1 | A bill to be entitled |
2 | An act relating to the siting of electric transmission |
3 | lines; amending s. 403.52, F.S.; changing the short title |
4 | to the "Florida Electric Transmission Line Siting Act"; |
5 | amending s. 403.521, F.S.; revising legislative intent; |
6 | amending s. 403.522, F.S.; revising definitions; defining |
7 | the terms "licensee" and "maintenance and access roads"; |
8 | amending s. 403.523, F.S.; revising powers and duties of |
9 | the Department of Environmental Protection; requiring the |
10 | department to collect and process fees, to prepare a |
11 | project analysis, to act as clerk for the siting board, |
12 | and to administer and manage the terms and conditions of |
13 | the certification order and supporting documents and |
14 | records; amending s. 403.524, F.S.; revising provisions |
15 | for applicability, certification, and exemptions under the |
16 | act; revising provisions for notice by an electric utility |
17 | of its intent to construct an exempt transmission line; |
18 | amending s. 403.525, F.S.; providing for powers and duties |
19 | of the administrative law judge designated by the Division |
20 | of Administrative Hearings to conduct the required |
21 | hearings; amending s. 403.5251, F.S.; revising application |
22 | procedures and schedules; providing for the formal date of |
23 | filing an application for certification and commencement |
24 | of the certification review process; requiring the |
25 | department to prepare a proposed schedule of dates for |
26 | determination of completeness and other significant dates |
27 | to be followed during the certification process; providing |
28 | for the formal date of application distribution; requiring |
29 | the applicant to provide notice of filing the application; |
30 | amending s. 403.5252, F.S.; revising timeframes and |
31 | procedures for determination of completeness of the |
32 | application; requiring the department to consult with |
33 | affected agencies; revising requirements for the |
34 | department to file a statement of its determination of |
35 | completeness with the Division of Administrative Hearings, |
36 | the applicant, and all parties within a certain time after |
37 | distribution of the application; revising requirements for |
38 | the applicant to file a statement with the department, the |
39 | division, and all parties, if the department determines |
40 | the application is not complete; providing for the |
41 | statement to notify the department whether the information |
42 | will be provided; revising timeframes and procedures for |
43 | contests of the determination by the department; providing |
44 | for parties to a hearing on the issue of completeness; |
45 | amending s. 403.526, F.S.; revising criteria and |
46 | procedures for preliminary statements of issues, reports, |
47 | and studies; revising timeframes; requiring that the |
48 | preliminary statement of issues from each affected agency |
49 | be submitted to the department and the applicant; revising |
50 | criteria for the Department of Community Affairs' report; |
51 | requiring the Department of Transportation, the Public |
52 | Service Commission, and any other affected agency to |
53 | prepare a project report; revising required content of the |
54 | report; providing for notice of any nonprocedural |
55 | requirements not listed in the application; providing for |
56 | failure to provide such notification; providing for a |
57 | recommendation for approval or denial of the application; |
58 | providing that receipt of an affirmative determination of |
59 | need is a condition precedent to further processing of the |
60 | application; requiring that the department prepare a |
61 | project analysis to be filed with the administrative law |
62 | judge and served on all parties within a certain time; |
63 | amending s. 403.527, F.S.; revising procedures and |
64 | timeframes for the certification hearing conducted by the |
65 | administrative law judge; revising provisions for notices |
66 | and publication of notices, public hearings held by local |
67 | governments, testimony at the public-hearing portion of |
68 | the certification hearing, the order of presentations at |
69 | the hearing, and consideration of certain communications |
70 | by the administrative law judge; requiring the applicant |
71 | to pay certain expenses and costs; requiring the |
72 | administrative law judge to issue a recommended order |
73 | disposing of the application; requiring that certain |
74 | notices be made in accordance with specified requirements |
75 | and within a certain time; requiring the Department of |
76 | Transportation to be a party to the proceedings; providing |
77 | for the administrative law judge to cancel the |
78 | certification hearing and relinquish jurisdiction to the |
79 | Department of Environmental Protection upon request by the |
80 | applicant or the department; requiring the department and |
81 | the applicant to publish notice of such cancellation; |
82 | providing for parties to submit proposed recommended |
83 | orders to the department when the certification hearing |
84 | has been canceled; providing that the department prepare a |
85 | recommended order for final action by the siting board |
86 | when the hearing has been canceled; amending s. 403.5271, |
87 | F.S.; revising procedures and timeframes for consideration |
88 | of proposed alternate corridors; revising notice |
89 | requirements; providing for notice of the filing of the |
90 | alternate corridor and revised time schedules; providing |
91 | for notice to agencies newly affected by the proposed |
92 | alternate corridor; requiring the person proposing the |
93 | alternate corridor to provide all data to the agencies |
94 | within a certain time; providing for a determination by |
95 | the department that the data is not complete; providing |
96 | for withdrawal of the proposed alternate corridor upon |
97 | such determination; requiring that agencies file reports |
98 | with the applicant and the department which address the |
99 | proposed alternate corridor; requiring that the department |
100 | file with the administrative law judge, the applicant, and |
101 | all parties a project analysis of the proposed alternate |
102 | corridor; providing that the party proposing an alternate |
103 | corridor has the burden of proof concerning the |
104 | certifiability of the alternate corridor; amending s. |
105 | 403.5272, F.S.; revising procedures for informational |
106 | public meetings; providing for informational public |
107 | meetings held by regional planning councils; revising |
108 | timeframes; amending s. 403.5275, F.S.; revising |
109 | provisions for amendment to the application prior to |
110 | certification; amending s. 403.528, F.S.; providing that a |
111 | comprehensive application encompassing more than one |
112 | proposed transmission line may be good cause for altering |
113 | established time limits; amending s. 403.529, F.S.; |
114 | revising provisions for final disposition of the |
115 | application by the siting board; providing for the |
116 | administrative law judge's or department's recommended |
117 | order; amending s. 403.531, F.S.; revising provisions for |
118 | conditions of certification; amending s. 403.5312, F.S.; |
119 | requiring the applicant to file notice of a certified |
120 | corridor route with the department; amending s. 403.5315, |
121 | F.S.; revising the circumstances under which a |
122 | certification may be modified after the certification has |
123 | been issued; providing for procedures if objections are |
124 | raised to the proposed modification; creating s. 403.5317, |
125 | F.S.; providing procedures for changes proposed by the |
126 | licensee after certification; requiring the department to |
127 | determine within a certain time if the proposed change |
128 | requires modification of the conditions of certification; |
129 | requiring notice to the licensee, all agencies, and all |
130 | parties of changes that are approved as not requiring |
131 | modification of the conditions of certification; creating |
132 | s. 403.5363, F.S.; requiring publication of certain |
133 | notices by the applicant, the proponent of an alternate |
134 | corridor, and the department; requiring the department to |
135 | adopt rules specifying the content of such notices; |
136 | amending s. 403.5365, F.S.; revising application fees and |
137 | the distribution of fees collected; revising procedures |
138 | for reimbursement of local governments and regional |
139 | planning organizations; amending s. 403.537, F.S.; |
140 | revising the schedule for notice of a public hearing by |
141 | the Public Service Commission in order to determine the |
142 | need for a transmission line; providing that the |
143 | commission is the sole forum in which to determine the |
144 | need for a transmission line; amending ss. 373.441, |
145 | 403.061, 403.0876, and 403.809, F.S.; conforming |
146 | terminology to changes made by the act; repealing ss. |
147 | 403.5253 and 403.5369, F.S., relating to determination of |
148 | sufficiency of application or amendment to the application |
149 | and the application of the act to applications filed |
150 | before a certain date; providing an effective date. |
151 |
|
152 | Be It Enacted by the Legislature of the State of Florida: |
153 |
|
154 | Section 1. Section 403.52, Florida Statutes, is amended to |
155 | read: |
156 | 403.52 Short title.--Sections 403.52-403.5365 may be cited |
157 | as the "Florida Electric Transmission Line Siting Act." |
158 | Section 2. Section 403.521, Florida Statutes, is amended |
159 | to read: |
160 | 403.521 Legislative intent.--The legislative intent of |
161 | this act is to establish a centralized and coordinated licensing |
162 | permitting process for the location of electric transmission |
163 | line corridors and the construction, operation, and maintenance |
164 | of electric transmission lines, which are critical |
165 | infrastructure facilities. This necessarily involves several |
166 | broad interests of the public addressed through the subject |
167 | matter jurisdiction of several agencies. The Legislature |
168 | recognizes that electric transmission lines will have an effect |
169 | upon the reliability of the electric power system, the |
170 | environment, land use, and the welfare of the population. |
171 | Recognizing the need to ensure electric power system reliability |
172 | and integrity, and in order to meet electric electrical energy |
173 | needs in an orderly and timely fashion, the centralized and |
174 | coordinated licensing permitting process established by this act |
175 | is intended to further the legislative goal of ensuring through |
176 | available and reasonable methods that the location of |
177 | transmission line corridors and the construction, operation, and |
178 | maintenance of electric transmission lines produce minimal |
179 | adverse effects on the environment and public health, safety, |
180 | and welfare while not unduly conflicting with the goals |
181 | established by the applicable local comprehensive plan. It is |
182 | the intent of this act to fully balance the need for |
183 | transmission lines with the broad interests of the public in |
184 | order to effect a reasonable balance between the need for the |
185 | facility as a means of providing reliable, economical, and |
186 | efficient electric abundant low-cost electrical energy and the |
187 | impact on the public and the environment resulting from the |
188 | location of the transmission line corridor and the construction, |
189 | operation, and maintenance of the transmission lines. The |
190 | Legislature intends that the provisions of chapter 120 apply to |
191 | this act and to proceedings under pursuant to it except as |
192 | otherwise expressly exempted by other provisions of this act. |
193 | Section 3. Section 403.522, Florida Statutes, is amended |
194 | to read: |
195 | 403.522 Definitions relating to the Florida Electric |
196 | Transmission Line Siting Act.--As used in this act: |
197 | (1) "Act" means the Florida Electric Transmission Line |
198 | Siting Act. |
199 | (2) "Agency," as the context requires, means an official, |
200 | officer, commission, authority, council, committee, department, |
201 | division, bureau, board, section, or other unit or entity of |
202 | government, including a county, municipality, or other regional |
203 | or local governmental entity. |
204 | (3) "Amendment" means a material change in information |
205 | provided by the applicant to the application for certification |
206 | made after the initial application filing. |
207 | (4) "Applicant" means any electric utility that which |
208 | applies for certification under pursuant to the provisions of |
209 | this act. |
210 | (5) "Application" means the documents required by the |
211 | department to be filed to initiate and support a certification |
212 | review and evaluation, including the initial document filing, |
213 | amendments, and responses to requests from the department for |
214 | additional data and information proceeding. An electric utility |
215 | may file a comprehensive application encompassing all or a part |
216 | of one or more proposed transmission lines. |
217 | (6) "Board" means the Governor and Cabinet sitting as the |
218 | siting board. |
219 | (7) "Certification" means the approval by the board of the |
220 | license for a corridor proper for certification pursuant to |
221 | subsection (10) and the construction, operation, and maintenance |
222 | of transmission lines within the such corridor with the such |
223 | changes or conditions as the siting board deems appropriate. |
224 | Certification shall be evidenced by a written order of the |
225 | board. |
226 | (8) "Commission" means the Florida Public Service |
227 | Commission. |
228 | (9) "Completeness" means that the application has |
229 | addressed all applicable sections of the prescribed application |
230 | format and, but does not mean that those sections are sufficient |
231 | in comprehensiveness of data or in quality of information |
232 | provided to allow the department to determine whether the |
233 | application provides the reviewing agencies adequate information |
234 | to prepare the reports required by s. 403.526. |
235 | (10) "Corridor" means the proposed area within which a |
236 | transmission line right-of-way, including maintenance and access |
237 | roads, is to be located. The width of the corridor proposed for |
238 | certification by an applicant or other party, at the option of |
239 | the applicant, may be the width of the transmission line right- |
240 | of-way, or a wider boundary, not to exceed a width of 1 mile. |
241 | The area within the corridor in which a right-of-way may be |
242 | located may be further restricted by a condition of |
243 | certification. After all property interests required for the |
244 | transmission line right-of-way and maintenance and access roads |
245 | have been acquired by the applicant, the boundaries of the area |
246 | certified shall narrow to only that land within the boundaries |
247 | of the transmission line right-of-way. The corridors proper for |
248 | certification shall be those addressed in the application, in |
249 | amendments to the application filed under pursuant to s. |
250 | 403.5275, and in notices of acceptance of proposed alternate |
251 | corridors filed by an applicant and the department pursuant to |
252 | s. 403.5271 for which the required sufficient information for |
253 | the preparation of agency supplemental reports was filed. |
254 | (11) "Department" means the Department of Environmental |
255 | Protection. |
256 | (12) "Electric utility" means cities and towns, counties, |
257 | public utility districts, regulated electric companies, electric |
258 | cooperatives, regional transmission organizations, operators of |
259 | independent transmission systems, or other transmission |
260 | organizations approved by the Federal Energy Regulatory |
261 | Commission or the commission for the operation of transmission |
262 | facilities, and joint operating agencies, or combinations |
263 | thereof, engaged in, or authorized to engage in, the business of |
264 | generating, transmitting, or distributing electric energy. |
265 | (13) "License" means a franchise, permit, certification, |
266 | registration, charter, comprehensive plan amendment, development |
267 | order, or permit as defined in chapters 163 and 380, or similar |
268 | form of authorization required by law, but it does not include a |
269 | license required primarily for revenue purposes when issuance of |
270 | the license is merely a ministerial act. |
271 | (14) "Licensee" means an applicant that has obtained a |
272 | certification order for the subject project. |
273 | (15)(14) "Local government" means a municipality or county |
274 | in the jurisdiction of which the project is proposed to be |
275 | located. |
276 | (16) "Maintenance and access roads" mean roads constructed |
277 | within the transmission line right-of-way. Nothing in this act |
278 | prohibits an applicant from constructing a road to support |
279 | construction, operation, or maintenance of the transmission line |
280 | that lies outside the transmission line right-of-way. |
281 | (17)(15) "Modification" means any change in the |
282 | certification order after issuance, including a change in the |
283 | conditions of certification. |
284 | (18)(16) "Nonprocedural requirements of agencies" means |
285 | any agency's regulatory requirements established by statute, |
286 | rule, ordinance, or comprehensive plan, excluding any provisions |
287 | prescribing forms, fees, procedures, or time limits for the |
288 | review or processing of information submitted to demonstrate |
289 | compliance with such regulatory requirements. |
290 | (19)(17) "Person" means an individual, partnership, joint |
291 | venture, private or public corporation, association, firm, |
292 | public service company, political subdivision, municipal |
293 | corporation, government agency, public utility district, or any |
294 | other entity, public or private, however organized. |
295 | (20)(18) "Preliminary statement of issues" means a listing |
296 | and explanation of those issues within the agency's jurisdiction |
297 | which are of major concern to the agency in relation to the |
298 | proposed electric electrical transmission line corridor. |
299 | (21)(19) "Regional planning council" means a regional |
300 | planning council as defined in s. 186.503(4) in the jurisdiction |
301 | of which the project is proposed to be located. |
302 | (20) "Sufficiency" means that the application is not only |
303 | complete but that all sections are adequate in the |
304 | comprehensiveness of data and in the quality of information |
305 | provided to allow the department to determine whether the |
306 | application provides the reviewing agencies adequate information |
307 | to prepare the reports authorized by s. 403.526. |
308 | (22)(21) "Transmission line" or "electric transmission |
309 | line" means structures, maintenance and access roads, and all |
310 | other facilities that need to be constructed, operated, or |
311 | maintained for the purpose of conveying electric power any |
312 | electrical transmission line extending from, but not including, |
313 | an existing or proposed substation or power plant to, but not |
314 | including, an existing or proposed transmission network or |
315 | rights-of-way or substation to which the applicant intends to |
316 | connect which defines the end of the proposed project and which |
317 | is designed to operate at 230 kilovolts or more. The starting |
318 | point and ending point of a transmission line must be |
319 | specifically defined by the applicant and must be verified by |
320 | the commission in its determination of need. A transmission line |
321 | includes structures and maintenance and access roads that need |
322 | to be constructed for the project to become operational. The |
323 | transmission line may include, at the applicant's option, any |
324 | proposed terminal or intermediate substations or substation |
325 | expansions necessary to serve the transmission line. |
326 | (23)(22) "Transmission line right-of-way" means land |
327 | necessary for the construction, operation, and maintenance of a |
328 | transmission line. The typical width of the right-of-way shall |
329 | be identified in the application. The right-of-way shall be |
330 | located within the certified corridor and shall be identified by |
331 | the applicant subsequent to certification in documents filed |
332 | with the department before prior to construction. |
333 | (24)(23) "Water management district" means a water |
334 | management district created pursuant to chapter 373 in the |
335 | jurisdiction of which the project is proposed to be located. |
336 | Section 4. Section 403.523, Florida Statutes, is amended |
337 | to read: |
338 | 403.523 Department of Environmental Protection; powers and |
339 | duties.--The department has shall have the following powers and |
340 | duties: |
341 | (1) To adopt procedural rules pursuant to ss. 120.536(1) |
342 | and 120.54 to administer implement the provisions of this act |
343 | and to adopt or amend rules to implement the provisions of |
344 | subsection (10). |
345 | (2) To prescribe the form and content of the public |
346 | notices and the form, content, and necessary supporting |
347 | documentation, and any required studies, for certification |
348 | applications. All such data and studies shall be related to the |
349 | jurisdiction of the agencies relevant to the application. |
350 | (3) To receive applications for transmission line and |
351 | corridor certifications and initially determine the completeness |
352 | and sufficiency thereof. |
353 | (4) To make or contract for studies of certification |
354 | applications. All such studies shall be related to the |
355 | jurisdiction of the agencies relevant to the application. For |
356 | studies in areas outside the jurisdiction of the department and |
357 | in the jurisdiction of another agency, the department may |
358 | initiate such studies, but only with the consent of the such |
359 | agency. |
360 | (5) To administer the processing of applications for |
361 | certification and ensure that the applications, including |
362 | postcertification reviews, are processed on an expeditious and |
363 | priority basis as expeditiously as possible. |
364 | (6) To collect and process require such fees as allowed by |
365 | this act. |
366 | (7) To prepare a report and project written analysis as |
367 | required by s. 403.526. |
368 | (8) To prescribe the means for monitoring the effects |
369 | arising from the location of the transmission line corridor and |
370 | the construction, operation, and maintenance of the transmission |
371 | lines to assure continued compliance with the terms of the |
372 | certification. |
373 | (9) To make a determination of acceptability of any |
374 | alternate corridor proposed for consideration under pursuant to |
375 | s. 403.5271. |
376 | (10) To set requirements that reasonably protect the |
377 | public health and welfare from the electric and magnetic fields |
378 | of transmission lines for which an application is filed under |
379 | after the effective date of this act. |
380 | (11) To present rebuttal evidence on any issue properly |
381 | raised at the certification hearing. |
382 | (12) To issue final orders after receipt of the |
383 | administrative law judge's order relinquishing jurisdiction |
384 | pursuant to s. 403.527(6). |
385 | (13) To act as clerk for the siting board. |
386 | (14) To administer and manage the terms and conditions of |
387 | the certification order and supporting documents and records for |
388 | the life of the facility. |
389 | (15) To issue emergency orders on behalf of the board for |
390 | facilities licensed under this act. |
391 | Section 5. Section 403.524, Florida Statutes, is amended |
392 | to read: |
393 | 403.524 Applicability; and certification; exemptions.-- |
394 | (1) The provisions of This act applies apply to each |
395 | transmission line, except a transmission line certified under |
396 | pursuant to the Florida Electrical Power Plant Siting Act. |
397 | (2) Except as provided in subsection (1), no construction |
398 | of a any transmission line may not be undertaken without first |
399 | obtaining certification under this act, but the provisions of |
400 | this act does do not apply to: |
401 | (a) Transmission lines for which development approval has |
402 | been obtained under pursuant to chapter 380. |
403 | (b) Transmission lines that which have been exempted by a |
404 | binding letter of interpretation issued under s. 380.06(4), or |
405 | in which the Department of Community Affairs or its predecessor |
406 | agency has determined the utility to have vested development |
407 | rights within the meaning of s. 380.05(18) or s. 380.06(20). |
408 | (c) Transmission line development in which all |
409 | construction is limited to established rights-of-way. |
410 | Established rights-of-way include such rights-of-way established |
411 | at any time for roads, highways, railroads, gas, water, oil, |
412 | electricity, or sewage and any other public purpose rights-of- |
413 | way. If an established transmission line right-of-way is used to |
414 | qualify for this exemption, the transmission line right-of-way |
415 | must have been established at least 5 years before notice of the |
416 | start of construction under subsection (4) of the proposed |
417 | transmission line. If an established transmission line right-of- |
418 | way is relocated to accommodate a public project, the date the |
419 | original transmission line right-of-way was established applies |
420 | to the relocated transmission line right-of-way for purposes of |
421 | this exemption. Except for transmission line rights-of-way, |
422 | established rights-of-way include rights-of-way created before |
423 | or after October 1, 1983. For transmission line rights-of-way, |
424 | established rights-of-way include rights-of-way created before |
425 | October 1, 1983. |
426 | (d) Unless the applicant has applied for certification |
427 | under this act, transmission lines that which are less than 15 |
428 | miles in length or are located in a single which do not cross a |
429 | county within the state line, unless the applicant has elected |
430 | to apply for certification under the act. |
431 | (3) The exemption of a transmission line under this act |
432 | does not constitute an exemption for the transmission line from |
433 | other applicable permitting processes under other provisions of |
434 | law or local government ordinances. |
435 | (4) An electric A utility shall notify the department in |
436 | writing, before prior to the start of construction, of its |
437 | intent to construct a transmission line exempted under pursuant |
438 | to this section. The Such notice is shall be only for |
439 | information purposes, and no action by the department is not |
440 | shall be required pursuant to the such notice. This notice may |
441 | be included in any submittal filed with the department before |
442 | the start of construction demonstrating that a new transmission |
443 | line complies with the applicable electric and magnetic field |
444 | standards. |
445 | Section 6. Section 403.525, Florida Statutes, is amended |
446 | to read: |
447 | 403.525 Appointment of Administrative law judge; |
448 | appointment; powers and duties.-- |
449 | (1)(a) Within 7 days after receipt of an application, |
450 | whether complete or not, the department shall request the |
451 | Division of Administrative Hearings to designate an |
452 | administrative law judge to conduct the hearings required by |
453 | this act. |
454 | (b) The division director shall designate an |
455 | administrative law judge to conduct the hearings required by |
456 | this act within 7 days after receipt of the request from the |
457 | department. Whenever practicable, the division director shall |
458 | assign an administrative law judge who has had prior experience |
459 | or training in this type of certification proceeding. |
460 | (c) Upon being advised that an administrative law judge |
461 | has been designated, the department shall immediately file a |
462 | copy of the application and all supporting documents with the |
463 | administrative law judge, who shall docket the application. |
464 | (2) The administrative law judge has all powers and duties |
465 | granted to administrative law judges under chapter 120 and by |
466 | the laws and rules of the department. |
467 | Section 7. Section 403.5251, Florida Statutes, is amended |
468 | to read: |
469 | 403.5251 Distribution of Application; schedules.-- |
470 | (1)(a) The formal date of the filing of the application |
471 | for certification and commencement of the review process for |
472 | certification is the date on which the applicant submits: |
473 | 1. Copies of the application for certification in a |
474 | quantity and format, electronic or otherwise as prescribed by |
475 | rule, to the department and other agencies identified in s. |
476 | 403.526(2); and |
477 | 2. The application fee as specified under s. 403.5365 to |
478 | the department. |
479 |
|
480 | The department shall provide to the applicant and the Division |
481 | of Administrative Hearings the names and addresses of any |
482 | additional agencies or persons entitled to notice and copies of |
483 | the application and amendments, if any, within 7 days after |
484 | receiving the application for certification and the application |
485 | fees. |
486 | (b) In the application, the starting point and ending |
487 | point of a transmission line must be specifically defined by the |
488 | applicant. Within 7 days after the filing of an application, the |
489 | department shall provide the applicant and the Division of |
490 | Administrative Hearings the names and addresses of those |
491 | affected or other agencies entitled to notice and copies of the |
492 | application and any amendments. |
493 | (2) Within 15 7 days after the formal date of the |
494 | application filing completeness has been determined, the |
495 | department shall prepare a proposed schedule of dates for |
496 | determination of completeness, submission of statements of |
497 | issues, determination of sufficiency, and submittal of final |
498 | reports, from affected and other agencies and other significant |
499 | dates to be followed during the certification process, including |
500 | dates for filing notices of appearances to be a party under s. |
501 | 403.527(2) pursuant to s. 403.527(4). This schedule shall be |
502 | provided by the department to the applicant, the administrative |
503 | law judge, and the agencies identified under pursuant to |
504 | subsection (1). Within 7 days after the filing of this proposed |
505 | schedule, the administrative law judge shall issue an order |
506 | establishing a schedule for the matters addressed in the |
507 | department's proposed schedule and other appropriate matters, if |
508 | any. |
509 | (3) Within 7 days after completeness has been determined, |
510 | the applicant shall distribute copies of the application to all |
511 | agencies identified by the department pursuant to subsection |
512 | (1). Copies of changes and amendments to the application shall |
513 | be timely distributed by the applicant to all agencies and |
514 | parties who have received a copy of the application. |
515 | (4) Notice of the filing of the application shall be made |
516 | in accordance with the requirements of s. 403.5363. |
517 | Section 8. Section 403.5252, Florida Statutes, is amended |
518 | to read: |
519 | 403.5252 Determination of completeness.-- |
520 | (1)(a) Within 30 days after distribution of an |
521 | application, the affected agencies shall file a statement with |
522 | the department containing the recommendations of each agency |
523 | concerning the completeness of the application for |
524 | certification. |
525 | (b) Within 7 15 days after receipt of the completeness |
526 | statements of each agency an application, the department shall |
527 | file a statement with the Division of Administrative Hearings, |
528 | and with the applicant, and with all parties declaring its |
529 | position with regard to the completeness, not the sufficiency, |
530 | of the application. The statement of the department shall be |
531 | based upon its consultation with the affected agencies. |
532 | (2)(1) If the department declares the application to be |
533 | incomplete, the applicant, within 14 15 days after the filing of |
534 | the statement by the department, shall file with the Division of |
535 | Administrative Hearings, with all parties, and with the |
536 | department a statement: |
537 | (a) A withdrawal of Agreeing with the statement of the |
538 | department and withdrawing the application; |
539 | (b) Additional information necessary to make the |
540 | application complete. After the department first determines the |
541 | application to be incomplete, the time schedules under this act |
542 | are not tolled if the applicant makes the application complete |
543 | within the 14-day period. A subsequent finding by the department |
544 | that the application remains incomplete tolls the time schedules |
545 | under this act until the application is determined complete; |
546 | Agreeing with the statement of the department and agreeing to |
547 | amend the application without withdrawing it. The time schedules |
548 | referencing a complete application under this act shall not |
549 | commence until the application is determined complete; or |
550 | (c) A statement contesting the department's determination |
551 | of incompleteness; or statement of the department. |
552 | (d) A statement agreeing with the department and |
553 | requesting additional time to provide the information necessary |
554 | to make the application complete. If the applicant exercises |
555 | this option, the time schedules under this act are tolled until |
556 | the application is determined complete. |
557 | (3)(a)(2) If the applicant contests the determination by |
558 | the department that an application is incomplete, the |
559 | administrative law judge shall schedule a hearing on the |
560 | statement of completeness. The hearing shall be held as |
561 | expeditiously as possible, but not later than 21 30 days after |
562 | the filing of the statement by the department. The |
563 | administrative law judge shall render a decision within 7 10 |
564 | days after the hearing. |
565 | (b) Parties to a hearing on the issue of completeness |
566 | shall include the applicant, the department, and any agency that |
567 | has jurisdiction over the matter in dispute. Any substantially |
568 | affected person who wishes to become a party to the hearing on |
569 | the issue of completeness must file a motion no later than 10 |
570 | days before the date of the hearing. |
571 | (c)(a) If the administrative law judge determines that the |
572 | application was not complete as filed, the applicant shall |
573 | withdraw the application or make such additional submittals as |
574 | necessary to complete it. The time schedules referencing a |
575 | complete application under this act do shall not commence until |
576 | the application is determined complete. |
577 | (d)(b) If the administrative law judge determines that the |
578 | application was complete at the time it was declared incomplete |
579 | filed, the time schedules referencing a complete application |
580 | under this act shall commence upon such determination. |
581 | (4) If the applicant provides additional information to |
582 | address the issues identified in the determination of |
583 | incompleteness, each affected agency may submit to the |
584 | department, no later than 14 days after the applicant files the |
585 | additional information, a recommendation on whether the agency |
586 | believes the application is complete. Within 21 days after |
587 | receipt of the additional information from the applicant |
588 | submitted under paragraphs (2)(b), (2)(d), or (3)(c) and |
589 | considering the recommendations of the affected agencies, the |
590 | department shall determine whether the additional information |
591 | supplied by an applicant makes the application complete. If the |
592 | department finds that the application is still incomplete, the |
593 | applicant may exercise any of the options specified in |
594 | subsection (2) as often as is necessary to resolve the dispute. |
595 | Section 9. Section 403.526, Florida Statutes, is amended |
596 | to read: |
597 | 403.526 Preliminary statements of issues, reports, and |
598 | project analyses; and studies.-- |
599 | (1) Each affected agency that is required to file a report |
600 | which received an application in accordance with this section s. |
601 | 403.5251(3) shall submit a preliminary statement of issues to |
602 | the department and all parties the applicant no later than 50 60 |
603 | days after the filing distribution of the complete application. |
604 | Such statements of issues shall be made available to each local |
605 | government for use as information for public meetings held under |
606 | pursuant to s. 403.5272. The failure to raise an issue in this |
607 | preliminary statement of issues does shall not preclude the |
608 | issue from being raised in the agency's report. |
609 | (2)(a) The following affected agencies shall prepare |
610 | reports as provided below and shall submit them to the |
611 | department and the applicant no later than within 90 days after |
612 | the filing distribution of the complete application: |
613 | 1. The department shall prepare a report as to the impact |
614 | of each proposed transmission line or corridor as it relates to |
615 | matters within its jurisdiction. |
616 | 2. Each water management district in the jurisdiction of |
617 | which a proposed transmission line or corridor is to be located |
618 | shall prepare a report as to the impact on water resources and |
619 | other matters within its jurisdiction. |
620 | 3. The Department of Community Affairs shall prepare a |
621 | report containing recommendations which address the impact upon |
622 | the public of the proposed transmission line or corridor, based |
623 | on the degree to which the proposed transmission line or |
624 | corridor is consistent with the applicable portions of the state |
625 | comprehensive plan, emergency management, and other matters |
626 | within its jurisdiction. The Department of Community Affairs may |
627 | also comment on the consistency of the proposed transmission |
628 | line or corridor with applicable strategic regional policy plans |
629 | or local comprehensive plans and land development regulations. |
630 | 4. The Fish and Wildlife Conservation Commission shall |
631 | prepare a report as to the impact of each proposed transmission |
632 | line or corridor on fish and wildlife resources and other |
633 | matters within its jurisdiction. |
634 | 5. Each local government shall prepare a report as to the |
635 | impact of each proposed transmission line or corridor on matters |
636 | within its jurisdiction, including the consistency of the |
637 | proposed transmission line or corridor with all applicable local |
638 | ordinances, regulations, standards, or criteria that apply to |
639 | the proposed transmission line or corridor, including local |
640 | comprehensive plans, zoning regulations, land development |
641 | regulations, and any applicable local environmental regulations |
642 | adopted pursuant to s. 403.182 or by other means. A No change by |
643 | the responsible local government or local agency in local |
644 | comprehensive plans, zoning ordinances, or other regulations |
645 | made after the date required for the filing of the local |
646 | government's report required by this section is not shall be |
647 | applicable to the certification of the proposed transmission |
648 | line or corridor unless the certification is denied or the |
649 | application is withdrawn. |
650 | 6. Each regional planning council shall present a report |
651 | containing recommendations that address the impact upon the |
652 | public of the proposed transmission line or corridor based on |
653 | the degree to which the transmission line or corridor is |
654 | consistent with the applicable provisions of the strategic |
655 | regional policy plan adopted under pursuant to chapter 186 and |
656 | other impacts of each proposed transmission line or corridor on |
657 | matters within its jurisdiction. |
658 | 7. The Department of Transportation shall prepare a report |
659 | as to the impact of the proposed transmission line or corridor |
660 | on state roads, railroads, airports, aeronautics, seaports, and |
661 | other matters within its jurisdiction. |
662 | 8. The commission shall prepare a report containing its |
663 | determination under s. 403.537 and the report may include the |
664 | comments from the commission with respect to any other subject |
665 | within its jurisdiction. |
666 | 9. Any other agency, if requested by the department, shall |
667 | also perform studies or prepare reports as to subjects within |
668 | the jurisdiction of the agency which may potentially be affected |
669 | by the proposed transmission line. |
670 | (b) Each report must shall contain: |
671 | 1. A notice of any nonprocedural requirements not |
672 | specifically listed in the application from which a variance, |
673 | exemption, exception, or other relief is necessary in order for |
674 | the proposed corridor to be certified. Failure to include the |
675 | notice shall be treated as a waiver from the nonprocedural |
676 | requirements of that agency. |
677 | 2. A recommendation for approval or denial of the |
678 | application. |
679 | 3. The information on variances required by s. 403.531(2) |
680 | and proposed conditions of certification on matters within the |
681 | jurisdiction of each agency. For each condition proposed by an |
682 | agency, the agency shall list the specific statute, rule, or |
683 | ordinance, as applicable, which authorizes the proposed |
684 | condition. |
685 | (c) Each reviewing agency shall initiate the activities |
686 | required by this section no later than 15 days after the |
687 | complete application is filed distributed. Each agency shall |
688 | keep the applicant and the department informed as to the |
689 | progress of its studies and any issues raised thereby. |
690 | (d) Receipt of an affirmative determination of need from |
691 | the commission by the submittal deadline for agency reports |
692 | under paragraph (a) is a condition precedent to further |
693 | processing of the application. |
694 | (3) The department shall prepare a project written |
695 | analysis containing which contains a compilation of agency |
696 | reports and summaries of the material contained therein which |
697 | shall be filed with the administrative law judge and served on |
698 | all parties no later than 115 135 days after the application is |
699 | filed complete application has been distributed to the affected |
700 | agencies, and which shall include: |
701 | (a) A statement indicating whether the proposed electric |
702 | transmission line will be in compliance with the rules of the |
703 | department and affected agencies. |
704 | (b)(a) The studies and reports required by this section |
705 | and s. 403.537. |
706 | (c)(b) Comments received from any other agency or person. |
707 | (d)(c) The recommendation of the department as to the |
708 | disposition of the application, of variances, exemptions, |
709 | exceptions, or other relief identified by any party, and of any |
710 | proposed conditions of certification which the department |
711 | believes should be imposed. |
712 | (4) The failure of any agency to submit a preliminary |
713 | statement of issues or a report, or to submit its preliminary |
714 | statement of issues or report within the allowed time, is shall |
715 | not be grounds for the alteration of any time limitation in this |
716 | act under pursuant to s. 403.528. Neither The failure to submit |
717 | a preliminary statement of issues or a report, or nor the |
718 | inadequacy of the preliminary statement of issues or report, are |
719 | not shall be grounds to deny or condition certification. |
720 | Section 10. Section 403.527, Florida Statutes, is amended |
721 | to read: |
722 | (Substantial rewording of section. See s. 403.527, F.S., |
723 | for present text.) |
724 | 403.527 Certification hearing, parties, participants.-- |
725 | (1)(a) No later than 145 days after the application is |
726 | filed, the administrative law judge shall conduct a |
727 | certification hearing pursuant to ss. 120.569 and 120.57 at a |
728 | central location in proximity to the proposed transmission line |
729 | or corridor. |
730 | (b) Notice of the certification hearing and other public |
731 | hearings provided for in this section and notice of the deadline |
732 | for filing of notice of intent to be a party shall be made in |
733 | accordance with the requirements of s. 403.5363. |
734 | (2)(a) Parties to the proceeding shall be: |
735 | 1. The applicant. |
736 | 2. The department. |
737 | 3. The commission. |
738 | 4. The Department of Community Affairs. |
739 | 5. The Fish and Wildlife Conservation Commission. |
740 | 6. The Department of Transportation. |
741 | 7. Each water management district in the jurisdiction of |
742 | which the proposed transmission line or corridor is to be |
743 | located. |
744 | 8. The local government. |
745 | 9. The regional planning council. |
746 | (b) Any party listed in paragraph (a), other than the |
747 | department or the applicant, may waive its right to participate |
748 | in these proceedings. If any listed party fails to file a notice |
749 | of its intent to be a party on or before the 30th day before the |
750 | certification hearing, the party is deemed to have waived its |
751 | right to be a party unless its participation would not prejudice |
752 | the rights of any party to the proceeding. |
753 | (c) Notwithstanding the provisions of chapter 120 to the |
754 | contrary, upon the filing with the administrative law judge of a |
755 | notice of intent to be a party by an agency, corporation, or |
756 | association described in subparagraphs 1. and 2. or a petition |
757 | for intervention by a person described in subparagraph 3. no |
758 | later than 30 days before the date set for the certification |
759 | hearing, the following shall also be parties to the proceeding: |
760 | 1. Any agency not listed in paragraph (a) as to matters |
761 | within its jurisdiction. |
762 | 2. Any domestic nonprofit corporation or association |
763 | formed, in whole or in part, to promote conservation of natural |
764 | beauty; to protect the environment, personal health, or other |
765 | biological values; to preserve historical sites; to promote |
766 | consumer interests; to represent labor, commercial, or |
767 | industrial groups; or to promote comprehensive planning or |
768 | orderly development of the area in which the proposed |
769 | transmission line or corridor is to be located. |
770 | 3. Any person whose substantial interests are affected and |
771 | being determined by the proceeding. |
772 | (d) Any agency whose properties or works may be affected |
773 | shall be made a party upon the request of the agency or any |
774 | party to this proceeding. |
775 | (3)(a) The order of presentation at the certification |
776 | hearing, unless otherwise changed by the administrative law |
777 | judge to ensure the orderly presentation of witnesses and |
778 | evidence, shall be: |
779 | 1. The applicant. |
780 | 2. The department. |
781 | 3. State agencies. |
782 | 4. Regional agencies, including regional planning councils |
783 | and water management districts. |
784 | 5. Local governments. |
785 | 6. Other parties. |
786 | (b) When appropriate, any person may be given an |
787 | opportunity to present oral or written communications to the |
788 | administrative law judge. If the administrative law judge |
789 | proposes to consider such communications, all parties shall be |
790 | given an opportunity to cross-examine, challenge, or rebut the |
791 | communications. |
792 | (4) One public hearing where members of the public who are |
793 | not parties to the certification hearing may testify shall be |
794 | held within the boundaries of each county, at the option of any |
795 | local government. |
796 | (a) A local government shall notify the administrative law |
797 | judge and all parties not later than 21 days after the |
798 | application has been determined complete as to whether the local |
799 | government wishes to have a public hearing. If a filing for an |
800 | alternate corridor is accepted for consideration under s. |
801 | 403.5271(1) by the department and the applicant, any newly |
802 | affected local government must notify the administrative law |
803 | judge and all parties not later than 10 days after the data |
804 | concerning the alternate corridor has been determined complete |
805 | as to whether the local government wishes to have such a public |
806 | hearing. The local government is responsible for providing the |
807 | location of the public hearing if held separately from the |
808 | certification hearing. |
809 | (b) Within 5 days after notification, the administrative |
810 | law judge shall determine the date of the public hearing, which |
811 | shall be held before or during the certification hearing. If two |
812 | or more local governments within one county request a public |
813 | hearing, the hearing shall be consolidated so that only one |
814 | public hearing is held in any county. The location of a |
815 | consolidated hearing shall be determined by the administrative |
816 | law judge. |
817 | (c) If a local government does not request a public |
818 | hearing within 21 days after the application has been determined |
819 | complete, persons residing within the jurisdiction of the local |
820 | government may testify during that portion of the certification |
821 | hearing at which public testimony is heard. |
822 | (5) At the conclusion of the certification hearing, the |
823 | administrative law judge shall, after consideration of all |
824 | evidence of record, issue a recommended order disposing of the |
825 | application no later than 45 days after the transcript of the |
826 | certification hearing and the public hearings is filed with the |
827 | Division of Administrative Hearings. |
828 | (6)(a) No later than 25 days before the certification |
829 | hearing, the department or the applicant may request that the |
830 | administrative law judge cancel the certification hearing and |
831 | relinquish jurisdiction to the department if all parties to the |
832 | proceeding stipulate that there are no disputed issues of |
833 | material fact to be raised at the certification hearing. |
834 | (b) The administrative law judge shall issue an order |
835 | granting or denying the request within 5 days. |
836 | (c) If the administrative law judge grants the request, |
837 | the department and the applicant shall publish notices of the |
838 | cancellation of the certification hearing in accordance with s. |
839 | 403.5363. |
840 | (d)1. If the administrative law judge grants the request, |
841 | the department shall prepare and issue a final order in |
842 | accordance with s. 403.529(1)(a). |
843 | 2. Parties may submit proposed final orders to the |
844 | department no later than 10 days after the administrative law |
845 | judge issues an order relinquishing jurisdiction. |
846 | (7) The applicant shall pay those expenses and costs |
847 | associated with the conduct of the hearing and the recording and |
848 | transcription of the proceedings. |
849 | Section 11. Section 403.5271, Florida Statutes, is amended |
850 | to read: |
851 | 403.5271 Alternate corridors.-- |
852 | (1) No later than 45 50 days before prior to the |
853 | originally scheduled certification hearing, any party may |
854 | propose alternate transmission line corridor routes for |
855 | consideration under pursuant to the provisions of this act. |
856 | (a) A notice of a any such proposed alternate corridor |
857 | must shall be filed with the administrative law judge, all |
858 | parties, and any local governments in whose jurisdiction the |
859 | alternate corridor is proposed. The Such filing must shall |
860 | include the most recent United States Geological Survey 1:24,000 |
861 | quadrangle maps specifically delineating the corridor |
862 | boundaries, a description of the proposed corridor, and a |
863 | statement of the reasons the proposed alternate corridor should |
864 | be certified. |
865 | (b)1. Within 7 days after receipt of the such notice, the |
866 | applicant and the department shall file with the administrative |
867 | law judge and all parties a notice of acceptance or rejection of |
868 | a proposed alternate corridor for consideration. If the |
869 | alternate corridor is rejected either by the applicant or the |
870 | department, the certification hearing and the public hearings |
871 | shall be held as scheduled. If both the applicant and the |
872 | department accept a proposed alternate corridor for |
873 | consideration, the certification hearing and the public hearings |
874 | shall be rescheduled, if necessary. |
875 | 2. If rescheduled, the certification hearing shall be held |
876 | no more than 90 days after the previously scheduled |
877 | certification hearing, unless the data submitted under paragraph |
878 | (d) is determined to be incomplete, in which case the |
879 | rescheduled certification hearing shall be held no more than 105 |
880 | days after the previously scheduled certification hearing. If |
881 | additional time is needed due to the alternate corridor crossing |
882 | a local government jurisdiction that was not previously |
883 | affected, in which case the remainder of the schedule listed |
884 | below shall be appropriately adjusted by the administrative law |
885 | judge to allow that local government to prepare a report |
886 | pursuant to s. 403.526(2)(a)5. |
887 | (c) Notice of the filing of the alternate corridor, of the |
888 | revised time schedules, of the deadline for newly affected |
889 | persons and agencies to file notice of intent to become a party, |
890 | of the rescheduled hearing date, and of the proceedings pursuant |
891 | to s. 403.527(1)(b) and (c) shall be published in accordance |
892 | with s. 403.5363. |
893 | (d) Within 21 25 days after acceptance of an alternate |
894 | corridor by the department and the applicant, the party |
895 | proposing an alternate corridor shall have the burden of |
896 | providing all additional data to the agencies listed in s. |
897 | 403.526(2) and newly affected agencies s. 403.526 necessary for |
898 | the preparation of a supplementary report on the proposed |
899 | alternate corridor. |
900 | (e)1. Reviewing agencies shall advise the department of |
901 | any issues concerning completeness no later than 15 days after |
902 | the submittal of the data required by paragraph (d). Within 22 |
903 | days after receipt of the data, the department shall issue a |
904 | determination of completeness. |
905 | 2. If the department determines that the data required by |
906 | paragraph (d) is not complete, the party proposing the alternate |
907 | corridor must file such additional data to correct the |
908 | incompleteness. This additional data must be submitted within 14 |
909 | days after the determination by the department. |
910 | 3. If the department, within 14 days after receiving the |
911 | additional data, determines that the data remains incomplete, |
912 | the incompleteness of the data is deemed a withdrawal of the |
913 | proposed alternate corridor. The department may make its |
914 | determination based on recommendations made by other affected |
915 | agencies. If the department determines within 15 days that this |
916 | additional data is insufficient, the party proposing the |
917 | alternate corridor shall file such additional data that corrects |
918 | the insufficiency within 15 days after the filing of the |
919 | department's determination. If such additional data is |
920 | determined insufficient, such insufficiency of data shall be |
921 | deemed a withdrawal of the proposed alternate corridor. The |
922 | party proposing an alternate corridor shall have the burden of |
923 | proof on the certifiability of the alternate corridor at the |
924 | certification hearing pursuant to s. 403.529(4). Nothing in this |
925 | act shall be construed as requiring the applicant or agencies |
926 | not proposing the alternate corridor to submit data in support |
927 | of such alternate corridor. |
928 | (f) The agencies listed in s. 403.526(2) and any newly |
929 | affected agencies s. 403.526 shall file supplementary reports |
930 | with the applicant and the department which address addressing |
931 | the proposed alternate corridors no later than 24 60 days after |
932 | the additional data is submitted pursuant to paragraph (d) or |
933 | paragraph (e) is determined to be complete. |
934 | (g) The agency reports on alternate corridors must include |
935 | all information required by s. 403.526(2) agencies shall submit |
936 | supplementary notice pursuant to s. 403.531(2) at the time of |
937 | filing of their supplemental report. |
938 | (h) The department shall file with the administrative law |
939 | judge, the applicant, and all parties a project prepare a |
940 | written analysis consistent with s. 403.526(3) no more than 16 |
941 | at least 29 days after submittal of agency reports on prior to |
942 | the rescheduled certification hearing addressing the proposed |
943 | alternate corridor. |
944 | (2) If the original certification hearing date is |
945 | rescheduled, the rescheduling shall not provide the opportunity |
946 | for parties to file additional alternate corridors to the |
947 | applicant's proposed corridor or any accepted alternate |
948 | corridor. However, an amendment to the application which changes |
949 | the alignment of the applicant's proposed corridor shall require |
950 | rescheduling of the certification hearing, if necessary, so as |
951 | to allow time for a party to file alternate corridors to the |
952 | realigned proposed corridor for which the application has been |
953 | amended. Any such alternate corridor proposal shall have the |
954 | same starting and ending points as the realigned portion of the |
955 | corridor proposed by the applicant's amendment, provided that |
956 | the administrative law judge for good cause shown may authorize |
957 | another starting or ending point in the area of the applicant's |
958 | amended corridor. |
959 | (3)(a) Notwithstanding the rejection of a proposed |
960 | alternate corridor by the applicant or the department, any party |
961 | may present evidence at the certification hearing to show that a |
962 | corridor proper for certification does not satisfy the criteria |
963 | listed in s. 403.529 or that a rejected alternate corridor would |
964 | meet the criteria set forth in s. 403.529. No Evidence may not |
965 | shall be admitted at the certification hearing on any alternate |
966 | corridor, unless the alternate corridor was proposed by the |
967 | filing of a notice at least 45 50 days before prior to the |
968 | originally scheduled certification hearing pursuant to this |
969 | section. Rejected alternate corridors shall be considered by the |
970 | board as provided in s. 403.529(4) and (5). |
971 | (b) The party proposing an alternate corridor has the |
972 | burden to prove that the alternate corridor can be certified at |
973 | the certification hearing. This act does not require an |
974 | applicant or agency that is not proposing the alternate corridor |
975 | to submit data in support of the alternate corridor. |
976 | (4) If an alternate corridor is accepted by the applicant |
977 | and the department pursuant to a notice of acceptance as |
978 | provided in this subsection and the such corridor is ultimately |
979 | determined to be the corridor that would meet the criteria set |
980 | forth in s. 403.529(4) and (5), the board shall certify that |
981 | corridor. |
982 | Section 12. Section 403.5272, Florida Statutes, is amended |
983 | to read: |
984 | 403.5272 Local governments; Informational public |
985 | meetings.-- |
986 | (1) A local government whose jurisdiction is to be crossed |
987 | by a proposed corridor governments may hold one informational |
988 | public meeting meetings in addition to the hearings specifically |
989 | authorized by this act on any matter associated with the |
990 | transmission line proceeding. The Such informational public |
991 | meeting may be conducted by the local government or the regional |
992 | planning council and shall meetings should be held no later than |
993 | 55 80 days after the application is filed. The purpose of an |
994 | informational public meeting is for the local government or |
995 | regional planning council to further inform the general public |
996 | about the transmission line proposed, obtain comments from the |
997 | public, and formulate its recommendation with respect to the |
998 | proposed transmission line. |
999 | (2) Informational public meetings shall be held solely at |
1000 | the option of each local government or regional planning |
1001 | council. It is the legislative intent that local governments or |
1002 | regional planning councils attempt to hold such public meetings. |
1003 | Parties to the proceedings under this act shall be encouraged to |
1004 | attend; however, a no party other than the applicant and the |
1005 | department is not shall be required to attend the such |
1006 | informational public meetings hearings. |
1007 | (3) A local government or regional planning council that |
1008 | intends to conduct an informational public meeting must provide |
1009 | notice of the meeting, with notice sent to all parties listed in |
1010 | s. 403.527(2)(a), not less than 5 days before the meeting. |
1011 | (4)(3) The failure to hold an informational public meeting |
1012 | or the procedure used for the informational public meeting are |
1013 | shall not be grounds for the alteration of any time limitation |
1014 | in this act under pursuant to s. 403.528 or grounds to deny or |
1015 | condition certification. |
1016 | Section 13. Section 403.5275, Florida Statutes, is amended |
1017 | to read: |
1018 | 403.5275 Amendment to the application.-- |
1019 | (1) Any amendment made to the application before |
1020 | certification shall be sent by the applicant to the |
1021 | administrative law judge and to all parties to the proceeding. |
1022 | (2) Any amendment to the application made before prior to |
1023 | certification shall be disposed of as part of the original |
1024 | certification proceeding. Amendment of the application may be |
1025 | considered "good cause" for alteration of time limits pursuant |
1026 | to s. 403.528. |
1027 | Section 14. Section 403.528, Florida Statutes, is amended |
1028 | to read: |
1029 | 403.528 Alteration of time limits.-- |
1030 | (1) Any time limitation in this act may be altered by the |
1031 | administrative law judge upon stipulation between the department |
1032 | and the applicant unless objected to by any party within 5 days |
1033 | after notice or for good cause shown by any party. |
1034 | (2) A comprehensive application encompassing more than one |
1035 | proposed transmission line may be good cause for alternation of |
1036 | time limits. |
1037 | Section 15. Section 403.529, Florida Statutes, is amended |
1038 | to read: |
1039 | 403.529 Final disposition of application.-- |
1040 | (1)(a) If the administrative law judge has granted a |
1041 | request to cancel the certification hearing and has relinquished |
1042 | jurisdiction to the department under s. 403.527(6), within 40 |
1043 | days thereafter, the secretary of the department shall act upon |
1044 | the application by written order in accordance with the terms of |
1045 | this act and state the reasons for issuance or denial. |
1046 | (b) If the administrative law judge does not grant a |
1047 | request to cancel the certification hearing under the provisions |
1048 | of s. 403.527(6) within 60 30 days after receipt of the |
1049 | administrative law judge's recommended order, the board shall |
1050 | act upon the application by written order, approving in whole, |
1051 | approving with such conditions as the board deems appropriate, |
1052 | or denying the certification and stating the reasons for |
1053 | issuance or denial. |
1054 | (2) The issues that may be raised in any hearing before |
1055 | the board shall be limited to matters raised in the |
1056 | certification proceeding before the administrative law judge or |
1057 | raised in the recommended order of the administrative law judge. |
1058 | All parties, or their representatives, or persons who appear |
1059 | before the board shall be subject to the provisions of s. |
1060 | 120.66. |
1061 | (3) If certification is denied, the board, or secretary if |
1062 | applicable, shall set forth in writing the action the applicant |
1063 | would have to take to secure the approval of the application by |
1064 | the board. |
1065 | (4) In determining whether an application should be |
1066 | approved in whole, approved with modifications or conditions, or |
1067 | denied, the board, or secretary when applicable, shall consider |
1068 | whether, and the extent to which, the location of the |
1069 | transmission line corridor and the construction, operation, and |
1070 | maintenance of the transmission line will: |
1071 | (a) Ensure electric power system reliability and |
1072 | integrity; |
1073 | (b) Meet the electrical energy needs of the state in an |
1074 | orderly, economical, and timely fashion; |
1075 | (c) Comply with applicable nonprocedural requirements of |
1076 | agencies; |
1077 | (d) Be consistent with applicable provisions of local |
1078 | government comprehensive plans, if any; and |
1079 | (e) Effect a reasonable balance between the need for the |
1080 | transmission line as a means of providing reliable, economically |
1081 | efficient electric energy, as determined by the commission, |
1082 | under s. 403.537, abundant low-cost electrical energy and the |
1083 | impact upon the public and the environment resulting from the |
1084 | location of the transmission line corridor and the construction, |
1085 | operation, and maintenance of the transmission lines. |
1086 | (5)(a) Any transmission line corridor certified by the |
1087 | board, or secretary if applicable, shall meet the criteria of |
1088 | this section. When more than one transmission line corridor is |
1089 | proper for certification under pursuant to s. 403.522(10) and |
1090 | meets the criteria of this section, the board, or secretary if |
1091 | applicable, shall certify the transmission line corridor that |
1092 | has the least adverse impact regarding the criteria in |
1093 | subsection (4), including costs. |
1094 | (b) If the board, or secretary if applicable, finds that |
1095 | an alternate corridor rejected pursuant to s. 403.5271 meets the |
1096 | criteria of subsection (4) and has the least adverse impact |
1097 | regarding the criteria in subsection (4), including cost, of all |
1098 | corridors that meet the criteria of subsection (4), then the |
1099 | board, or secretary if applicable, shall deny certification or |
1100 | shall allow the applicant to submit an amended application to |
1101 | include the such corridor. |
1102 | (c) If the board, or secretary if applicable, finds that |
1103 | two or more of the corridors that comply with the provisions of |
1104 | subsection (4) have the least adverse impacts regarding the |
1105 | criteria in subsection (4), including costs, and that the such |
1106 | corridors are substantially equal in adverse impacts regarding |
1107 | the criteria in subsection (4), including costs, then the board, |
1108 | or secretary if applicable, shall certify the corridor preferred |
1109 | by the applicant if the corridor is one proper for certification |
1110 | under pursuant to s. 403.522(10). |
1111 | (6) The issuance or denial of the certification is by the |
1112 | board shall be the final administrative action required as to |
1113 | that application. |
1114 | Section 16. Section 403.531, Florida Statutes, is amended |
1115 | to read: |
1116 | 403.531 Effect of certification.-- |
1117 | (1) Subject to the conditions set forth therein, |
1118 | certification shall constitute the sole license of the state and |
1119 | any agency as to the approval of the location of transmission |
1120 | line corridors and the construction, operation, and maintenance |
1121 | of transmission lines. The certification is shall be valid for |
1122 | the life of the transmission line, if provided that construction |
1123 | on, or condemnation or acquisition of, the right-of-way is |
1124 | commenced within 5 years after of the date of certification or |
1125 | such later date as may be authorized by the board. |
1126 | (2)(a) The certification authorizes shall authorize the |
1127 | licensee applicant to locate the transmission line corridor and |
1128 | to construct and maintain the transmission lines subject only to |
1129 | the conditions of certification set forth in the such |
1130 | certification. |
1131 | (b) The certification may include conditions that which |
1132 | constitute variances and exemptions from nonprocedural standards |
1133 | or rules regulations of the department or any other agency, |
1134 | which were expressly considered during the certification review |
1135 | proceeding unless waived by the agency as provided in s. 403.526 |
1136 | below and which otherwise would be applicable to the location of |
1137 | the proposed transmission line corridor or the construction, |
1138 | operation, and maintenance of the transmission lines. Each party |
1139 | shall notify the applicant and other parties at the time |
1140 | scheduled for the filing of the agency reports of any |
1141 | nonprocedural requirements not specifically listed in the |
1142 | application from which a variance, exemption, exception, or |
1143 | other relief is necessary in order for the board to certify any |
1144 | corridor proposed for certification. Failure of such |
1145 | notification shall be treated as a waiver from the nonprocedural |
1146 | requirements of that agency. |
1147 | (3)(a) The certification shall be in lieu of any license, |
1148 | permit, certificate, or similar document required by any state, |
1149 | regional, or local agency under pursuant to, but not limited to, |
1150 | chapter 125, chapter 161, chapter 163, chapter 166, chapter 186, |
1151 | chapter 253, chapter 258, chapter 298, chapter 370, chapter 372, |
1152 | chapter 373, chapter 376, chapter 380, chapter 381, chapter 387, |
1153 | chapter 403, chapter 404, the Florida Transportation Code, or 33 |
1154 | U.S.C. s. 1341. |
1155 | (b) On certification, any license, easement, or other |
1156 | interest in state lands, except those the title of which is |
1157 | vested in the Board of Trustees of the Internal Improvement |
1158 | Trust Fund, shall be issued by the appropriate agency as a |
1159 | ministerial act. The applicant shall be required to seek any |
1160 | necessary interest in state lands the title to which is vested |
1161 | in the Board of Trustees of the Internal Improvement Trust Fund |
1162 | from the board of trustees before, during, or after the |
1163 | certification proceeding, and certification may be made |
1164 | contingent upon issuance of the appropriate interest in realty. |
1165 | However, neither the applicant and nor any party to the |
1166 | certification proceeding may not directly or indirectly raise or |
1167 | relitigate any matter that which was or could have been an issue |
1168 | in the certification proceeding in any proceeding before the |
1169 | Board of Trustees of the Internal Improvement Trust Fund wherein |
1170 | the applicant is seeking a necessary interest in state lands, |
1171 | but the information presented in the certification proceeding |
1172 | shall be available for review by the board of trustees and its |
1173 | staff. |
1174 | (4) This act does shall not in any way affect the |
1175 | ratemaking powers of the commission under chapter 366. This act |
1176 | does shall also not in any way affect the right of any local |
1177 | government to charge appropriate fees or require that |
1178 | construction be in compliance with the National Electrical |
1179 | Safety Code, as prescribed by the commission. |
1180 | (5) A No term or condition of certification may not shall |
1181 | be interpreted to preclude the postcertification exercise by any |
1182 | party of whatever procedural rights it may have under chapter |
1183 | 120, including those related to rulemaking proceedings. |
1184 | Section 17. Section 403.5312, Florida Statutes, is amended |
1185 | to read: |
1186 | 403.5312 Filing Recording of notice of certified corridor |
1187 | route.-- |
1188 | (1) Within 60 days after certification of a directly |
1189 | associated transmission line under pursuant to ss. 403.501- |
1190 | 403.518 or a transmission line corridor under pursuant to ss. |
1191 | 403.52-403.5365, the applicant shall file with the department |
1192 | and, in accordance with s. 28.222, with the clerk of the circuit |
1193 | court for each county through which the corridor will pass, a |
1194 | notice of the certified route. |
1195 | (2) The notice must shall consist of maps or aerial |
1196 | photographs in the scale of 1:24,000 which clearly show the |
1197 | location of the certified route and must shall state that the |
1198 | certification of the corridor will result in the acquisition of |
1199 | rights-of-way within the corridor. Each clerk shall record the |
1200 | filing in the official record of the county for the duration of |
1201 | the certification or until such time as the applicant certifies |
1202 | to the department and the clerk that all lands required for the |
1203 | transmission line rights-of-way within the corridor have been |
1204 | acquired within the such county, whichever is sooner. |
1205 | (3) The recording of this notice does shall not constitute |
1206 | a lien, cloud, or encumbrance on real property. |
1207 | Section 18. Section 403.5315, Florida Statutes, is amended |
1208 | to read: |
1209 | 403.5315 Modification of certification.--A certification |
1210 | may be modified after issuance in any one of the following ways: |
1211 | (1) The board may delegate to the department the authority |
1212 | to modify specific conditions in the certification. |
1213 | (2) The licensee may file a petition for modification with |
1214 | the department or the department may initiate the modification |
1215 | upon its own initiative. |
1216 | (a) A petition for modification must set forth: |
1217 | 1. The proposed modification; |
1218 | 2. The factual reasons asserted for the modification; and |
1219 | 3. The anticipated additional environmental effects of the |
1220 | proposed modification. |
1221 | (b)(2) The department may modify the terms and conditions |
1222 | of the certification if no party objects in writing to the such |
1223 | modification within 45 days after notice by mail to the last |
1224 | address of record in the certification proceeding, and if no |
1225 | other person whose substantial interests will be affected by the |
1226 | modification objects in writing within 30 days after issuance of |
1227 | public notice. |
1228 | (c) If objections are raised or the department denies the |
1229 | proposed modification, the licensee may file a request for |
1230 | hearing on the modification with the department. Such a request |
1231 | shall be handled pursuant to chapter 120. |
1232 | (d) A request for hearing referred to the Division of |
1233 | Administrative Hearings shall be disposed of in the same manner |
1234 | as an application but with time periods established by the |
1235 | administrative law judge commensurate with the significance of |
1236 | the modification requested. If objections are raised, the |
1237 | applicant may file a petition for modification pursuant to |
1238 | subsection (3). |
1239 | (3) The applicant or the department may file a petition |
1240 | for modification with the department and the Division of |
1241 | Administrative Hearings setting forth: |
1242 | (a) The proposed modification; |
1243 | (b) The factual reasons asserted for the modification; and |
1244 | (c) The anticipated additional environmental effects of |
1245 | the proposed modification. |
1246 | (4) Petitions filed pursuant to subsection (3) shall be |
1247 | disposed of in the same manner as an application but with time |
1248 | periods established by the administrative law judge commensurate |
1249 | with the significance of the modification requested. |
1250 | Section 19. Section 403.5317, Florida Statutes, is created |
1251 | to read: |
1252 | 403.5317 Postcertification activities.-- |
1253 | (1)(a) If, subsequent to certification, a licensee |
1254 | proposes any material change to the application or prior |
1255 | amendments, the licensee shall submit to the department a |
1256 | written request for amendment and description of the proposed |
1257 | change to the application. The department shall, within 30 days |
1258 | after the receipt of the request for the amendment, determine |
1259 | whether the proposed change to the application requires a |
1260 | modification of the conditions of certification. |
1261 | (b) If the department concludes that the change would not |
1262 | require a modification of the conditions of certification, the |
1263 | department shall notify, in writing, the licensee, all agencies, |
1264 | and all parties of the approval of the amendment. |
1265 | (c) If the department concludes that the change would |
1266 | require a modification of the conditions of certification, the |
1267 | department shall notify the licensee that the proposed change to |
1268 | the application requires a request for modification under s. |
1269 | 403.5315. |
1270 | (2) Postcertification submittals filed by a licensee with |
1271 | one or more agencies are for the purpose of monitoring for |
1272 | compliance with the issued certification. Each submittal must be |
1273 | reviewed by each agency on an expedited and priority basis |
1274 | because each facility certified under this act is a critical |
1275 | infrastructure facility. Postcertification review may not be |
1276 | completed more than 90 days after complete information for a |
1277 | segment of the certified transmission line is submitted to the |
1278 | reviewing agencies. |
1279 | Section 20. Section 403.5363, Florida Statutes, is created |
1280 | to read: |
1281 | 403.5363 Public notices; requirements.-- |
1282 | (1)(a) The applicant shall arrange for the publication of |
1283 | the notices specified in paragraph (b). |
1284 | 1. The notices shall be published in newspapers of general |
1285 | circulation within counties crossed by the transmission line |
1286 | corridors proper for certification. The required newspaper |
1287 | notices for filing of an application and for the certification |
1288 | hearing shall be one-half page in size in a standard-size |
1289 | newspaper or a full page in a tabloid-size newspaper and |
1290 | published in a section of the newspaper other than the section |
1291 | for legal notices. These two notices must include a map |
1292 | generally depicting all transmission corridors proper for |
1293 | certification. A newspaper of general circulation shall be the |
1294 | newspaper within a county crossed by a transmission line |
1295 | corridor proper for certification which newspaper has the |
1296 | largest daily circulation in that county and has its principal |
1297 | office in that county. If the newspaper having the largest daily |
1298 | circulation has its principal office outside the county, the |
1299 | notices must appear in both the newspaper having the largest |
1300 | circulation in that county and in a newspaper authorized to |
1301 | publish legal notices in that county. |
1302 | 2. The department shall adopt rules specifying the content |
1303 | of the newspaper notices. |
1304 | 3. All notices published by the applicant shall be paid |
1305 | for by the applicant and shall be in addition to the application |
1306 | fee. |
1307 | (b) Public notices that must be published under this |
1308 | section include: |
1309 | 1. The notice of the filing of an application, which must |
1310 | include a description of the proceedings required by this act. |
1311 | The notice must describe the provisions of s. 403.531(1) and (2) |
1312 | and give the date by which notice of intent to be a party or a |
1313 | petition to intervene in accordance with s. 403.527(2) must be |
1314 | filed. This notice must be published no more than 21 days after |
1315 | the application is filed. |
1316 | 2. The notice of the certification hearing and any other |
1317 | public hearing permitted under s. 403.527. The notice must |
1318 | include the date by which a person wishing to appear as a party |
1319 | must file the notice to do so. The notice of the certification |
1320 | hearing must be published at least 65 days before the date set |
1321 | for the certification hearing. |
1322 | 3. The notice of the cancellation of the certification |
1323 | hearing, if applicable. The notice must be published at least 3 |
1324 | days before the date of the originally scheduled certification |
1325 | hearing. |
1326 | 4. The notice of the filing of a proposal to modify the |
1327 | certification submitted under s. 403.5315, if the department |
1328 | determines that the modification would require relocation or |
1329 | expansion of the transmission line right-of-way or a certified |
1330 | substation. |
1331 | (2) The proponent of an alternate corridor shall arrange |
1332 | for the publication of the filing of the proposal for an |
1333 | alternate corridor, the revised time schedules, the date by |
1334 | which newly affected persons or agencies may file the notice of |
1335 | intent to become a party, and the date of the rescheduled |
1336 | hearing. A notice listed in this subsection must be published in |
1337 | a newspaper of general circulation within the county or counties |
1338 | crossed by the proposed alternate corridor and comply with the |
1339 | content requirements set forth in paragraph (1)(a). The notice |
1340 | must be published not less than 50 days before the rescheduled |
1341 | certification hearing. |
1342 | (3) The department shall arrange for the publication of |
1343 | the following notices in the manner specified by chapter 120: |
1344 | (a) The notice of the filing of an application and the |
1345 | date by which a person intending to become a party must file the |
1346 | notice of intent. The notice must be published no later than 21 |
1347 | days after the application has been filed. |
1348 | (b) The notice of any administrative hearing for |
1349 | certification, if applicable. The notice must be published not |
1350 | less than 65 days before the date set for a hearing, except that |
1351 | notice for a rescheduled certification hearing after acceptance |
1352 | of an alternative corridor must be published not less than 50 |
1353 | days before the date set for the hearing. |
1354 | (c) The notice of the cancellation of a certification |
1355 | hearing, if applicable. The notice must be published not later |
1356 | than 7 days before the date of the originally scheduled |
1357 | certification hearing. |
1358 | (d) The notice of the hearing before the siting board, if |
1359 | applicable. |
1360 | (e) The notice of stipulations, proposed agency action, or |
1361 | a petition for modification. |
1362 | Section 21. Section 403.5365, Florida Statutes, is amended |
1363 | to read: |
1364 | 403.5365 Fees; disposition.--The department shall charge |
1365 | the applicant the following fees, as appropriate, which, unless |
1366 | otherwise specified, shall be paid into the Florida Permit Fee |
1367 | Trust Fund: |
1368 | (1) An application fee. |
1369 | (a) The application fee shall be of $100,000, plus $750 |
1370 | per mile for each mile of corridor in which the transmission |
1371 | line right-of-way is proposed to be located within an existing |
1372 | electric electrical transmission line right-of-way or within any |
1373 | existing right-of-way for any road, highway, railroad, or other |
1374 | aboveground linear facility, or $1,000 per mile for each mile of |
1375 | electric transmission line corridor proposed to be located |
1376 | outside the such existing right-of-way. |
1377 | (b)(a) Sixty percent of the fee shall go to the department |
1378 | to cover any costs associated with coordinating the review of |
1379 | reviewing and acting upon the application and any costs for |
1380 | field services associated with monitoring construction and |
1381 | operation of the electric transmission line facility. |
1382 | (c)(b) The following percentage Twenty percent of the fees |
1383 | specified under this section, except postcertification fees, |
1384 | shall be transferred to the Administrative Trust Fund of the |
1385 | Division of Administrative Hearings of the Department of |
1386 | Management Services:. |
1387 | 1. Five percent to compensate for expenses from the |
1388 | initial exercise of duties associated with the filing of an |
1389 | application. |
1390 | 2. An additional 10 percent if an administrative hearing |
1391 | under s. 403.527 is held. |
1392 | (d)1.(c) Upon written request with proper itemized |
1393 | accounting within 90 days after final agency action by the |
1394 | siting board or the department or the withdrawal of the |
1395 | application, the agencies that prepared reports under s. 403.526 |
1396 | or s. 403.5271 or participated in a hearing under s. 403.527 or |
1397 | s. 403.5271 may submit a written request to the department for |
1398 | reimbursement of expenses incurred during the certification |
1399 | proceedings. The request must contain an accounting of expenses |
1400 | incurred, which may include time spent reviewing the |
1401 | application, department shall reimburse the expenses and costs |
1402 | of the Department of Community Affairs, the Fish and Wildlife |
1403 | Conservation Commission, the water management district, regional |
1404 | planning council, and local government in the jurisdiction of |
1405 | which the transmission line is to be located. Such reimbursement |
1406 | shall be authorized for the preparation of any studies required |
1407 | of the agencies by this act, and for agency travel and per diem |
1408 | to attend any hearing held under pursuant to this act, and for |
1409 | the local government or regional planning council providing |
1410 | additional notice of the informational public meeting. The |
1411 | department shall review the request and verify whether a claimed |
1412 | expense is valid. Valid expenses shall be reimbursed; however, |
1413 | if to participate in the proceedings. In the event the amount of |
1414 | funds available for reimbursement allocation is insufficient to |
1415 | provide for full compensation complete reimbursement to the |
1416 | agencies, reimbursement shall be on a prorated basis. |
1417 | 2. If the application review is held in abeyance for more |
1418 | than 1 year, the agencies may submit a request for reimbursement |
1419 | under subparagraph 1. |
1420 | (e)(d) If any sums are remaining, the department shall |
1421 | retain them for its use in the same manner as is otherwise |
1422 | authorized by this section; provided, however, that if the |
1423 | certification application is withdrawn, the remaining sums shall |
1424 | be refunded to the applicant within 90 days after withdrawal. |
1425 | (2) An amendment fee. |
1426 | (a) If no corridor alignment change is proposed by the |
1427 | amendment, no amendment fee shall be charged. |
1428 | (b) If a corridor alignment change under s. 403.5275 is |
1429 | proposed by the applicant, an additional fee of a minimum of |
1430 | $2,000 and $750 per mile shall be submitted to the department |
1431 | for use in accordance with this act. |
1432 | (c) If an amendment is required to address issues, |
1433 | including alternate corridors under pursuant to s. 403.5271, |
1434 | raised by the department or other parties, no fee for the such |
1435 | amendment shall be charged. |
1436 | (3) A certification modification fee. |
1437 | (a) If no corridor alignment change is proposed by the |
1438 | licensee applicant, the modification fee shall be $4,000. |
1439 | (b) If a corridor alignment change is proposed by the |
1440 | licensee applicant, the fee shall be $1,000 for each mile of |
1441 | realignment plus an amount not to exceed $10,000 to be fixed by |
1442 | rule on a sliding scale based on the load-carrying capability |
1443 | and configuration of the transmission line for use in accordance |
1444 | with subsection (1) (2). |
1445 | Section 22. Subsection (1) of section 403.537, Florida |
1446 | Statutes, is amended to read: |
1447 | 403.537 Determination of need for transmission line; |
1448 | powers and duties.-- |
1449 | (1)(a) Upon request by an applicant or upon its own |
1450 | motion, the Florida Public Service Commission shall schedule a |
1451 | public hearing, after notice, to determine the need for a |
1452 | transmission line regulated by the Florida Electric Transmission |
1453 | Line Siting Act, ss. 403.52-403.5365. The Such notice shall be |
1454 | published at least 21 45 days before the date set for the |
1455 | hearing and shall be published by the applicant in at least one- |
1456 | quarter page size notice in newspapers of general circulation, |
1457 | and by the commission in the manner specified in chapter 120 in |
1458 | the Florida Administrative Weekly, by giving notice to counties |
1459 | and regional planning councils in whose jurisdiction the |
1460 | transmission line could be placed, and by giving notice to any |
1461 | persons who have requested to be placed on the mailing list of |
1462 | the commission for this purpose. Within 21 days after receipt of |
1463 | a request for determination by an applicant, the commission |
1464 | shall set a date for the hearing. The hearing shall be held |
1465 | pursuant to s. 350.01 within 45 days after the filing of the |
1466 | request, and a decision shall be rendered within 60 days after |
1467 | such filing. |
1468 | (b) The commission shall be the sole forum in which to |
1469 | determine the need for a transmission line. The need for a |
1470 | transmission line may not be raised or be the subject of review |
1471 | in another proceeding. |
1472 | (c)(b) In the determination of need, the commission shall |
1473 | take into account the need for electric system reliability and |
1474 | integrity, the need for abundant, low-cost electrical energy to |
1475 | assure the economic well-being of the residents citizens of this |
1476 | state, the appropriate starting and ending point of the line, |
1477 | and other matters within its jurisdiction deemed relevant to the |
1478 | determination of need. The appropriate starting and ending |
1479 | points of the electric transmission line must be verified by the |
1480 | commission in its determination of need. |
1481 | (d)(c) The determination by the commission of the need for |
1482 | the transmission line, as defined in s. 403.522(22) s. |
1483 | 403.522(21), is binding on all parties to any certification |
1484 | proceeding under pursuant to the Florida Electric Transmission |
1485 | Line Siting Act and is a condition precedent to the conduct of |
1486 | the certification hearing prescribed therein. An order entered |
1487 | pursuant to this section constitutes final agency action. |
1488 | Section 23. Subsection (3) of section 373.441, Florida |
1489 | Statutes, is amended to read: |
1490 | 373.441 Role of counties, municipalities, and local |
1491 | pollution control programs in permit processing.-- |
1492 | (3) The department shall review environmental resource |
1493 | permit applications for electrical distribution and transmission |
1494 | lines and other facilities related to the production, |
1495 | transmission, and distribution of electricity which are not |
1496 | certified under ss. 403.52-403.5365, the Florida Electric |
1497 | Transmission Line Siting Act, regulated under this part. |
1498 | Section 24. Subsection (30) of section 403.061, Florida |
1499 | Statutes, is amended to read: |
1500 | 403.061 Department; powers and duties.--The department |
1501 | shall have the power and the duty to control and prohibit |
1502 | pollution of air and water in accordance with the law and rules |
1503 | adopted and promulgated by it and, for this purpose, to: |
1504 | (30) Establish requirements by rule that reasonably |
1505 | protect the public health and welfare from electric and magnetic |
1506 | fields associated with existing 230 kV or greater electrical |
1507 | transmission lines, new 230 kV and greater electrical |
1508 | transmission lines for which an application for certification |
1509 | under the Florida Electric Transmission Line Siting Act, ss. |
1510 | 403.52-403.5365, is not filed, new or existing electrical |
1511 | transmission or distribution lines with voltage less than 230 |
1512 | kV, and substation facilities. Notwithstanding any other |
1513 | provision in this chapter or any other law of this state or |
1514 | political subdivision thereof, the department shall have |
1515 | exclusive jurisdiction in the regulation of electric and |
1516 | magnetic fields associated with all electrical transmission and |
1517 | distribution lines and substation facilities. However, nothing |
1518 | herein shall be construed as superseding or repealing the |
1519 | provisions of s. 403.523(1) and (10). |
1520 |
|
1521 | The department shall implement such programs in conjunction with |
1522 | its other powers and duties and shall place special emphasis on |
1523 | reducing and eliminating contamination that presents a threat to |
1524 | humans, animals or plants, or to the environment. |
1525 | Section 25. Paragraph (a) of subsection (3) of section |
1526 | 403.0876, Florida Statutes, is amended to read: |
1527 | 403.0876 Permits; processing.-- |
1528 | (3)(a) The department shall establish a special unit for |
1529 | permit coordination and processing to provide expeditious |
1530 | processing of department permits which the district offices are |
1531 | unable to process expeditiously and to provide accelerated |
1532 | processing of certain permits or renewals for economic and |
1533 | operating stability. The ability of the department to process |
1534 | applications under pursuant to this subsection in a more timely |
1535 | manner than allowed by subsections (1) and (2) is dependent upon |
1536 | the timely exchange of information between the applicant and the |
1537 | department and the intervention of outside parties as allowed by |
1538 | law. An applicant may request the processing of its permit |
1539 | application by the special unit if the application is from an |
1540 | area of high unemployment or low per capita income, is from a |
1541 | business or industry that is the primary employer within an |
1542 | area's labor market, or is in an industry with respect to which |
1543 | the complexities involved in the review of the application |
1544 | require special skills uniquely available in the headquarters |
1545 | office. The department may require the applicant to waive the |
1546 | 90-day time limitation for department issuance or denial of the |
1547 | permit once for a period not to exceed 90 days. The department |
1548 | may require a special fee to cover the direct cost of processing |
1549 | special applications in addition to normal permit fees and |
1550 | costs. The special fee may not exceed $10,000 per permit |
1551 | required. Applications for renewal permits, but not applications |
1552 | for initial permits, required for facilities pursuant to the |
1553 | Electrical Power Plant Siting Act or the Florida Electric |
1554 | Transmission Line Siting Act may be processed under this |
1555 | subsection. Personnel staffing the special unit shall have |
1556 | lengthy experience in permit processing. |
1557 | Section 26. Paragraph (b) of subsection (3) of section |
1558 | 403.809, Florida Statutes, is amended to read: |
1559 | 403.809 Environmental districts; establishment; managers; |
1560 | functions.-- |
1561 | (3) |
1562 | (b) The processing of all applications for permits, |
1563 | licenses, certificates, and exemptions shall be accomplished at |
1564 | the district center or the branch office, except for those |
1565 | applications specifically assigned elsewhere in the department |
1566 | under s. 403.805 or to the water management districts under s. |
1567 | 403.812 and those applications assigned by interagency agreement |
1568 | as provided in this act. However, the secretary, as head of the |
1569 | department, may not delegate to district or subdistrict |
1570 | managers, water management districts, or any unit of local |
1571 | government the authority to act on the following types of permit |
1572 | applications: |
1573 | 1. Permits issued under s. 403.0885, except such permit |
1574 | issuance may be delegated to district managers. |
1575 | 2. Construction of major air pollution sources. |
1576 | 3. Certifications under the Florida Electrical Power Plant |
1577 | Siting Act or the Florida Electric Transmission Line Siting Act |
1578 | and the associated permit issued under s. 403.0885, if |
1579 | applicable. |
1580 | 4. Permits issued under s. 403.0885 to steam electric |
1581 | generating facilities regulated pursuant to 40 C.F.R. part 423. |
1582 | 5. Permits issued under s. 378.901. |
1583 | Section 27. Sections 403.5253 and 403.5369, Florida |
1584 | Statutes, are repealed. |
1585 | Section 28. This act shall take effect upon becoming a |
1586 | law. |