Florida Senate - 2008 SENATOR AMENDMENT

Bill No. CS/CS/HB 1399, 2nd Eng.

328378

CHAMBER ACTION

Senate

.

.

.

.

.

House



1

Senator Baker moved the following amendment to amendment

2

(844108):

3

4

     Senate Amendment (with title amendment)

5

     Delete line(s) 1375-1392

6

and insert:

7

8

     (7) If the department determines that it is in the best

9

interest of the public, the department may pay a stipend to

10

unsuccessful firms who have submitted responsive proposals for

11

construction or maintenance contracts. The decision and amount of

12

a stipend will be based upon department analysis of the estimated

13

proposal development costs and the anticipated degree of

14

competition during the procurement process. Stipends shall be

15

used to encourage competition and compensate unsuccessful firms

16

for a portion of their proposal development costs. The department

17

shall retain the right to use ideas from unsuccessful firms that

18

accept a stipend.

19

     (8)(7)(a) If the head of the department determines that it

20

is in the best interests of the public, the department may

21

combine the design and construction phases of a building, a major

22

bridge, a limited access facility, or a rail corridor project

23

into a single contract. Such contract is referred to as a design-

24

build contract. The department's goal shall be to procure up to

25

25 percent of the construction contracts which add capacity in

26

the 5-year adopted work program as design-build contracts by July

27

1, 2013. Design-build contracts may be advertised and awarded

28

notwithstanding the requirements of paragraph (3)(c). However,

29

construction activities may not begin on any portion of such

30

projects for which the department has not yet obtained title to

31

the necessary rights-of-way and easements for the construction of

32

that portion of the project has vested in the state or a local

33

governmental entity and all railroad crossing and utility

34

agreements have been executed. Title to rights-of-way shall be

35

deemed to have vested in the state when the title has been

36

dedicated to the public or acquired by prescription.

37

     (b)  The department shall adopt by rule procedures for

38

administering design-build contracts. Such procedures shall

39

include, but not be limited to:

40

     1.  Prequalification requirements.

41

     2.  Public announcement procedures.

42

     3.  Scope of service requirements.

43

     4.  Letters of interest requirements.

44

     5.  Short-listing criteria and procedures.

45

     6.  Bid proposal requirements.

46

     7.  Technical review committee.

47

     8.  Selection and award processes.

48

     9. Stipend requirements.

49

50

================ T I T L E  A M E N D M E N T ================

51

And the title is amended as follows:

52

     Delete line(s) 2889-2890

53

and insert:

54

s. 337.11, F.S.; providing for the department to pay a

55

portion of certain proposal development costs; requiring

56

the department to advertise certain contracts as design-

57

build contracts; amending s. 337.18, F.S.;

4/30/2008  8:39:00 PM     TR.20.09320