997525                                                     
Committee
GA
Amendment
12
GENERAL APPROPRIATIONS BILL SB2800 Senator(s) Alexander and Margolis moved the following amendment:
Section: 05
On Page: 234

Spec App: 1859











EXPLANATION:
Reallocates water project funds by reducing $400,000
from the Miami Beach Stormwater Infrastructure
Improvement project and $100,000 from the Sunny
Isles Beach 172nd Street Drainage project, to
provide: $100,000 for the Aventura Hospital District
Stormwater Drainage System project; $50,000 for the
Bay Harbor Islands Installation of Automated Water
Meters project; $50,000 for the Surfside Sewer
Rehabilitation Phase I project; $100,000 for the
Highland Village Stormwater and Sanitary Sewer
Improvements project; $100,000 for the Key Biscayne
Sanitary Sewer project; and $100,000 for the North
Bay Village Wastewater Forcemain & Pump Replacement
project.
NET IMPACT ON: Total Funds General Revenue Trust Funds Recurring - 0 0 0 Non-Recurring - 0 0 0 ______________________________________________________________________________________ Positions & Amounts Positions & Amounts DELETE INSERT ENVIRONMENTAL PROTECTION, DEPARTMENT OF Program: Water Resource Management Water Resource Protection And Restoration 37350200 In Section 05 On Page 234 1859 Grants And Aids To Local Governments And 140047 Nonstate Entities - Fixed Capital Outlay Grants And Aids - Water Projects IOEM In the list of projects immediately following Specific Appropriation 1859, DELETE: Miami Beach Stormwater Infrastructure Improvement Project... 1,400,000 Sunny Isles Beach 172nd Street Drainage..................... 600,000 and INSERT: 997525 Log:0024 CSK/CSK 04/10/07 02:16:50 PM Senate Page: 1
Aventura Hospital District Stormwater Drainage System..... 100,000 Bay Harbor Islands Installation of Automated Water Meters... 50,000 Surfside Sewer Rehabilitation Phase I....................... 50,000 Highland Village Stormwater and Sanitary Sewer Improvements. 100,000 Key Biscayne Sanitary Sewer................................. 100,000 Miami Beach Stormwater Infrastructure Improvement Project... 1,000,000 North Bay Village Wastewater Forcemain & Pump Replacement... 100,000 Sunny Isles Beach 172nd Street Drainage..................... 500,000
Line item amendments are accepted as part of the amendatory process. However, due to the necessity of using computerized systems this may entail a different placement within a budget entity or the renumbering of the specific appropriation items. Items printed in italics are computer codes and are not a part of the official text of this amendment.
997525 Log:0024 CSK/CSK 04/10/07 02:16:50 PM Senate Page: 2