designated, the department shall immediately file a
462copy of the application and all supporting documents with the
463administrative law judge, who shall docket the application.
464     (2)  The administrative law judge has all powers and duties
465granted to administrative law judges under chapter 120 and by
466the laws and rules of the department.
467     Section 7.  Section 403.5251, Florida Statutes, is amended
468to read:
469     403.5251  Distribution of Application; schedules.--
470     (1)(a)  The formal date of the filing of the application
471for certification and commencement of the review process for
472certification is the date on which the applicant submits:
473     1.  Copies of the application for certification in a
474quantity and format, electronic or otherwise as prescribed by
475rule, to the department and other agencies identified in s.
476403.526(2); and
477     2.  The application fee as specified under s. 403.5365 to
478the department.
479
480The department shall provide to the applicant and the Division
481of Administrative Hearings the names and addresses of any
482additional agencies or persons entitled to notice and copies of
483the application and amendments, if any, within 7 days after
484receiving the application for certification and the application
485fees.
486     (b)  In the application, the starting point and ending
487point of a transmission line must be specifically defined by the
488applicant. Within 7 days after the filing of an application, the
489department shall provide the applicant and the Division of
490Administrative Hearings the names and addresses of those
491affected or other agencies entitled to notice and copies of the
492application and any amendments.
493     (2)  Within 15 7 days after the formal date of the
494application filing completeness has been determined, the
495department shall prepare a proposed schedule of dates for
496determination of completeness, submission of statements of
497issues, determination of sufficiency, and submittal of final
498reports, from affected and other agencies and other significant
499dates to be followed during the certification process, including
500dates for filing notices of appearances to be a party under s.
501403.527(2) pursuant to s. 403.527(4). This schedule shall be
502provided by the department to the applicant, the administrative
503law judge, and the agencies identified under pursuant to
504subsection (1). Within 7 days after the filing of this proposed
505schedule, the administrative law judge shall issue an order
506establishing a schedule for the matters addressed in the
507department's proposed schedule and other appropriate matters, if
508any.
509     (3)  Within 7 days after completeness has been determined,
510the applicant shall distribute copies of the application to all
511agencies identified by the department pursuant to subsection
512(1). Copies of changes and amendments to the application shall
513be timely distributed by the applicant to all agencies and
514parties who have received a copy of the application.
515     (4)  Notice of the filing of the application shall be made
516in accordance with the requirements of s. 403.5363.
517     Section 8.  Section 403.5252, Florida Statutes, is amended
518to read:
519     403.5252  Determination of completeness.--
520     (1)(a)  Within 30 days after distribution of an
521application, the affected agencies shall file a statement with
522the department containing the recommendations of each agency
523concerning the completeness of the application for
524certification.
525     (b)  Within 7 15 days after receipt of the completeness
526statements of each agency an application, the department shall
527file a statement with the Division of Administrative Hearings,
528and with the applicant, and with all parties declaring its
529position with regard to the completeness, not the sufficiency,
530of the application. The statement of the department shall be
531based upon its consultation with the affected agencies.
532     (2)(1)  If the department declares the application to be
533incomplete, the applicant, within 14 15 days after the filing of
534the statement by the department, shall file with the Division of
535Administrative Hearings, with all parties, and with the
536department a statement:
537     (a)  A withdrawal of Agreeing with the statement of the
538department and withdrawing the application;
539     (b)  Additional information necessary to make the
540application complete. After the department first determines the
541application to be incomplete, the time schedules under this act
542are not tolled if the applicant makes the application complete
543within the 14-day period. A subsequent finding by the department
544that the application remains incomplete tolls the time schedules
545under this act until the application is determined complete;
546Agreeing with the statement of the department and agreeing to
547amend the application without withdrawing it. The time schedules
548referencing a complete application under this act shall not
549commence until the application is determined complete; or
550     (c)  A statement contesting the department's determination
551of incompleteness; or statement of the department.
552     (d)  A statement agreeing with the department and
553requesting additional time to provide the information necessary
554to make the application complete. If the applicant exercises
555this option, the time schedules under this act are tolled until
556the application is determined complete.
557     (3)(a)(2)  If the applicant contests the determination by
558the department that an application is incomplete, the
559administrative law judge shall schedule a hearing on the
560statement of completeness. The hearing shall be held as
561expeditiously as possible, but not later than 21 30 days after
562the filing of the statement by the department. The
563administrative law judge shall render a decision within 7 10
564days after the hearing.
565     (b)  Parties to a hearing on the issue of completeness
566shall include the applicant, the department, and any agency that
567has jurisdiction over the matter in dispute. Any substantially
568affected person who wishes to become a party to the hearing on
569the issue of completeness must file a motion no later than 10
570days before the date of the hearing.
571     (c)(a)  If the administrative law judge determines that the
572application was not complete as filed, the applicant shall
573withdraw the application or make such additional submittals as
574necessary to complete it. The time schedules referencing a
575complete application under this act do shall not commence until
576the application is determined complete.
577     (d)(b)  If the administrative law judge determines that the
578application was complete at the time it was declared incomplete
579filed, the time schedules referencing a complete application
580under this act shall commence upon such determination.
581     (4)  If the applicant provides additional information to
582address the issues identified in the determination of
583incompleteness, each affected agency may submit to the
584department, no later than 14 days after the applicant files the
585additional information, a recommendation on whether the agency
586believes the application is complete. Within 21 days after
587receipt of the additional information from the applicant
588submitted under paragraphs (2)(b), (2)(d), or (3)(c) and
589considering the recommendations of the affected agencies, the
590department shall determine whether the additional information
591supplied by an applicant makes the application complete. If the
592department finds that the application is still incomplete, the
593applicant may exercise any of the options specified in
594subsection (2) as often as is necessary to resolve the dispute.
595     Section 9.  Section 403.526, Florida Statutes, is amended
596to read:
597     403.526  Preliminary statements of issues, reports, and
598project analyses; and studies.--
599     (1)  Each affected agency that is required to file a report
600which received an application in accordance with this section s.
601403.5251(3) shall submit a preliminary statement of issues to
602the department and all parties the applicant no later than 50 60
603days after the filing distribution of the complete application.
604Such statements of issues shall be made available to each local
605government for use as information for public meetings held under
606pursuant to s. 403.5272. The failure to raise an issue in this
607preliminary statement of issues does shall not preclude the
608issue from being raised in the agency's report.
609     (2)(a)  The following affected agencies shall prepare
610reports as provided below and shall submit them to the
611department and the applicant no later than within 90 days after
612the filing distribution of the complete application:
613     1.  The department shall prepare a report as to the impact
614of each proposed transmission line or corridor as it relates to
615matters within its jurisdiction.
616     2.  Each water management district in the jurisdiction of
617which a proposed transmission line or corridor is to be located
618shall prepare a report as to the impact on water resources and
619other matters within its jurisdiction.
620     3.  The Department of Community Affairs shall prepare a
621report containing recommendations which address the impact upon
622the public of the proposed transmission line or corridor, based
623on the degree to which the proposed transmission line or
624corridor is consistent with the applicable portions of the state
625comprehensive plan, emergency management, and other matters
626within its jurisdiction. The Department of Community Affairs may
627also comment on the consistency of the proposed transmission
628line or corridor with applicable strategic regional policy plans
629or local comprehensive plans and land development regulations.
630     4.  The Fish and Wildlife Conservation Commission shall
631prepare a report as to the impact of each proposed transmission
632line or corridor on fish and wildlife resources and other
633matters within its jurisdiction.
634     5.  Each local government shall prepare a report as to the
635impact of each proposed transmission line or corridor on matters
636within its jurisdiction, including the consistency of the
637proposed transmission line or corridor with all applicable local
638ordinances, regulations, standards, or criteria that apply to
639the proposed transmission line or corridor, including local
640comprehensive plans, zoning regulations, land development
641regulations, and any applicable local environmental regulations
642adopted pursuant to s. 403.182 or by other means. A No change by
643the responsible local government or local agency in local
644comprehensive plans, zoning ordinances, or other regulations
645made after the date required for the filing of the local
646government's report required by this section is not shall be
647applicable to the certification of the proposed transmission
648line or corridor unless the certification is denied or the
649application is withdrawn.
650     6.  Each regional planning council shall present a report
651containing recommendations that address the impact upon the
652public of the proposed transmission line or corridor based on
653the degree to which the transmission line or corridor is
654consistent with the applicable provisions of the strategic
655regional policy plan adopted under pursuant to chapter 186 and
656other impacts of each proposed transmission line or corridor on
657matters within its jurisdiction.
658     7.  The Department of Transportation shall prepare a report
659as to the impact of the proposed transmission line or corridor
660on state roads, railroads, airports, aeronautics, seaports, and
661other matters within its jurisdiction.
662     8.  The commission shall prepare a report containing its
663determination under s. 403.537 and the report may include the
664comments from the commission with respect to any other subject
665within its jurisdiction.
666     9.  Any other agency, if requested by the department, shall
667also perform studies or prepare reports as to subjects within
668the jurisdiction of the agency which may potentially be affected
669by the proposed transmission line.
670     (b)  Each report must shall contain:
671     1.  A notice of any nonprocedural requirements not
672specifically listed in the application from which a variance,
673exemption, exception, or other relief is necessary in order for
674the proposed corridor to be certified. Failure to include the
675notice shall be treated as a waiver from the nonprocedural
676requirements of that agency.
677     2.  A recommendation for approval or denial of the
678application.
679     3.  The information on variances required by s. 403.531(2)
680and proposed conditions of certification on matters within the
681jurisdiction of each agency. For each condition proposed by an
682agency, the agency shall list the specific statute, rule, or
683ordinance, as applicable, which authorizes the proposed
684condition.
685     (c)  Each reviewing agency shall initiate the activities
686required by this section no later than 15 days after the
687complete application is filed distributed. Each agency shall
688keep the applicant and the department informed as to the
689progress of its studies and any issues raised thereby.
690     (d)  Receipt of an affirmative determination of need from
691the commission by the submittal deadline for agency reports
692under paragraph (a) is a condition precedent to further
693processing of the application.
694     (3)  The department shall prepare a project written
695analysis containing which contains a compilation of agency
696reports and summaries of the material contained therein which
697shall be filed with the administrative law judge and served on
698all parties no later than 115 135 days after the application is
699filed complete application has been distributed to the affected
700agencies, and which shall include:
701     (a)  A statement indicating whether the proposed electric
702transmission line will be in compliance with the rules of the
703department and affected agencies.
704     (b)(a)  The studies and reports required by this section
705and s. 403.537.
706     (c)(b)  Comments received from any other agency or person.
707     (d)(c)  The recommendation of the department as to the
708disposition of the application, of variances, exemptions,
709exceptions, or other relief identified by any party, and of any
710proposed conditions of certification which the department
711believes should be imposed.
712     (4)  The failure of any agency to submit a preliminary
713statement of issues or a report, or to submit its preliminary
714statement of issues or report within the allowed time, is shall
715not be grounds for the alteration of any time limitation in this
716act under pursuant to s. 403.528. Neither The failure to submit
717a preliminary statement of issues or a report, or nor the
718inadequacy of the preliminary statement of issues or report, are
719not shall be grounds to deny or condition certification.
720     Section 10.  Section 403.527, Florida Statutes, is amended
721to read:
722(Substantial rewording of section. See s. 403.527, F.S.,
723for present text.)
724     403.527  Certification hearing, parties, participants.--
725     (1)(a)  No later than 145 days after the application is
726filed, the administrative law judge shall conduct a
727certification hearing pursuant to ss. 120.569 and 120.57 at a
728central location in proximity to the proposed transmission line
729or corridor.
730     (b)  Notice of the certification hearing and other public
731hearings provided for in this section and notice of the deadline
732for filing of notice of intent to be a party shall be made in
733accordance with the requirements of s. 403.5363.
734     (2)(a)  Parties to the proceeding shall be:
735     1.  The applicant.
736     2.  The department.
737     3.  The commission.
738     4.  The Department of Community Affairs.
739     5.  The Fish and Wildlife Conservation Commission.
740     6.  The Department of Transportation.
741     7.  Each water management district in the jurisdiction of
742which the proposed transmission line or corridor is to be
743located.
744     8.  The local government.
745     9.  The regional planning council.
746     (b)  Any party listed in paragraph (a), other than the
747department or the applicant, may waive its right to participate
748in these proceedings. If any listed party fails to file a notice
749of its intent to be a party on or before the 30th day before the
750certification hearing, the party is deemed to have waived its
751right to be a party unless its participation would not prejudice
752the rights of any party to the proceeding.
753     (c)  Notwithstanding the provisions of chapter 120 to the
754contrary, upon the filing with the administrative law judge of a
755notice of intent to be a party by an agency, corporation, or
756association described in subparagraphs 1. and 2. or a petition
757for intervention by a person described in subparagraph 3. no
758later than 30 days before the date set for the certification
759hearing, the following shall also be parties to the proceeding:
760     1.  Any agency not listed in paragraph (a) as to matters
761within its jurisdiction.
762     2.  Any domestic nonprofit corporation or association
763formed, in whole or in part, to promote conservation of natural
764beauty; to protect the environment, personal health, or other
765biological values; to preserve historical sites; to promote
766consumer interests; to represent labor, commercial, or
767industrial groups; or to promote comprehensive planning or
768orderly development of the area in which the proposed
769transmission line or corridor is to be located.
770     3.  Any person whose substantial interests are affected and
771being determined by the proceeding.
772     (d)  Any agency whose properties or works may be affected
773shall be made a party upon the request of the agency or any
774party to this proceeding.
775     (3)(a)  The order of presentation at the certification
776hearing, unless otherwise changed by the administrative law
777judge to ensure the orderly presentation of witnesses and
778evidence, shall be:
779     1.  The applicant.
780     2.  The department.
781     3.  State agencies.
782     4.  Regional agencies, including regional planning councils
783and water management districts.
784     5.  Local governments.
785     6.  Other parties.
786     (b)  When appropriate, any person may be given an
787opportunity to present oral or written communications to the
788administrative law judge. If the administrative law judge
789proposes to consider such communications, all parties shall be
790given an opportunity to cross-examine, challenge, or rebut the
791communications.
792     (4)  One public hearing where members of the public who are
793not parties to the certification hearing may testify shall be
794held within the boundaries of each county, at the option of any
795local government.
796     (a)  A local government shall notify the administrative law
797judge and all parties not later than 21 days after the
798application has been determined complete as to whether the local
799government wishes to have a public hearing. If a filing for an
800alternate corridor is accepted for consideration under s.
801403.5271(1) by the department and the applicant, any newly
802affected local government must notify the administrative law
803judge and all parties not later than 10 days after the data
804concerning the alternate corridor has been determined complete
805as to whether the local government wishes to have such a public
806hearing. The local government is responsible for providing the
807location of the public hearing if held separately from the
808certification hearing.
809     (b)  Within 5 days after notification, the administrative
810law judge shall determine the date of the public hearing, which
811shall be held before or during the certification hearing. If two
812or more local governments within one county request a public
813hearing, the hearing shall be consolidated so that only one
814public hearing is held in any county. The location of a
815consolidated hearing shall be determined by the administrative
816law judge.
817     (c)  If a local government does not request a public
818hearing within 21 days after the application has been determined
819complete, persons residing within the jurisdiction of the local
820government may testify during that portion of the certification
821hearing at which public testimony is heard.
822     (5)  At the conclusion of the certification hearing, the
823administrative law judge shall, after consideration of all
824evidence of record, issue a recommended order disposing of the
825application no later than 45 days after the transcript of the
826certification hearing and the public hearings is filed with the
827Division of Administrative Hearings.
828     (6)(a)  No later than 25 days before the certification
829hearing, the department or the applicant may request that the
830administrative law judge cancel the certification hearing and
831relinquish jurisdiction to the department if all parties to the
832proceeding stipulate that there are no disputed issues of
833material fact to be raised at the certification hearing.
834     (b)  The administrative law judge shall issue an order
835granting or denying the request within 5 days.
836     (c)  If the administrative law judge grants the request,
837the department and the applicant shall publish notices of the
838cancellation of the certification hearing in accordance with s.
839403.5363.
840     (d)1.  If the administrative law judge grants the request,
841the department shall prepare and issue a final order in
842accordance with s. 403.529(1)(a).
843     2.  Parties may submit proposed final orders to the
844department no later than 10 days after the administrative law
845judge issues an order relinquishing jurisdiction.
846     (7)  The applicant shall pay those expenses and costs
847associated with the conduct of the hearing and the recording and
848transcription of the proceedings.
849     Section 11.  Section 403.5271, Florida Statutes, is amended
850to read:
851     403.5271  Alternate corridors.--
852     (1)  No later than 45 50 days before prior to the
853originally scheduled certification hearing, any party may
854propose alternate transmission line corridor routes for
855consideration under pursuant to the provisions of this act.
856     (a)  A notice of a any such proposed alternate corridor
857must shall be filed with the administrative law judge, all
858parties, and any local governments in whose jurisdiction the
859alternate corridor is proposed. The Such filing must shall
860include the most recent United States Geological Survey 1:24,000
861quadrangle maps specifically delineating the corridor
862boundaries, a description of the proposed corridor, and a
863statement of the reasons the proposed alternate corridor should
864be certified.
865     (b)1.  Within 7 days after receipt of the such notice, the
866applicant and the department shall file with the administrative
867law judge and all parties a notice of acceptance or rejection of
868a proposed alternate corridor for consideration. If the
869alternate corridor is rejected either by the applicant or the
870department, the certification hearing and the public hearings
871shall be held as scheduled. If both the applicant and the
872department accept a proposed alternate corridor for
873consideration, the certification hearing and the public hearings
874shall be rescheduled, if necessary.
875     2.  If rescheduled, the certification hearing shall be held
876no more than 90 days after the previously scheduled
877certification hearing, unless the data submitted under paragraph
878(d) is determined to be incomplete, in which case the
879rescheduled certification hearing shall be held no more than 105
880days after the previously scheduled certification hearing. If
881additional time is needed due to the alternate corridor crossing
882a local government jurisdiction that was not previously
883affected, in which case the remainder of the schedule listed
884below shall be appropriately adjusted by the administrative law
885judge to allow that local government to prepare a report
886pursuant to s. 403.526(2)(a)5.
887     (c)  Notice of the filing of the alternate corridor, of the
888revised time schedules, of the deadline for newly affected
889persons and agencies to file notice of intent to become a party,
890of the rescheduled hearing date, and of the proceedings pursuant
891to s. 403.527(1)(b) and (c) shall be published in accordance
892with s. 403.5363.
893     (d)  Within 21 25 days after acceptance of an alternate
894corridor by the department and the applicant, the party
895proposing an alternate corridor shall have the burden of
896providing all additional data to the agencies listed in s.
897403.526(2) and newly affected agencies s. 403.526 necessary for
898the preparation of a supplementary report on the proposed
899alternate corridor.
900     (e)1.  Reviewing agencies shall advise the department of
901any issues concerning completeness no later than 15 days after
902the submittal of the data required by paragraph (d). Within 22
903days after receipt of the data, the department shall issue a
904determination of completeness.
905     2.  If the department determines that the data required by
906paragraph (d) is not complete, the party proposing the alternate
907corridor must file such additional data to correct the
908incompleteness. This additional data must be submitted within 14
909days after the determination by the department.
910     3.  If the department, within 14 days after receiving the
911additional data, determines that the data remains incomplete,
912the incompleteness of the data is deemed a withdrawal of the
913proposed alternate corridor. The department may make its
914determination based on recommendations made by other affected
915agencies. If the department determines within 15 days that this
916additional data is insufficient, the party proposing the
917alternate corridor shall file such additional data that corrects
918the insufficiency within 15 days after the filing of the
919department's determination. If such additional data is
920determined insufficient, such insufficiency of data shall be
921deemed a withdrawal of the proposed alternate corridor. The
922party proposing an alternate corridor shall have the burden of
923proof on the certifiability of the alternate corridor at the
924certification hearing pursuant to s. 403.529(4). Nothing in this
925act shall be construed as requiring the applicant or agencies
926not proposing the alternate corridor to submit data in support
927of such alternate corridor.
928     (f)  The agencies listed in s. 403.526(2) and any newly
929affected agencies s. 403.526 shall file supplementary reports
930with the applicant and the department which address addressing
931the proposed alternate corridors no later than 24 60 days after
932the additional data is submitted pursuant to paragraph (d) or
933paragraph (e) is determined to be complete.
934     (g)  The agency reports on alternate corridors must include
935all information required by s. 403.526(2) agencies shall submit
936supplementary notice pursuant to s. 403.531(2) at the time of
937filing of their supplemental report.
938     (h)  The department shall file with the administrative law
939judge, the applicant, and all parties a project prepare a
940written analysis consistent with s. 403.526(3) no more than 16
941at least 29 days after submittal of agency reports on prior to
942the rescheduled certification hearing addressing the proposed
943alternate corridor.
944     (2)  If the original certification hearing date is
945rescheduled, the rescheduling shall not provide the opportunity
946for parties to file additional alternate corridors to the
947applicant's proposed corridor or any accepted alternate
948corridor. However, an amendment to the application which changes
949the alignment of the applicant's proposed corridor shall require
950rescheduling of the certification hearing, if necessary, so as
951to allow time for a party to file alternate corridors to the
952realigned proposed corridor for which the application has been
953amended. Any such alternate corridor proposal shall have the
954same starting and ending points as the realigned portion of the
955corridor proposed by the applicant's amendment, provided that
956the administrative law judge for good cause shown may authorize
957another starting or ending point in the area of the applicant's
958amended corridor.
959     (3)(a)  Notwithstanding the rejection of a proposed
960alternate corridor by the applicant or the department, any party
961may present evidence at the certification hearing to show that a
962corridor proper for certification does not satisfy the criteria
963listed in s. 403.529 or that a rejected alternate corridor would
964meet the criteria set forth in s. 403.529. No Evidence may not
965shall be admitted at the certification hearing on any alternate
966corridor, unless the alternate corridor was proposed by the
967filing of a notice at least 45 50 days before prior to the
968originally scheduled certification hearing pursuant to this
969section. Rejected alternate corridors shall be considered by the
970board as provided in s. 403.529(4) and (5).
971     (b)  The party proposing an alternate corridor has the
972burden to prove that the alternate corridor can be certified at
973the certification hearing. This act does not require an
974applicant or agency that is not proposing the alternate corridor
975to submit data in support of the alternate corridor.
976     (4)  If an alternate corridor is accepted by the applicant
977and the department pursuant to a notice of acceptance as
978provided in this subsection and the such corridor is ultimately
979determined to be the corridor that would meet the criteria set
980forth in s. 403.529(4) and (5), the board shall certify that
981corridor.
982     Section 12.  Section 403.5272, Florida Statutes, is amended
983to read:
984     403.5272  Local governments; Informational public
985meetings.--
986     (1)  A local government whose jurisdiction is to be crossed
987by a proposed corridor governments may hold one informational
988public meeting meetings in addition to the hearings specifically
989authorized by this act on any matter associated with the
990transmission line proceeding. The Such informational public
991meeting may be conducted by the local government or the regional
992planning council and shall meetings should be held no later than
99355 80 days after the application is filed. The purpose of an
994informational public meeting is for the local government or
995regional planning council to further inform the general public
996about the transmission line proposed, obtain comments from the
997public, and formulate its recommendation with respect to the
998proposed transmission line.
999     (2)  Informational public meetings shall be held solely at
1000the option of each local government or regional planning
1001council. It is the legislative intent that local governments or
1002regional planning councils attempt to hold such public meetings.
1003Parties to the proceedings under this act shall be encouraged to
1004attend; however, a no party other than the applicant and the
1005department is not shall be required to attend the such
1006informational public meetings hearings.
1007     (3)  A local government or regional planning council that
1008intends to conduct an informational public meeting must provide
1009notice of the meeting, with notice sent to all parties listed in
1010s. 403.527(2)(a), not less than 5 days before the meeting.
1011     (4)(3)  The failure to hold an informational public meeting
1012or the procedure used for the informational public meeting are
1013shall not be grounds for the alteration of any time limitation
1014in this act under pursuant to s. 403.528 or grounds to deny or
1015condition certification.
1016     Section 13.  Section 403.5275, Florida Statutes, is amended
1017to read:
1018     403.5275  Amendment to the application.--
1019     (1)  Any amendment made to the application before
1020certification shall be sent by the applicant to the
1021administrative law judge and to all parties to the proceeding.
1022     (2)  Any amendment to the application made before prior to
1023certification shall be disposed of as part of the original
1024certification proceeding. Amendment of the application may be
1025considered "good cause" for alteration of time limits pursuant
1026to s. 403.528.
1027     Section 14.  Section 403.528, Florida Statutes, is amended
1028to read:
1029     403.528  Alteration of time limits.--
1030     (1)  Any time limitation in this act may be altered by the
1031administrative law judge upon stipulation between the department
1032and the applicant unless objected to by any party within 5 days
1033after notice or for good cause shown by any party.
1034     (2)  A comprehensive application encompassing more than one
1035proposed transmission line may be good cause for alternation of
1036time limits.
1037     Section 15.  Section 403.529, Florida Statutes, is amended
1038to read:
1039     403.529  Final disposition of application.--
1040     (1)(a)  If the administrative law judge has granted a
1041request to cancel the certification hearing and has relinquished
1042jurisdiction to the department under s. 403.527(6), within 40
1043days thereafter, the secretary of the department shall act upon
1044the application by written order in accordance with the terms of
1045this act and state the reasons for issuance or denial.
1046     (b)  If the administrative law judge does not grant a
1047request to cancel the certification hearing under the provisions
1048of s. 403.527(6) within 60 30 days after receipt of the
1049administrative law judge's recommended order, the board shall
1050act upon the application by written order, approving in whole,
1051approving with such conditions as the board deems appropriate,
1052or denying the certification and stating the reasons for
1053issuance or denial.
1054     (2)  The issues that may be raised in any hearing before
1055the board shall be limited to matters raised in the
1056certification proceeding before the administrative law judge or
1057raised in the recommended order of the administrative law judge.
1058All parties, or their representatives, or persons who appear
1059before the board shall be subject to the provisions of s.
1060120.66.
1061     (3)  If certification is denied, the board, or secretary if
1062applicable, shall set forth in writing the action the applicant
1063would have to take to secure the approval of the application by
1064the board.
1065     (4)  In determining whether an application should be
1066approved in whole, approved with modifications or conditions, or
1067denied, the board, or secretary when applicable, shall consider
1068whether, and the extent to which, the location of the
1069transmission line corridor and the construction, operation, and
1070maintenance of the transmission line will:
1071     (a)  Ensure electric power system reliability and
1072integrity;
1073     (b)  Meet the electrical energy needs of the state in an
1074orderly, economical, and timely fashion;
1075     (c)  Comply with applicable nonprocedural requirements of
1076agencies;
1077     (d)  Be consistent with applicable provisions of local
1078government comprehensive plans, if any; and
1079     (e)  Effect a reasonable balance between the need for the
1080transmission line as a means of providing reliable, economically
1081efficient electric energy, as determined by the commission,
1082under s. 403.537, abundant low-cost electrical energy and the
1083impact upon the public and the environment resulting from the
1084location of the transmission line corridor and the construction,
1085operation, and maintenance of the transmission lines.
1086     (5)(a)  Any transmission line corridor certified by the
1087board, or secretary if applicable, shall meet the criteria of
1088this section. When more than one transmission line corridor is
1089proper for certification under pursuant to s. 403.522(10) and
1090meets the criteria of this section, the board, or secretary if
1091applicable, shall certify the transmission line corridor that
1092has the least adverse impact regarding the criteria in
1093subsection (4), including costs.
1094     (b)  If the board, or secretary if applicable, finds that
1095an alternate corridor rejected pursuant to s. 403.5271 meets the
1096criteria of subsection (4) and has the least adverse impact
1097regarding the criteria in subsection (4), including cost, of all
1098corridors that meet the criteria of subsection (4), then the
1099board, or secretary if applicable, shall deny certification or
1100shall allow the applicant to submit an amended application to
1101include the such corridor.
1102     (c)  If the board, or secretary if applicable, finds that
1103two or more of the corridors that comply with the provisions of
1104subsection (4) have the least adverse impacts regarding the
1105criteria in subsection (4), including costs, and that the such
1106corridors are substantially equal in adverse impacts regarding
1107the criteria in subsection (4), including costs, then the board,
1108or secretary if applicable, shall certify the corridor preferred
1109by the applicant if the corridor is one proper for certification
1110under pursuant to s. 403.522(10).
1111     (6)  The issuance or denial of the certification is by the
1112board shall be the final administrative action required as to
1113that application.
1114     Section 16.  Section 403.531, Florida Statutes, is amended
1115to read:
1116     403.531  Effect of certification.--
1117     (1)  Subject to the conditions set forth therein,
1118certification shall constitute the sole license of the state and
1119any agency as to the approval of the location of transmission
1120line corridors and the construction, operation, and maintenance
1121of transmission lines. The certification is shall be valid for
1122the life of the transmission line, if provided that construction
1123on, or condemnation or acquisition of, the right-of-way is
1124commenced within 5 years after of the date of certification or
1125such later date as may be authorized by the board.
1126     (2)(a)  The certification authorizes shall authorize the
1127licensee applicant to locate the transmission line corridor and
1128to construct and maintain the transmission lines subject only to
1129the conditions of certification set forth in the such
1130certification.
1131     (b)  The certification may include conditions that which
1132constitute variances and exemptions from nonprocedural standards
1133or rules regulations of the department or any other agency,
1134which were expressly considered during the certification review
1135proceeding unless waived by the agency as provided in s. 403.526
1136below and which otherwise would be applicable to the location of
1137the proposed transmission line corridor or the construction,
1138operation, and maintenance of the transmission lines. Each party
1139shall notify the applicant and other parties at the time
1140scheduled for the filing of the agency reports of any
1141nonprocedural requirements not specifically listed in the
1142application from which a variance, exemption, exception, or
1143other relief is necessary in order for the board to certify any
1144corridor proposed for certification. Failure of such
1145notification shall be treated as a waiver from the nonprocedural
1146requirements of that agency.
1147     (3)(a)  The certification shall be in lieu of any license,
1148permit, certificate, or similar document required by any state,
1149regional, or local agency under pursuant to, but not limited to,
1150chapter 125, chapter 161, chapter 163, chapter 166, chapter 186,
1151chapter 253, chapter 258, chapter 298, chapter 370, chapter 372,
1152chapter 373, chapter 376, chapter 380, chapter 381, chapter 387,
1153chapter 403, chapter 404, the Florida Transportation Code, or 33
1154U.S.C. s. 1341.
1155     (b)  On certification, any license, easement, or other
1156interest in state lands, except those the title of which is
1157vested in the Board of Trustees of the Internal Improvement
1158Trust Fund, shall be issued by the appropriate agency as a
1159ministerial act. The applicant shall be required to seek any
1160necessary interest in state lands the title to which is vested
1161in the Board of Trustees of the Internal Improvement Trust Fund
1162from the board of trustees before, during, or after the
1163certification proceeding, and certification may be made
1164contingent upon issuance of the appropriate interest in realty.
1165However, neither the applicant and nor any party to the
1166certification proceeding may not directly or indirectly raise or
1167relitigate any matter that which was or could have been an issue
1168in the certification proceeding in any proceeding before the
1169Board of Trustees of the Internal Improvement Trust Fund wherein
1170the applicant is seeking a necessary interest in state lands,
1171but the information presented in the certification proceeding
1172shall be available for review by the board of trustees and its
1173staff.
1174     (4)  This act does shall not in any way affect the
1175ratemaking powers of the commission under chapter 366. This act
1176does shall also not in any way affect the right of any local
1177government to charge appropriate fees or require that
1178construction be in compliance with the National Electrical
1179Safety Code, as prescribed by the commission.
1180     (5)  A No term or condition of certification may not shall
1181be interpreted to preclude the postcertification exercise by any
1182party of whatever procedural rights it may have under chapter
1183120, including those related to rulemaking proceedings.
1184     Section 17.  Section 403.5312, Florida Statutes, is amended
1185to read:
1186     403.5312  Filing Recording of notice of certified corridor
1187route.--
1188     (1)  Within 60 days after certification of a directly
1189associated transmission line under pursuant to ss. 403.501-
1190403.518 or a transmission line corridor under pursuant to ss.
1191403.52-403.5365, the applicant shall file with the department
1192and, in accordance with s. 28.222, with the clerk of the circuit
1193court for each county through which the corridor will pass, a
1194notice of the certified route.
1195     (2)  The notice must shall consist of maps or aerial
1196photographs in the scale of 1:24,000 which clearly show the
1197location of the certified route and must shall state that the
1198certification of the corridor will result in the acquisition of
1199rights-of-way within the corridor. Each clerk shall record the
1200filing in the official record of the county for the duration of
1201the certification or until such time as the applicant certifies
1202to the department and the clerk that all lands required for the
1203transmission line rights-of-way within the corridor have been
1204acquired within the such county, whichever is sooner.
1205     (3)  The recording of this notice does shall not constitute
1206a lien, cloud, or encumbrance on real property.
1207     Section 18.  Section 403.5315, Florida Statutes, is amended
1208to read:
1209     403.5315  Modification of certification.--A certification
1210may be modified after issuance in any one of the following ways:
1211     (1)  The board may delegate to the department the authority
1212to modify specific conditions in the certification.
1213     (2)  The licensee may file a petition for modification with
1214the department or the department may initiate the modification
1215upon its own initiative.
1216     (a)  A petition for modification must set forth:
1217     1.  The proposed modification;
1218     2.  The factual reasons asserted for the modification; and
1219     3.  The anticipated additional environmental effects of the
1220proposed modification.
1221     (b)(2)  The department may modify the terms and conditions
1222of the certification if no party objects in writing to the such
1223modification within 45 days after notice by mail to the last
1224address of record in the certification proceeding, and if no
1225other person whose substantial interests will be affected by the
1226modification objects in writing within 30 days after issuance of
1227public notice.
1228     (c)  If objections are raised or the department denies the
1229proposed modification, the licensee may file a request for
1230hearing on the modification with the department. Such a request
1231shall be handled pursuant to chapter 120.
1232     (d)  A request for hearing referred to the Division of
1233Administrative Hearings shall be disposed of in the same manner
1234as an application but with time periods established by the
1235administrative law judge commensurate with the significance of
1236the modification requested. If objections are raised, the
1237applicant may file a petition for modification pursuant to
1238subsection (3).
1239     (3)  The applicant or the department may file a petition
1240for modification with the department and the Division of
1241Administrative Hearings setting forth:
1242     (a)  The proposed modification;
1243     (b)  The factual reasons asserted for the modification; and
1244     (c)  The anticipated additional environmental effects of
1245the proposed modification.
1246     (4)  Petitions filed pursuant to subsection (3) shall be
1247disposed of in the same manner as an application but with time
1248periods established by the administrative law judge commensurate
1249with the significance of the modification requested.
1250     Section 19.  Section 403.5317, Florida Statutes, is created
1251to read:
1252     403.5317  Postcertification activities.--
1253     (1)(a)  If, subsequent to certification, a licensee
1254proposes any material change to the application or prior
1255amendments, the licensee shall submit to the department a
1256written request for amendment and description of the proposed
1257change to the application. The department shall, within 30 days
1258after the receipt of the request for the amendment, determine
1259whether the proposed change to the application requires a
1260modification of the conditions of certification.
1261     (b)  If the department concludes that the change would not
1262require a modification of the conditions of certification, the
1263department shall notify, in writing, the licensee, all agencies,
1264and all parties of the approval of the amendment.
1265     (c)  If the department concludes that the change would
1266require a modification of the conditions of certification, the
1267department shall notify the licensee that the proposed change to
1268the application requires a request for modification under s.
1269403.5315.
1270     (2)  Postcertification submittals filed by a licensee with
1271one or more agencies are for the purpose of monitoring for
1272compliance with the issued certification. Each submittal must be
1273reviewed by each agency on an expedited and priority basis
1274because each facility certified under this act is a critical
1275infrastructure facility. Postcertification review may not be
1276completed more than 90 days after complete information for a
1277segment of the certified transmission line is submitted to the
1278reviewing agencies.
1279     Section 20.  Section 403.5363, Florida Statutes, is created
1280to read:
1281     403.5363  Public notices; requirements.--
1282     (1)(a)  The applicant shall arrange for the publication of
1283the notices specified in paragraph (b).
1284     1.  The notices shall be published in newspapers of general
1285circulation within counties crossed by the transmission line
1286corridors proper for certification. The required newspaper
1287notices for filing of an application and for the certification
1288hearing shall be one-half page in size in a standard-size
1289newspaper or a full page in a tabloid-size newspaper and
1290published in a section of the newspaper other than the section
1291for legal notices. These two notices must include a map
1292generally depicting all transmission corridors proper for
1293certification. A newspaper of general circulation shall be the
1294newspaper within a county crossed by a transmission line
1295corridor proper for certification which newspaper has the
1296largest daily circulation in that county and has its principal
1297office in that county. If the newspaper having the largest daily
1298circulation has its principal office outside the county, the
1299notices must appear in both the newspaper having the largest
1300circulation in that county and in a newspaper authorized to
1301publish legal notices in that county.
1302     2.  The department shall adopt rules specifying the content
1303of the newspaper notices.
1304     3.  All notices published by the applicant shall be paid
1305for by the applicant and shall be in addition to the application
1306fee.
1307     (b)  Public notices that must be published under this
1308section include:
1309     1.  The notice of the filing of an application, which must
1310include a description of the proceedings required by this act.
1311The notice must describe the provisions of s. 403.531(1) and (2)
1312and give the date by which notice of intent to be a party or a
1313petition to intervene in accordance with s. 403.527(2) must be
1314filed. This notice must be published no more than 21 days after
1315the application is filed.
1316     2.  The notice of the certification hearing and any other
1317public hearing permitted under s. 403.527. The notice must
1318include the date by which a person wishing to appear as a party
1319must file the notice to do so. The notice of the certification
1320hearing must be published at least 65 days before the date set
1321for the certification hearing.
1322     3.  The notice of the cancellation of the certification
1323hearing, if applicable. The notice must be published at least 3
1324days before the date of the originally scheduled certification
1325hearing.
1326     4.  The notice of the filing of a proposal to modify the
1327certification submitted under s. 403.5315, if the department
1328determines that the modification would require relocation or
1329expansion of the transmission line right-of-way or a certified
1330substation.
1331     (2)  The proponent of an alternate corridor shall arrange
1332for the publication of the filing of the proposal for an
1333alternate corridor, the revised time schedules, the date by
1334which newly affected persons or agencies may file the notice of
1335intent to become a party, and the date of the rescheduled
1336hearing. A notice listed in this subsection must be published in
1337a newspaper of general circulation within the county or counties
1338crossed by the proposed alternate corridor and comply with the
1339content requirements set forth in paragraph (1)(a). The notice
1340must be published not less than 50 days before the rescheduled
1341certification hearing.
1342     (3)  The department shall arrange for the publication of
1343the following notices in the manner specified by chapter 120:
1344     (a)  The notice of the filing of an application and the
1345date by which a person intending to become a party must file the
1346notice of intent. The notice must be published no later than 21
1347days after the application has been filed.
1348     (b)  The notice of any administrative hearing for
1349certification, if applicable. The notice must be published not
1350less than 65 days before the date set for a hearing, except that
1351notice for a rescheduled certification hearing after acceptance
1352of an alternative corridor must be published not less than 50
1353days before the date set for the hearing.
1354     (c)  The notice of the cancellation of a certification
1355hearing, if applicable. The notice must be published not later
1356than 7 days before the date of the originally scheduled
1357certification hearing.
1358     (d)  The notice of the hearing before the siting board, if
1359applicable.
1360     (e)  The notice of stipulations, proposed agency action, or
1361a petition for modification.
1362     Section 21.  Section 403.5365, Florida Statutes, is amended
1363to read:
1364     403.5365  Fees; disposition.--The department shall charge
1365the applicant the following fees, as appropriate, which, unless
1366otherwise specified, shall be paid into the Florida Permit Fee
1367Trust Fund:
1368     (1)  An application fee.
1369     (a)  The application fee shall be of $100,000, plus $750
1370per mile for each mile of corridor in which the transmission
1371line right-of-way is proposed to be located within an existing
1372electric electrical transmission line right-of-way or within any
1373existing right-of-way for any road, highway, railroad, or other
1374aboveground linear facility, or $1,000 per mile for each mile of
1375electric transmission line corridor proposed to be located
1376outside the such existing right-of-way.
1377     (b)(a)  Sixty percent of the fee shall go to the department
1378to cover any costs associated with coordinating the review of
1379reviewing and acting upon the application and any costs for
1380field services associated with monitoring construction and
1381operation of the electric transmission line facility.
1382     (c)(b)  The following percentage Twenty percent of the fees
1383specified under this section, except postcertification fees,
1384shall be transferred to the Administrative Trust Fund of the
1385Division of Administrative Hearings of the Department of
1386Management Services:.
1387     1.  Five percent to compensate for expenses from the
1388initial exercise of duties associated with the filing of an
1389application.
1390     2.  An additional 10 percent if an administrative hearing
1391under s. 403.527 is held.
1392     (d)1.(c)  Upon written request with proper itemized
1393accounting within 90 days after final agency action by the
1394siting board or the department or the withdrawal of the
1395application, the agencies that prepared reports under s. 403.526
1396or s. 403.5271 or participated in a hearing under s. 403.527 or
1397s. 403.5271 may submit a written request to the department for
1398reimbursement of expenses incurred during the certification
1399proceedings. The request must contain an accounting of expenses
1400incurred, which may include time spent reviewing the
1401application, department shall reimburse the expenses and costs
1402of the Department of Community Affairs, the Fish and Wildlife
1403Conservation Commission, the water management district, regional
1404planning council, and local government in the jurisdiction of
1405which the transmission line is to be located. Such reimbursement
1406shall be authorized for the preparation of any studies required
1407of the agencies by this act, and for agency travel and per diem
1408to attend any hearing held under pursuant to this act, and for
1409the local government or regional planning council providing
1410additional notice of the informational public meeting. The
1411department shall review the request and verify whether a claimed
1412expense is valid. Valid expenses shall be reimbursed; however,
1413if to participate in the proceedings. In the event the amount of
1414funds available for reimbursement allocation is insufficient to
1415provide for full compensation complete reimbursement to the
1416agencies, reimbursement shall be on a prorated basis.
1417     2.  If the application review is held in abeyance for more
1418than 1 year, the agencies may submit a request for reimbursement
1419under subparagraph 1.
1420     (e)(d)  If any sums are remaining, the department shall
1421retain them for its use in the same manner as is otherwise
1422authorized by this section; provided, however, that if the
1423certification application is withdrawn, the remaining sums shall
1424be refunded to the applicant within 90 days after withdrawal.
1425     (2)  An amendment fee.
1426     (a)  If no corridor alignment change is proposed by the
1427amendment, no amendment fee shall be charged.
1428     (b)  If a corridor alignment change under s. 403.5275 is
1429proposed by the applicant, an additional fee of a minimum of
1430$2,000 and $750 per mile shall be submitted to the department
1431for use in accordance with this act.
1432     (c)  If an amendment is required to address issues,
1433including alternate corridors under pursuant to s. 403.5271,
1434raised by the department or other parties, no fee for the such
1435amendment shall be charged.
1436     (3)  A certification modification fee.
1437     (a)  If no corridor alignment change is proposed by the
1438licensee applicant, the modification fee shall be $4,000.
1439     (b)  If a corridor alignment change is proposed by the
1440licensee applicant, the fee shall be $1,000 for each mile of
1441realignment plus an amount not to exceed $10,000 to be fixed by
1442rule on a sliding scale based on the load-carrying capability
1443and configuration of the transmission line for use in accordance
1444with subsection (1) (2).
1445     Section 22.  Subsection (1) of section 403.537, Florida
1446Statutes, is amended to read:
1447     403.537  Determination of need for transmission line;
1448powers and duties.--
1449     (1)(a)  Upon request by an applicant or upon its own
1450motion, the Florida Public Service Commission shall schedule a
1451public hearing, after notice, to determine the need for a
1452transmission line regulated by the Florida Electric Transmission
1453Line Siting Act, ss. 403.52-403.5365. The Such notice shall be
1454published at least 21 45 days before the date set for the
1455hearing and shall be published by the applicant in at least one-
1456quarter page size notice in newspapers of general circulation,
1457and by the commission in the manner specified in chapter 120 in
1458the Florida Administrative Weekly, by giving notice to counties
1459and regional planning councils in whose jurisdiction the
1460transmission line could be placed, and by giving notice to any
1461persons who have requested to be placed on the mailing list of
1462the commission for this purpose. Within 21 days after receipt of
1463a request for determination by an applicant, the commission
1464shall set a date for the hearing. The hearing shall be held
1465pursuant to s. 350.01 within 45 days after the filing of the
1466request, and a decision shall be rendered within 60 days after
1467such filing.
1468     (b)  The commission shall be the sole forum in which to
1469determine the need for a transmission line. The need for a
1470transmission line may not be raised or be the subject of review
1471in another proceeding.
1472     (c)(b)  In the determination of need, the commission shall
1473take into account the need for electric system reliability and
1474integrity, the need for abundant, low-cost electrical energy to
1475assure the economic well-being of the residents citizens of this
1476state, the appropriate starting and ending point of the line,
1477and other matters within its jurisdiction deemed relevant to the
1478determination of need. The appropriate starting and ending
1479points of the electric transmission line must be verified by the
1480commission in its determination of need.
1481     (d)(c)  The determination by the commission of the need for
1482the transmission line, as defined in s. 403.522(22) s.
1483403.522(21), is binding on all parties to any certification
1484proceeding under pursuant to the Florida Electric Transmission
1485Line Siting Act and is a condition precedent to the conduct of
1486the certification hearing prescribed therein. An order entered
1487pursuant to this section constitutes final agency action.
1488     Section 23.  Subsection (3) of section 373.441, Florida
1489Statutes, is amended to read:
1490     373.441  Role of counties, municipalities, and local
1491pollution control programs in permit processing.--
1492     (3)  The department shall review environmental resource
1493permit applications for electrical distribution and transmission
1494lines and other facilities related to the production,
1495transmission, and distribution of electricity which are not
1496certified under ss. 403.52-403.5365, the Florida Electric
1497Transmission Line Siting Act, regulated under this part.
1498     Section 24.  Subsection (30) of section 403.061, Florida
1499Statutes, is amended to read:
1500     403.061  Department; powers and duties.--The department
1501shall have the power and the duty to control and prohibit
1502pollution of air and water in accordance with the law and rules
1503adopted and promulgated by it and, for this purpose, to:
1504     (30)  Establish requirements by rule that reasonably
1505protect the public health and welfare from electric and magnetic
1506fields associated with existing 230 kV or greater electrical
1507transmission lines, new 230 kV and greater electrical
1508transmission lines for which an application for certification
1509under the Florida Electric Transmission Line Siting Act, ss.
1510403.52-403.5365, is not filed, new or existing electrical
1511transmission or distribution lines with voltage less than 230
1512kV, and substation facilities. Notwithstanding any other
1513provision in this chapter or any other law of this state or
1514political subdivision thereof, the department shall have
1515exclusive jurisdiction in the regulation of electric and
1516magnetic fields associated with all electrical transmission and
1517distribution lines and substation facilities. However, nothing
1518herein shall be construed as superseding or repealing the
1519provisions of s. 403.523(1) and (10).
1520
1521The department shall implement such programs in conjunction with
1522its other powers and duties and shall place special emphasis on
1523reducing and eliminating contamination that presents a threat to
1524humans, animals or plants, or to the environment.
1525     Section 25.  Paragraph (a) of subsection (3) of section
1526403.0876, Florida Statutes, is amended to read:
1527     403.0876  Permits; processing.--
1528     (3)(a)  The department shall establish a special unit for
1529permit coordination and processing to provide expeditious
1530processing of department permits which the district offices are
1531unable to process expeditiously and to provide accelerated
1532processing of certain permits or renewals for economic and
1533operating stability. The ability of the department to process
1534applications under pursuant to this subsection in a more timely
1535manner than allowed by subsections (1) and (2) is dependent upon
1536the timely exchange of information between the applicant and the
1537department and the intervention of outside parties as allowed by
1538law. An applicant may request the processing of its permit
1539application by the special unit if the application is from an
1540area of high unemployment or low per capita income, is from a
1541business or industry that is the primary employer within an
1542area's labor market, or is in an industry with respect to which
1543the complexities involved in the review of the application
1544require special skills uniquely available in the headquarters
1545office. The department may require the applicant to waive the
154690-day time limitation for department issuance or denial of the
1547permit once for a period not to exceed 90 days. The department
1548may require a special fee to cover the direct cost of processing
1549special applications in addition to normal permit fees and
1550costs. The special fee may not exceed $10,000 per permit
1551required. Applications for renewal permits, but not applications
1552for initial permits, required for facilities pursuant to the
1553Electrical Power Plant Siting Act or the Florida Electric
1554Transmission Line Siting Act may be processed under this
1555subsection. Personnel staffing the special unit shall have
1556lengthy experience in permit processing.
1557     Section 26.  Paragraph (b) of subsection (3) of section
1558403.809, Florida Statutes, is amended to read:
1559     403.809  Environmental districts; establishment; managers;
1560functions.--
1561     (3)
1562     (b)  The processing of all applications for permits,
1563licenses, certificates, and exemptions shall be accomplished at
1564the district center or the branch office, except for those
1565applications specifically assigned elsewhere in the department
1566under s. 403.805 or to the water management districts under s.
1567403.812 and those applications assigned by interagency agreement
1568as provided in this act. However, the secretary, as head of the
1569department, may not delegate to district or subdistrict
1570managers, water management districts, or any unit of local
1571government the authority to act on the following types of permit
1572applications:
1573     1.  Permits issued under s. 403.0885, except such permit
1574issuance may be delegated to district managers.
1575     2.  Construction of major air pollution sources.
1576     3.  Certifications under the Florida Electrical Power Plant
1577Siting Act or the Florida Electric Transmission Line Siting Act
1578and the associated permit issued under s. 403.0885, if
1579applicable.
1580     4.  Permits issued under s. 403.0885 to steam electric
1581generating facilities regulated pursuant to 40 C.F.R. part 423.
1582     5.  Permits issued under s. 378.901.
1583     Section 27.  Sections 403.5253 and 403.5369, Florida
1584Statutes, are repealed.
1585     Section 28.  This act shall take effect upon becoming a
1586law.


CODING: Words stricken are deletions; words underlined are additions.