     Section 48.  Section 377.921, Florida Statutes, is created

7

to read:

8

     377.921 Qualified solar energy system program.-The

9

Legislature finds that qualified solar energy systems provide

10

fuel savings and can help protect against future electricity and

11

natural gas shortages, reduce the state's dependence on foreign

12

sources of energy, and improve environmental conditions. The

13

Legislature further finds that the deployment of qualified solar

14

energy systems advances Florida's goals of promoting energy

15

efficiency and the development of renewable energy resources.

16

Therefore, the Legislature finds that it is in the public

17

interest to encourage public utilities to develop and implement

18

programs that promote the deployment and use of qualified solar

19

energy systems.     

20

     (2) As used in this section:     

21

     (a) "Qualified solar energy system" means a solar thermal

22

water heating system installed at a customer's premises under a

23

program administered and facilitated by a public utility. In

24

order for a system to be deemed as qualified under this section,

25

the public utility must incur all costs of the purchase and

26

installation of the system, whether directly or indirectly

27

through a customer rebate.     

28

     (b) "Public utility" or "utility" means a utility as

29

defined in s. 366.02(1).     

30

     (c) "Eligible program" means a program developed by a

31

public utility and approved by the commission pursuant to

32

subsection (5) under which the utility facilitates the

33

installation of solar thermal water heating systems at a utility

34

customer's premises.     

35

     (d) "Program fuel cost savings" means the total fuel cost

36

savings that a utility is projected to achieve from all solar

37

thermal water heating systems installed at a customer's premises

38

over the life of the qualified solar energy system.     

39

     (e) "Program costs" means all costs incurred in

40

implementing an eligible program, including, but not limited to:     

41

     1. In-service capital investments, including the utility's

42

last authorized rate of return thereon; and     

43

     2. Operating and maintenance expense, including, but not

44

limited to, labor, overhead, materials, advertising, marketing,

45

customer incentives, or rebates.     

46

     (3) Notwithstanding any provision in chapter 366 or rule to

47

the contrary, a public utility shall be allowed to recover

48

through the energy conservation cost-recovery clause, either as

49

period expenses or by capitalizing and amortizing, all prudent

50

and reasonable program costs incurred in implementing an eligible

51

program. With respect to any solar hot water heating system, the

52

amortization period shall be 5 years.     

53

     (4) Notwithstanding any provision in chapter 366 or rule to

54

the contrary, and in addition to recovery under subsection (3), a

55

utility shall be allowed to recover through the fuel cost-

56

recovery clause beginning in the year each solar thermal water

57

heating system begins operation 50 percent of any such program

58

fuel cost savings for five years from the installation date. The

59

remaining 50 percent of fuel saving shall be returned to the

60

utility's customers through the fuel cost-recovery clause.     

61

     (5) Notwithstanding any provision in chapter 366 or rule to

62

the contrary, the commission shall enter an order approving a

63

public utility's qualified solar energy system program if the

64

utility demonstrates in a petition that:     

65

(a) The qualified solar energy systems to be installed as

66

part of the program at minimum meet applicable Solar Rating and

67

Certification Corporation OG-300 certification requirements.     

68

     (b) The qualified solar energy systems are constructed and

69

installed in conformity with the manufacturer's specifications

70

and all applicable codes and standards.     

71

     (6) Within 60 days after receiving a petition to approve a

72

qualified solar energy system program, the commission shall

73

approve the petition or inform the utility of any deficiencies

74

therein. If the commission informs the utility of deficiencies,

75

the utility may correct those deficiencies and refile its

76

petition to approve the qualified solar energy system program.     

77

     (7) In order to encourage public utilities to promote the

78

deployment and use of qualified solar energy systems, the public

79

utility shall own the renewable attributes or benefits associated

80

with the energy output of a qualified solar energy system

81

installed pursuant to an eligible program, including any

82

renewable energy credit or other instrument issued as a result of

83

the utility's eligible program.

84

     (8) This section shall sunset on June 30, 2011 unless

85

reenacted by the Legislature. Utilities may not enroll new

86

customers in the qualified solar energy program after June 30,

87

2011 unless this section is reenacted.

88

89

(renumber subsequent sections)

4/16/2008  4:50:00 PM     EP.37.07773

CODING: Words stricken are deletions; words underlined are additions.