Florida Senate - 2008 SB 1506
By Senator Bennett
21-02713C-08 20081506__
1
A bill to be entitled
2
An act relating to electric utilities; amending s. 74.051,
3
F.S.; requiring a court to conduct a hearing and issue a
4
final judgment on a petition for a taking within specified
5
times after a utility's request for such hearing; amending
6
s. 186.801, F.S.; requiring a local government to advise
7
the Public Service Commission and utility of a need for
8
amendments to the local government's adopted comprehensive
9
plan or zoning ordinances for use of an electrical plant
10
site; amending s. 253.02, F.S.; authorizing the Secretary
11
of Environmental Protection or the board of a
12
jurisdictional water management district to grant
13
easements across lands owned by the Board of Trustees of
14
the Internal Improvement Trust Fund under certain
15
conditions; amending s. 253.034, F.S.; granting a utility
16
the use of nonsovereignty state-owned lands upon a showing
17
of competent substantial evidence that the use is
18
reasonable; establishing criteria relating to the title,
19
distribution, and cost of such lands; amending s. 337.401,
20
F.S.; requiring the Department of Environmental Protection
21
to adopt rules relating to the placement of and access to
22
aerial and underground electric transmission lines having
23
certain specifications; defining the term "base-load
24
generating facilities"; amending s. 366.93, F.S.; revising
25
the definitions of "cost" and "preconstruction"; requiring
26
the Public Service Commission to establish rules relating
27
to cost recovery for the construction of new, expanded, or
28
relocated electrical transmission lines and facilities for
30
F.S.; conforming cross-references; amending s. 403.503,
31
F.S.; defining the term "alternate corridor" and
32
redefining the term "corridor" for purposes of the Florida
33
Electrical Power Plant Siting Act; amending s. 403.504,
34
F.S.; requiring the Department of Environmental Protection
35
to determine whether a proposed alternate corridor is
36
acceptable; amending s. 403.506, F.S.; exempting an
37
electric utility from obtaining certification under the
38
Florida Electrical Power Plant Siting Act before
39
constructing facilities for a power plant using nuclear
40
materials as fuel; providing that a utility may obtain
41
separate licenses, permits, and approvals for such
42
construction under certain circumstances; amending s.
43
403.50665, F.S.; requiring an application to include a
44
statement on the consistency of directly nonlinear
45
associated facilities constituting a "development";
46
requiring the Department of Environmental Protection to
47
address at the certification hearing the issue of
48
compliance with land use plans and zoning ordinances for a
49
proposed substation located in or along an alternate
50
corridor; exempting directly associated linear facilities
51
from local government land use determinations; creating s.
52
403.5081, F.S., relating to a proposal for an alternative
53
transmission line corridor; providing a schedule and
54
certification process; requiring a party to file such
55
proposal within a specified period after an application is
56
filed; requiring the party to file a notice of proposal
57
with the administrative law judge, all parties, newly
58
affected agencies, and local governments; requiring that
59
such notice include certain information relating to the
60
alternate corridor; requiring the applicant and the
61
Department of Environmental Protection to file a notice
62
accepting or rejecting the proposal within 7 days after
63
receiving the notice; requiring that a certification
64
hearing and public hearing be held if the proposal is
65
rejected; requiring that a certification hearing be
66
rescheduled if the proposal is accepted; requiring that a
67
rescheduled certification hearing be held if the
68
Department of Environmental Protection determines that the
69
data are incomplete; authorizing the administrative law
70
judge to adjust the schedule if necessary; requiring that
71
the publication of all notices be in compliance with the
72
requirements for public notice; requiring an interested
73
party to provide data to certain agencies; requiring the
74
agencies to make recommendations to the Department of
75
Environmental Protection within 15 days after receiving
76
the data; requiring the Department of Environmental
77
Protection to determine if the data are complete;
78
requiring the party to submit additional data if the
79
department determines such data are incomplete; providing
80
that the proposal is considered withdrawn if the
81
Department of Environmental Protection determines that the
82
data remain incomplete within 14 days after receiving the
83
additional data; requiring an affected agency to submit a
84
supplementary report within a specified time after the
85
department makes such determination; providing that an
86
agency having a collegial body as agency head may submit a
87
draft of the report to the Department of Environmental
88
Protection by the specified deadline; requiring the
89
department to include an analysis of the agencies' reports
90
in its project analysis; prohibiting a party from filing
91
for an alternate corridor unless the application is
92
amended; authorizing the administrative law judge to
93
authorize a different starting or ending point based upon
94
a showing of good cause; prohibiting the presentation of
95
evidence at a certification hearing if the proposal was
96
improperly noticed; placing the burden of proof on the
97
party proposing the alternate corridor; requiring the
98
board, consisting of the Governor and Cabinet, to certify
99
an alternate corridor if it is accepted by the applicant
100
and the Department of Environmental Protection and if it
101
satisfies certain criteria; amending s. 403.509, F.S.;
102
requiring the board to certify the corridor having the
103
least adverse impact; authorizing the board to deny
104
certification or allow a party to amend its proposal;
105
amending s. 403.5115, F.S.; requiring the applicant
106
proposing the alternate corridor to publish all notices
107
relating to the application; requiring that such notices
108
comply with certain requirements; requiring that notices
109
be published at least 45 days before the rescheduled
110
certification hearing; amending s. 403.5175, F.S.;
111
conforming a cross-reference; amending s. 403.518, F.S.;
112
authorizing the Department of Environmental Protection to
113
charge an application fee for an alternate corridor;
114
authorizing the department to waive all or a portion of
115
such fee based on the applicant's economic circumstances;
117
determinations of need and general permits; conforming
118
provisions to changes made by the act; providing an
119
effective date.
120
121
Be It Enacted by the Legislature of the State of Florida:
122
123
Section 1. Present subsection (3) of section 74.051,
124
Florida Statutes, is redesignated as subsection (4), and a new
125
subsection (3) is added to that section, to read:
126
74.051 Hearing on order of taking.--
127
(3) If a defendant requests a hearing and the petitioner is
128
an electric utility that is seeking to appropriate property
129
necessary for an electric generation plant, an associated
130
facility of such plant, an electric substation, or a power line,
131
the court shall conduct the hearing no more than 120 days after
132
the petition is filed. The court shall issue its final judgment
133
no more than 30 days after the hearing.
134
Section 2. Paragraph (e) of subsection (2) of section
135
186.801, Florida Statutes, is amended to read:
136
186.801 Ten-year site plans.--
137
(2) Within 9 months after the receipt of the proposed plan,
138
the commission shall make a preliminary study of such plan and
139
classify it as "suitable" or "unsuitable." The commission may
140
suggest alternatives to the plan. All findings of the commission
141
shall be made available to the Department of Environmental
142
Protection for its consideration at any subsequent electrical
143
power plant site certification proceedings. It is recognized that
144
10-year site plans submitted by an electric utility are tentative
145
information for planning purposes only and may be amended at any
146
time at the discretion of the utility upon written notification
147
to the commission. A complete application for certification of an
148
electrical power plant site under chapter 403, when such site is
149
not designated in the current 10-year site plan of the applicant,
150
shall constitute an amendment to the 10-year site plan. In its
151
preliminary study of each 10-year site plan, the commission shall
152
consider such plan as a planning document and shall review:
153
(e) The views of appropriate local, state, and federal
154
agencies, including the views of the appropriate water management
155
district as to the availability of water and its recommendation
156
as to the use by the proposed plant of salt water or fresh water
157
for cooling purposes. The local government of the jurisdiction
158
where a specifically identified electrical power plant site is
159
located shall advise the commission and the utility if there is a
160
need to amend the local government's comprehensive plan adopted
161
pursuant to part II of chapter 163 or the zoning ordinances to
162
allow for use of the site. If a local government fails to
163
identify such a need, a site identified in a utility's plan
164
submitted in 2 or more consecutive years is presumed, for
165
purposes of s. 403.50665, to be consistent and in compliance with
166
the local government's land use plans and zoning ordinances.
167
Section 3. Subsection (2) of section 253.02, Florida
168
Statutes, is amended to read:
169
253.02 Board of trustees; powers and duties.--
170
(2)(a) The board of trustees shall not sell, transfer, or
171
otherwise dispose of any lands the title to which is vested in
172
the board of trustees except by vote of at least three of the
173
four trustees and as provided in this subsection.
174
(b) In order to promote efficient, effective, and
175
economical management of state lands and utility services and if
176
the Public Service Commission has determined a need exists or the
177
Federal Energy Regulatory Commission has granted a Certificate of
178
Public Convenience and Necessity, the authority to grant
179
easements for rights-of-way over, across, and upon lands the
180
title to which is vested in the board of trustees for the
181
construction and operation of natural gas pipeline transmission
182
and linear facilities, including electric transmission and
183
distribution facilities, is delegated to:
184
1. The Secretary of Environmental Protection for facilities
185
subject to part II of chapter 403; or
186
2. The Secretary of Environmental Protection or the
187
governing board of a jurisdictional water management district,
188
whichever has the authority under part IV of chapter 373 to
189
regulate facilities that are not subject to part II of chapter
190
403.
191
192
The board of trustees may review and approve such uses of state
193
lands if delegation would be inappropriate in regard to the
194
amount or location of state lands involved.
195
Section 4. Subsection (14) is added to section 253.034,
196
Florida Statutes, to read:
197
253.034 State-owned lands; uses.--
198
(14)(a) If a public utility, regional transmission
199
organization, or natural gas company presents competent and
200
substantial evidence that its use of nonsovereignty state-owned
201
lands is reasonable based upon a consideration of economic and
202
environmental factors, including an assessment of practicable
203
alternative alignments and assurance that the lands will remain
204
in their predominantly natural condition, the public utility,
205
regional transmission organization, or natural gas company may be
206
granted fee simple title, easements, or other interests in
207
nonsovereignty state-owned lands title to which is vested in the
208
board of trustees, a water management district, or any other
209
agency in the state for:
210
1. Electric transmission and distribution lines;
211
2. Natural gas pipelines; or
212
3. Other linear facilities for which the Public Service
213
Commission has determined a need exists or the Federal Energy
214
Regulatory Commission has issued a Certificate of Public
215
Convenience and Necessity.
216
(b) In exchange for less than a fee simple interest
217
acquired pursuant to this subsection, the grantee shall vest in
218
the grantor the same fee simple interest to other available land
219
that is at least 1.5 times the size of the land acquired by the
220
grantee. The grantor shall approve the property with a less than
221
fee simple interest on its behalf based on a determination that
222
the economic and ecological or recreational value is at least
223
equivalent to that of the property transferred to the public
224
utility, regional transmission organization, or natural gas
225
company.
226
(c) In exchange for a fee simple interest acquired pursuant
227
to this subsection, the grantee shall vest in the grantor a fee
228
simple title to other available land that is at least 2 times the
229
size of the land acquired by the grantee. The grantor shall
230
approve the land to be acquired on its behalf based on a
231
determination that the economic and ecological or recreational
232
value is at least equivalent to that of the property transferred
233
to the public utility, regional transmission organization, or
234
natural gas company.
235
(d) The grantee may, subject to the grantor's approval, pay
236
the fair market value of the state-owned land plus one-half of
237
the cost differential between the cost of constructing the
238
facility and the cost of constructing the facility on state-owned
239
land, up to a maximum of twice the fair market value of the land
240
acquired by the grantee. The grantor must use these moneys to
241
acquire fee simple or less than fee simple interest in other
242
available land.
243
Section 5. Subsection (1) of section 337.401, Florida
244
Statutes, is amended to read:
245
337.401 Use of right-of-way for utilities subject to
246
regulation; permit; fees.--
247
(1) The department and local governmental entities,
249
jurisdiction and control of public roads or publicly owned rail
250
corridors are authorized to prescribe and enforce reasonable
251
rules or regulations with reference to the placing and
252
maintaining along, across, or on any road or publicly owned rail
253
corridors under their respective jurisdictions any electric
254
transmission, telephone, telegraph, or other communications
255
services lines; pole lines; poles; railways; ditches; sewers;
256
water, heat, or gas mains; pipelines; fences; gasoline tanks and
257
pumps; or other structures hereinafter referred to in this
258
section as the "utility." The department shall adopt rules that
259
allow placement of and access to aerial and underground electric
260
utility transmission lines designed to operate at 69 kilovolts or
261
more which are adjacent to and within the right-of-way of any
262
department-controlled public roads, including longitudinally
263
within limited access facilities, to the extent allowed by
264
federal law and if access and placement complies with the minimum
265
clear zone and other safety standards and are needed to
266
accommodate the additional electrical transfer capacity on the
267
transmission grid resulting from new base-load generating
268
facilities. As used in this subsection, the term "base-load
269
generating facilities" means electrical power plants that are
270
certified under part II of chapter 403. The department may enter
271
into a permit-delegation agreement with a governmental entity if
272
issuance of a permit is based on requirements that the department
273
finds will ensure the safety and integrity of facilities of the
274
Department of Transportation; however, the permit-delegation
275
agreement does not apply to facilities of electric utilities as
276
defined in s. 366.02(2).
277
Section 6. Section 366.93, Florida Statutes, is amended to
278
read:
279
366.93 Cost recovery for the siting, design, licensing, and
280
construction of nuclear and integrated gasification combined
281
cycle power plants.--
282
(1) As used in this section, the term:
283
(a) "Cost" includes, but is not limited to, all capital
284
investments, including rate of return, any applicable taxes, and
285
all expenses, including operation and maintenance expenses,
286
related to or resulting from the siting, licensing, design,
287
construction, or operation of the nuclear power plant and any
288
new, enlarged, or relocated electrical transmission lines or
289
facilities of any size that are necessary to serve the nuclear or
290
integrated gasification combined cycle power plant.
291
(b) "Electric utility" or "utility" has the same meaning as
292
that provided in s. 366.8255(1)(a).
293
(c) "Integrated gasification combined cycle power plant" or
294
"plant" is an electrical power plant as defined in s. 403.503(14)
295
which s. 403.503(13) that uses synthesis gas produced by
296
integrated gasification technology.
297
(c)(d) "Nuclear power plant" or "plant" means is an
298
electrical power plant, as defined in s. 403.503(14), which s.
299
403.503(13) that uses nuclear materials for fuel.
300
(d)(e) "Power plant" or "plant" means a nuclear power plant
301
or an integrated gasification combined cycle power plant.
302
(e)(f) "Preconstruction" is that period of time after a
303
site, including any related electrical transmission lines or
304
facilities, has been selected through and including the date the
305
utility completes site-clearing site clearing work.
306
Preconstruction costs shall be afforded deferred accounting
307
treatment and shall accrue a carrying charge equal to the
308
utility's allowance for funds during construction (AFUDC) rate
309
until recovered in rates.
310
(2) Within 6 months after the enactment of this act, the
311
commission shall establish, by rule, alternative cost recovery
312
mechanisms for the recovery of costs incurred in the siting,
313
design, licensing, and construction of a nuclear power plant,
314
including new, expanded, or relocated electrical transmission
315
lines and facilities that are necessary to serve the nuclear or
316
integrated gasification combined cycle power plant. Such
317
mechanisms shall be designed to promote utility investment in
318
nuclear or integrated gasification combined cycle power plants
319
and allow for the recovery in rates of all prudently incurred
320
costs, and shall include, but need are not be limited to:
321
(a) Recovery through the capacity cost recovery clause of
322
any preconstruction costs.
323
(b) Recovery through an incremental increase in the
324
utility's capacity cost recovery clause rates of the carrying
325
costs on the utility's projected construction cost balance
326
associated with the nuclear or integrated gasification combined
327
cycle power plant. To encourage investment and provide certainty,
328
for nuclear or integrated gasification combined cycle power plant
329
need petitions submitted on or before December 31, 2010,
330
associated carrying costs shall be equal to the pretax AFUDC in
331
effect upon this act becoming law. For nuclear or integrated
332
gasification combined cycle power plants for which need petitions
333
are submitted after December 31, 2010, the utility's existing
334
pretax AFUDC rate is presumed to be appropriate unless determined
335
otherwise by the commission in the determination of need for the
336
nuclear or integrated gasification combined cycle power plant.
337
(3) After a petition for determination of need is granted,
338
a utility may petition the commission for cost recovery as
339
permitted by this section and commission rules.
340
(4) When the nuclear or integrated gasification combined
341
cycle power plant is placed in commercial service, the utility
342
shall be allowed to increase its base rate charges by the
343
projected annual revenue requirements of the nuclear or
344
integrated gasification combined cycle power plant based on the
345
jurisdictional annual revenue requirements of the plant for the
346
first 12 months of operation. The rate of return on capital
347
investments shall be calculated using the utility's rate of
348
return last approved by the commission prior to the commercial
349
inservice date of the nuclear or integrated gasification combined
350
cycle power plant. If any existing generating plant is retired as
351
a result of operation of the nuclear or integrated gasification
352
combined cycle power plant, the commission shall allow for the
353
recovery, through an increase in base rate charges, of the net
354
book value of the retired plant over a period not to exceed 5
355
years.
356
(5) The utility shall report to the commission annually the
357
budgeted and actual costs as compared to the estimated inservice
358
cost of the nuclear or integrated gasification combined cycle
359
power plant provided by the utility pursuant to s. 403.519(4),
360
until the commercial operation of the nuclear or integrated
361
gasification combined cycle power plant. The utility shall
362
provide such information on an annual basis following the final
363
order by the commission approving the determination of need for
364
the nuclear or integrated gasification combined cycle power
365
plant, with the understanding that some costs may be higher than
366
estimated and other costs may be lower.
367
(6) If In the event the utility elects not to complete or
368
is precluded from completing construction of the nuclear power
369
plant, including any new, expanded, or relocated electrical
370
transmission lines or facilities or integrated gasification
371
combined cycle power plant, the utility shall be allowed to
372
recover all prudent preconstruction and construction costs
373
incurred following the commission's issuance of a final order
374
granting a determination of need for the nuclear power plant and
375
electrical transmission lines and facilities or integrated
376
gasification combined cycle power plant. The utility shall
377
recover such costs through the capacity cost recovery clause over
378
a period equal to the period during which the costs were incurred
379
or 5 years, whichever is greater. The unrecovered balance during
380
the recovery period will accrue interest at the utility's
381
weighted average cost of capital as reported in the commission's
382
earnings surveillance reporting requirement for the prior year.
383
Section 7. Paragraph (c) of subsection (3) of section
384
380.23, Florida Statutes, is amended to read:
385
380.23 Federal consistency.--
386
(3) Consistency review shall be limited to review of the
387
following activities, uses, and projects to ensure that such
388
activities, uses, and projects are conducted in accordance with
389
the state's coastal management program:
390
(c) Federally licensed or permitted activities affecting
391
land or water uses when such activities are in or seaward of the
392
jurisdiction of local governments required to develop a coastal
393
zone protection element as provided in s. 380.24 and when such
394
activities involve:
395
1. Permits and licenses required under the Rivers and
396
Harbors Act of 1899, 33 U.S.C. ss. 401 et seq., as amended.
397
2. Permits and licenses required under the Marine
398
Protection, Research and Sanctuaries Act of 1972, 33 U.S.C. ss.
399
1401-1445 and 16 U.S.C. ss. 1431-1445, as amended.
400
3. Permits and licenses required under the Federal Water
401
Pollution Control Act of 1972, 33 U.S.C. ss. 1251 et seq., as
402
amended, unless such permitting activities have been delegated to
403
the state pursuant to said act.
404
4. Permits and licenses relating to the transportation of
405
hazardous substance materials or transportation and dumping which
406
are issued pursuant to the Hazardous Materials Transportation
407
Act, 49 U.S.C. ss. 1501 et seq., as amended, or 33 U.S.C. s.
408
1321, as amended.
409
5. Permits and licenses required under 15 U.S.C. ss. 717-
410
717w, 3301-3432, 42 U.S.C. ss. 7101-7352, and 43 U.S.C. ss. 1331-
411
1356 for construction and operation of interstate gas pipelines
412
and storage facilities.
413
6. Permits and licenses required for the siting and
414
construction of any new electrical power plants as defined in s.
416
relicensing of hydroelectric power plants under the Federal Power
417
Act, 16 U.S.C. ss. 791a et seq., as amended.
418
7. Permits and licenses required under the Mining Law of
419
1872, 30 U.S.C. ss. 21 et seq., as amended; the Mineral Lands
420
Leasing Act, 30 U.S.C. ss. 181 et seq., as amended; the Mineral
421
Leasing Act for Acquired Lands, 30 U.S.C. ss. 351 et seq., as
422
amended; the Federal Land Policy and Management Act, 43 U.S.C.
423
ss. 1701 et seq., as amended; the Mining in the Parks Act, 16
424
U.S.C. ss. 1901 et seq., as amended; and the OCS Lands Act, 43
425
U.S.C. ss. 1331 et seq., as amended, for drilling, mining,
426
pipelines, geological and geophysical activities, or rights-of-
427
way on public lands and permits and licenses required under the
428
Indian Mineral Development Act, 25 U.S.C. ss. 2101 et seq., as
429
amended.
430
8. Permits and licenses for areas leased under the OCS
431
Lands Act, 43 U.S.C. ss. 1331 et seq., as amended, including
432
leases and approvals of exploration, development, and production
433
plans.
434
9. Permits and licenses required under the Deepwater Port
435
Act of 1974, 33 U.S.C. ss. 1501 et seq., as amended.
436
10. Permits required for the taking of marine mammals under
437
the Marine Mammal Protection Act of 1972, as amended, 16 U.S.C.
438
s. 1374.
439
Section 8. Subsection (20) of section 403.031, Florida
440
Statutes, is amended to read:
441
403.031 Definitions.--In construing this chapter, or rules
442
and regulations adopted pursuant hereto, the following words,
443
phrases, or terms, unless the context otherwise indicates, have
444
the following meanings:
445
(20) "Electrical power plant" means, for purposes of this
446
part of this chapter, any electrical generating facility that
447
uses any process or fuel and that is owned or operated by an
449
and includes any associated facility that directly supports the
450
operation of the electrical power plant.
451
Section 9. Present subsections (3) through (30) of section
452
403.503, Florida Statutes, are redesignated as subsections (4)
453
through (31), respectively, a new subsection (3) is added to that
454
section, and present subsection (10) of that section is amended,
455
to read:
456
403.503 Definitions relating to Florida Electrical Power
457
Plant Siting Act.--As used in this act:
458
(3) "Alternate corridor" means an area that is proposed by
459
the applicant or a third party within which all or part of an
460
associated electrical transmission line right-of-way is to be
461
located and that is different from the preferred transmission
462
line corridor proposed by the applicant. The width of the
463
alternate corridor proposed for certification for an associated
464
electrical transmission line may be the width of the proposed
465
right-of-way or a wider boundary not to exceed a width of 1 mile.
466
The area within the alternate corridor may be further restricted
467
as a condition of certification. The alternate corridor may
468
include alternate electrical substation sites if the applicant
469
has proposed an electrical substation as part of the portion of
470
the proposed electrical transmission line.
471
(11)(10) "Corridor" means the proposed area within which an
472
associated linear facility right-of-way is to be located. The
473
width of the corridor proposed by an applicant for certification
474
as an associated facility, at the option of the applicant, may be
475
the width of the right-of-way or a wider boundary, not to exceed
476
a width of 1 mile. The area within the corridor in which a right-
477
of-way may be located may be further restricted by a condition of
478
certification. After all property interests required for the
479
right-of-way have been acquired by the licensee, the boundaries
480
of the area certified shall narrow to only that land within the
481
boundaries of the right-of-way. A corridor proposed for
482
certification must be addressed in the application, in amendments
483
to the application filed under s. 403.5064(3), and in notices of
484
acceptance filed by an applicant and the department pursuant to
485
s. 403.5081.
486
Section 10. Present subsections (9) through (12) of section
487
403.504, Florida Statutes, are redesignated as subsections (10)
488
through (13), respectively, and a new subsection (9) is added to
489
that section, to read:
490
403.504 Department of Environmental Protection; powers and
491
duties enumerated.--The department shall have the following
492
powers and duties in relation to this act:
493
(9) To determine whether an alternate corridor proposed for
494
consideration under s. 403.5081 is acceptable.
495
Section 11. Subsection (3) is added to section 403.506,
496
Florida Statutes, to read:
497
403.506 Applicability, thresholds, and certification.--
498
(3) An electric utility may obtain separate licenses,
499
permits, and approvals for the construction of facilities
500
necessary to construct an electrical power plant without first
501
obtaining certification under this act if the utility intends to
502
locate, license, and construct a proposed or expanded electrical
503
power plant that uses nuclear materials as fuel. Such facilities
504
may include, but are not limited to, access and onsite roads,
505
rail lines, electrical transmission facilities to support
506
construction, and facilities necessary for waterborne delivery of
507
construction materials and project components. This exemption
508
applies to such facilities regardless of whether the facilities
509
are used for operation of the power plant. The applicant shall
510
file with the department a statement that declares that the
511
construction of such facilities is necessary for the timely
512
construction of the proposed electrical power plant and
513
identifies those facilities that the applicant intends to seek
514
licenses for and construct prior to or separate from
515
certification of the project. The facilities may be located
516
within or off of the site for the proposed electrical power
517
plant. The filing of an application under this act does not
518
affect other applications for separate licenses which are pending
519
at the time of filing the application. Furthermore, the filing of
520
an application does not prevent an electric utility from seeking
521
separate licenses for facilities that are necessary to construct
522
the electrical power plant. Licenses, permits, or approvals
523
issued by any state, regional, or local agency for such
524
facilities shall be incorporated by the department into a final
525
certification upon completion of construction. Any facilities
526
necessary for construction of the electrical power plant shall
527
become part of the certified electrical power plant upon
528
completion of the electrical power plant's construction. The
529
exemption in this subsection does not require or authorize agency
530
rulemaking, and any action taken under this subsection is not
531
subject to chapter 120.
532
Section 12. Subsections (1), (2), (3), and (6) of section
533
403.50665, Florida Statutes are amended, and subsections (7) and
534
(8) are added to that section, to read:
535
403.50665 Land use consistency.--
536
(1) The applicant shall include in the application a
537
statement on the consistency of the site, or any directly
538
associated nonlinear facilities that constitute a "development,"
539
as defined by s. 380.04, with existing land use plans and zoning
540
ordinances that were in effect on the date the application was
541
filed and a full description of such consistency. However, such
542
statement is not required for a specifically identified
543
electrical power plant site under s. 186.801(2)(e).
544
(2) Within 45 days after the filing of the application,
545
each local government shall file a determination with the
546
department, the applicant, the administrative law judge, and all
547
parties on the consistency of the site or any directly associated
548
nonlinear facilities with existing land use plans and zoning
549
ordinances that were in effect on the date the application was
550
filed, based on the information provided in the application. The
551
local government may issue its determination up to 35 days later
552
if the local government has requested additional information on
553
land use and zoning consistency as part of the local government's
554
statement on completeness of the application submitted pursuant
555
to s. 403.5066(1)(a). Notice of the consistency determination
556
shall be published in accordance with the requirements of s.
557
558
(3) If the local government issues a determination that the
559
proposed electrical power plant and any directly associated
560
nonlinear facility is not consistent or in compliance with local
561
land use plans and zoning ordinances, the applicant may apply to
562
the local government for the necessary local approval to address
563
the inconsistencies in the local government's determination. If
564
the applicant makes such an application to the local government,
565
the time schedules under this act shall be tolled until the local
566
government issues its revised determination on land use and
567
zoning or the applicant otherwise withdraws its application to
568
the local government. If the applicant applies to the local
569
government for necessary local land use or zoning approval, the
570
local government shall issue a revised determination within 30
571
days following the conclusion of that local proceeding, and the
572
time schedules and notice requirements under this act shall apply
573
to such revised determination.
574
(6) If it is determined by the local government that the
575
proposed site or directly associated nonlinear facility does
576
conform with existing land use plans and zoning ordinances in
577
effect as of the date of the application and no petition has been
578
filed, the responsible zoning or planning authority shall not
579
thereafter change such land use plans or zoning ordinances so as
580
to foreclose construction and operation of the proposed site or
581
directly associated nonlinear facilities unless certification is
582
subsequently denied or withdrawn.
583
(7) If the department determines that an application for an
584
alternate corridor, accepted pursuant to s. 403.5081, is
585
complete, and if a portion of the applicant's preferred corridor
586
contains a location for a proposed substation and the proposed
587
alternate corridor contains a different electrical substation
588
location than that proposed by the applicant, the issue of
589
compliance with existing land use plans and zoning ordinances for
590
the proposed substation location in or along the alternate
591
corridor must be addressed at the site-certification hearing.
592
(8) A directly associated linear facility, including an
593
electrical transmission line, pipeline, or railway line, is
594
exempt from local government land use plans and zoning ordinances
595
under part II of chapter 163, and is not subject to local
596
government land use determinations or hearings held under this
597
section.
598
Section 13. Section 403.5081, Florida Statutes, is created
599
to read:
600
403.5081 Alternate transmission line corridors.--
601
(1) A party may, within 112 days after an application is
602
filed, propose one or more alternate transmission line corridor
603
routes for consideration under this act. An application for an
604
alternate corridor may not be filed for any other linear
605
facilities. The alternate corridor route may be for all or a
606
portion of the applicant's proposed corridor route, but must have
607
the same starting and ending points, and intermediate substation
608
or substation expansions, if any, as those proposed by the
609
applicant. If more than one alternate corridor is proposed by a
610
party, the party must designate which of the alternate corridors
611
is the primary alternate corridor and which is the secondary
612
alternate corridor.
613
(a) A notice proposing an alternate corridor must be filed
614
with the administrative law judge, all parties, any newly
615
affected agencies, and any local governments within which the
616
proposed alternate corridor is located. The notice must include
617
the most recent United States Geological Survey 1:24,000
618
quadrangle maps specifically delineating the corridor boundaries,
619
a description of the proposed alternate corridor, and a statement
620
of the reasons the proposed alternate corridor should be
621
certified.
622
(b)1. Within 7 days after the notice is received, the
623
applicant and the department shall file a notice accepting or
624
rejecting the proposal for an alternate corridor. The notice must
625
be filed with the administrative law judge and all parties. The
626
acceptance of a proposed alternate corridor by the applicant may
627
include the acceptance of a proposed alternate substation
628
location, at the applicant's option. If the alternate corridor is
629
rejected by the applicant or department, the certification
630
hearing and the public hearings must be held as scheduled. If
631
both the applicant and the department accept a proposed alternate
632
corridor for consideration, the certification hearing must be
633
rescheduled as provided in this paragraph, if necessary. The
634
alternate corridor must be accepted by both the applicant and the
635
department to receive further consideration.
636
2. If the certification hearing is rescheduled, it must be
637
held no more than 90 days after the previously scheduled
638
certification hearing. If the data submitted under paragraph (d)
639
are determined to be incomplete, the rescheduled certification
640
hearing shall be held no more than 105 days after the previously
641
scheduled certification hearing. If the alternate corridor
642
crosses the jurisdiction of a local government that was not
643
previously affected and, as a result, additional time is needed,
644
the schedule provided in this subsection shall be adjusted
645
accordingly by the administrative law judge to allow the newly
646
affected local government time to prepare a report pursuant to s.
647
648
(c) Notice for the filing of the proposed alternate
649
corridor, the revised time schedules, the deadline for newly
650
affected persons and agencies to file notice of intent to become
651
a party, the rescheduled hearing date, and the proceedings shall
652
be published in accordance with the requirements in s. 403.5115.
653
(d) Within 21 days after the department and the applicant
654
accept an alternate corridor, the party proposing an alternate
655
corridor shall provide all data required under the department's
656
rules and approved application forms to the agencies listed in s.
657
403.507(2) and newly affected agencies.
658
(e)1. An agency that is reviewing the data must advise the
659
department of any issues concerning the completeness of the data
660
relating to the alternate corridor within 15 days after the data
661
are submitted.
662
2. Within 22 days after the data are submitted, the
663
department shall determine whether the data are complete. If the
664
department determines that the data are incomplete, the party
665
proposing the alternate corridor must submit additional data to
666
cure the incompleteness. This additional data must be submitted
667
within 14 days after the department determines the data to be
668
incomplete.
669
3. If the department, within 14 days after the additional
670
data are submitted, determines that the data remain incomplete,
671
the proposal for an alternate corridor is considered withdrawn.
672
The department may base its determination on recommendations
673
submitted by the affected agencies.
674
(f) An agency listed in s. 403.507(2) and any newly
675
affected agency shall file a supplementary report with the
676
applicant and the department no later than 24 days after the data
677
are determined to be complete.
678
(g) The agency report must include the information required
679
under s. 403.507(2) and (3).
680
(h) If an agency required to submit a report pursuant to
681
this section has a collegial body as its agency head and the
682
agency's internal procedures require such report to be reviewed
683
by its agency head prior to finalization, the agency may submit a
684
draft version of the report to the department by the deadline
685
provided in paragraph (f). However, the agency shall submit a
686
final version of the report to the department after review by the
687
agency head and no later than 7 days after the deadline provided
688
in paragraph (f).
689
(i) The department shall include analysis of the agencies'
690
supplemental reports in its project analysis that must be filed
691
pursuant to s. 403.507(5).
692
(2) If the original date for the certification hearing is
693
rescheduled as a result of the acceptance of an alternate
694
corridor, a party may not file an additional proposal for an
695
alternate corridor. However, if an applicant submits an amendment
696
to its application which changes the alignment of the proposed
697
corridor, the certification hearing must be rescheduled to allow
698
a party time to propose an alternate corridor to the realigned
699
corridor. A proposal for an alternate corridor shall have the
700
same starting and ending points as the realigned portion of the
701
corridor unless the administrative law judge, based upon a
702
showing of good cause, authorizes otherwise.
703
(3)(a) Notwithstanding the rejection of a proposal for an
704
alternate corridor by the applicant or the department, any party
705
may present evidence at the certification hearing to show that a
706
corridor otherwise appropriate for certification does not satisfy
707
the criteria in s. 403.509(3) or that a rejected alternate
708
corridor satisfies the criteria in that section. Evidence may not
709
be admitted at the certification hearing unless the notice for
710
the alternate corridor was filed no later than 112 days after the
711
filing of the application or by the submission of an amendment to
712
the application. The board shall consider rejected alternate
713
corridors pursuant to s. 403.509(3).
714
(b) A party that proposes an alternate corridor has the
715
burden of proving that the alternate corridor satisfies the
716
certification criteria. Under this act, an applicant or agency
717
that is not proposing an alternate corridor is not required to
718
submit data in support of the alternate corridor.
719
(4) The board shall certify an alternate corridor if it is
720
accepted by the applicant and the department pursuant to a notice
721
of acceptance, and if the board determines that the alternate
722
corridor satisfies the criteria in s. 403.509(3).
723
Section 14. Paragraph (d) of subsection (3) of section
724
403.509, Florida Statutes, is amended, present subsections (4)
725
through (6) of that section, are redesignated as subsections (5)
726
through (7), respectively, and a new subsection (4) is added to
727
that section, to read:
728
403.509 Final disposition of application.--
729
(3) In determining whether an application should be
730
approved in whole, approved with modifications or conditions, or
731
denied, the board, or secretary when applicable, shall consider
732
whether, and the extent to which, the location of the electrical
733
power plant and directly associated facilities and their
734
construction and operation will:
735
(d) Meet the electrical energy needs of the state in an
736
orderly, reliable, and timely fashion.
737
(4)(a) The board shall certify a transmission line corridor
738
that meets the criteria of this section. If more than one
739
transmission line corridor satisfies the criteria for
740
certification, the board shall certify the transmission line
741
corridor that has the least adverse impact, including costs, with
742
respect to the criteria provided in subsection (3).
743
(b) If the board finds that an alternate corridor, rejected
744
pursuant to s. 403.5081, satisfies the criteria of subsection (3)
745
and has the least adverse impact compared to other corridors that
746
satisfy the criteria, the board may deny certification or allow
747
the applicant to amend its application.
748
(c) If the board finds that two or more corridors
749
appropriate for certification have the least adverse impact,
750
including costs, and the corridors are substantially equal in
751
impact, the board shall certify the corridor preferred by the
752
applicant.
753
Section 15. Subsection (5) is added to section 403.5115,
754
Florida Statutes, to read:
755
403.5115 Public notice.--
756
(5) An applicant shall publish public notices concerning
757
the filing of a proposal for an alternate corridor; the route of
758
the alternate corridor; the revised time schedules, if any; the
759
filing deadline for a petition to become a party; and the date of
760
the rescheduled certification hearing, if necessary. For purposes
761
of this subsection, all notices must be published in a newspaper
762
or newspapers of general circulation within the county or
763
counties affected by the proposed alternate corridor and must
764
comply with the requirements provided in subsection (2). The
765
notices must be published at least 45 days before the date of the
766
rescheduled certification hearing.
767
Section 16. Subsection (1) of section 403.5175, Florida
768
Statutes, is amended to read:
769
403.5175 Existing electrical power plant site
770
certification.--
771
(1) An electric utility that owns or operates an existing
772
electrical power plant as defined in s. 403.503(14) s.
773
403.503(13) may apply for certification of an existing power
774
plant and its site in order to obtain all agency licenses
775
necessary to ensure compliance with federal or state
776
environmental laws and regulation using the centrally
777
coordinated, one-stop licensing process established by this part.
778
An application for site certification under this section must be
779
in the form prescribed by department rule. Applications must be
780
reviewed and processed using the same procedural steps and
781
notices as for an application for a new facility, except that a
782
determination of need by the Public Service Commission is not
783
required.
784
Section 17. Subsection (6) is added to section 403.518,
785
Florida Statutes, to read:
786
403.518 Fees; disposition.--The department shall charge the
787
applicant the following fees, as appropriate, which, unless
788
otherwise specified, shall be paid into the Florida Permit Fee
789
Trust Fund:
790
(6)(a) An application fee for an alternate corridor filed
791
pursuant to s. 403.5081. The application fee shall be $750 per
792
mile for each mile of the alternate corridor located within an
793
existing electric transmission line right-of-way or within an
794
existing right-of-way for a road, highway, railroad, or other
795
aboveground linear facility, or $1,000 per mile for each mile of
796
an electric transmission line corridor proposed to be located
797
outside the existing right-of-way.
798
(b) The department may waive all or a portion of the
799
application fee based on the applicant's economic circumstances.
800
Section 18. Subsection (4) of section 403.519, Florida
801
Statutes, is amended to read:
802
403.519 Exclusive forum for determination of need.--
803
(4) In making its determination on a proposed electrical
804
power plant using nuclear materials or synthesis gas produced by
805
integrated gasification combined cycle power plant as fuel, the
806
commission shall hold a hearing within 90 days after the filing
807
of the petition to determine need and shall issue an order
808
granting or denying the petition within 135 days after the date
809
of the filing of the petition. The commission shall be the sole
810
forum for the determination of this matter and the issues
811
addressed in the petition, which accordingly shall not be
812
reviewed in any other forum, or in the review of proceedings in
813
such other forum. In making its determination to either grant or
814
deny the petition, the commission shall consider the need for
815
electric system reliability and integrity, including fuel
816
diversity, the need for base-load generating capacity, the need
817
for adequate electricity at a reasonable cost, and whether
818
renewable energy sources and technologies, as well as
819
conservation measures, are utilized to the extent reasonably
820
available.
821
(a) The applicant's petition shall include:
822
1. A description of the need for the generation capacity.
823
2. A description of how the proposed nuclear or integrated
824
gasification combined cycle power plant will enhance the
825
reliability of electric power production within the state by
826
improving the balance of power plant fuel diversity and reducing
827
Florida's dependence on fuel oil and natural gas.
828
3. A description of and a nonbinding estimate of the cost
829
of the nuclear or integrated gasification combined cycle power
830
plant, including any costs associated with new, enlarged, or
831
relocated electrical transmission lines or facilities of any size
832
that are necessary to serve the nuclear power plant.
833
4. The annualized base revenue requirement for the first 12
834
months of operation of the nuclear or integrated gasification
835
combined cycle power plant.
836
5. Information on whether there were any discussions with
837
any electric utilities regarding ownership of a portion of the
838
nuclear or integrated gasification combined cycle power plant by
839
such electric utilities.
840
(b) In making its determination, the commission shall take
841
into account matters within its jurisdiction, which it deems
842
relevant, including whether the nuclear or integrated
843
gasification combined cycle power plant will:
844
1. Provide needed base-load capacity.
845
2. Enhance the reliability of electric power production
846
within the state by improving the balance of power plant fuel
847
diversity and reducing Florida's dependence on fuel oil and
848
natural gas.
849
3. Provide the most cost-effective source of power, taking
850
into account the need to improve the balance of fuel diversity,
851
reduce Florida's dependence on fuel oil and natural gas, reduce
852
air emission compliance costs, and contribute to the long-term
853
stability and reliability of the electric grid.
854
(c) No provision of rule 25-22.082, Florida Administrative
855
Code, shall be applicable to a nuclear or integrated gasification
856
combined cycle power plant sited under this act, including
857
provisions for cost recovery, and an applicant shall not
858
otherwise be required to secure competitive proposals for power
859
supply prior to making application under this act or receiving a
860
determination of need from the commission.
861
(d) The commission's determination of need for a nuclear or
862
integrated gasification combined cycle power plant shall create a
863
presumption of public need and necessity and shall serve as the
864
commission's report required by s. 403.507(4)(a). An order
865
entered pursuant to this section constitutes final agency action.
866
Any petition for reconsideration of a final order on a petition
867
for need determination shall be filed within 5 days after the
868
date of such order. The commission's final order, including any
869
order on reconsideration, shall be reviewable on appeal in the
870
Florida Supreme Court. Inasmuch as delay in the determination of
871
need will delay siting of a nuclear or integrated gasification
872
combined cycle power plant or diminish the opportunity for
873
savings to customers under the federal Energy Policy Act of 2005,
874
the Supreme Court shall proceed to hear and determine the action
875
as expeditiously as practicable and give the action precedence
876
over matters not accorded similar precedence by law.
877
(e) After a petition for determination of need for a
878
nuclear or integrated gasification combined cycle power plant has
879
been granted, the right of a utility to recover any costs
880
incurred prior to commercial operation, including, but not
881
limited to, costs associated with the siting, design, licensing,
882
or construction of the plant and new, expanded, or relocated
883
electrical transmission lines or facilities of any size that are
884
necessary to serve the nuclear power plant, shall not be subject
885
to challenge unless and only to the extent the commission finds,
886
based on a preponderance of the evidence adduced at a hearing
887
before the commission under s. 120.57, that certain costs were
888
imprudently incurred. Proceeding with the construction of the
889
nuclear or integrated gasification combined cycle power plant
890
following an order by the commission approving the need for the
891
nuclear or integrated gasification combined cycle power plant
892
under this act shall not constitute or be evidence of imprudence.
893
Imprudence shall not include any cost increases due to events
894
beyond the utility's control. Further, a utility's right to
895
recover costs associated with a nuclear or integrated
896
gasification combined cycle power plant may not be raised in any
897
other forum or in the review of proceedings in such other forum.
898
Costs incurred prior to commercial operation shall be recovered
899
pursuant to chapter 366.
900
Section 19. Paragraph (i) of subsection (6) of section
901
403.814, Florida Statutes, is amended to read:
902
403.814 General permits; delegation.--
903
(6) Construction and maintenance of electric transmission
904
or distribution lines in wetlands by electric utilities, as
905
defined in s. 366.02, shall be authorized by general permit
906
provided the following provisions are implemented:
907
(i) This subsection applies to transmission lines and
908
appurtenances certified pursuant to part II of this chapter.
909
However, the criteria of the general permit shall not otherwise
910
affect the authority of the siting board to condition
911
certification of transmission lines as authorized under part II
912
of this chapter.
913
914
Maintenance of existing electric lines and clearing of vegetation
915
in wetlands conducted without the placement of structures in
916
wetlands or other dredge and fill activities does not require an
917
individual or general construction permit. For the purpose of
918
this subsection, wetlands shall mean the landward extent of
919
waters of the state regulated under ss. 403.91-403.929 and
920
isolated and nonisolated wetlands regulated under part IV of
921
chapter 373. The provisions provided in this subsection apply to
922
the permitting requirements of the department, any water
923
management district, and any local government implementing part
924
IV of chapter 373 or part VIII of this chapter.
925
Section 20. This act shall take effect upon becoming a law.
CODING: Words stricken are deletions; words underlined are additions.