Florida Senate - 2008 COMMITTEE AMENDMENT
Bill No. CS for CS for SB 1978
227172
Senate
Comm: RS
4/24/2008
.
.
.
.
.
House
1
The Committee on Transportation and Economic Development
2
Appropriations (Margolis) recommended the following amendment:
3
4
Senate Amendment (with title amendment)
5
Between line(s) 472 and 473
6
insert:
7
8
Section 4. Subsection (9), subsection (12) of section
9
163.3180, Florida Statutes, are amended to read:
10
163.3180 Concurrency.--
11
(9)(a) Each local government may adopt as a part of its
12
plan, long-term transportation and school concurrency management
13
systems with a planning period of up to 10 years for specially
14
designated districts or areas where significant backlogs exist.
15
The plan may include interim level-of-service standards on
16
certain facilities and shall rely on the local government's
17
schedule of capital improvements for up to 10 years as a basis
18
for issuing development orders that authorize commencement of
19
construction in these designated districts or areas. The
20
concurrency management system must be designed to correct
21
existing deficiencies and set priorities for addressing
22
backlogged facilities. The concurrency management system must be
23
financially feasible and consistent with other portions of the
24
adopted local plan, including the future land use map.
25
(b) If a local government has a transportation or school
26
facility backlog for existing development which cannot be
27
adequately addressed in a 10-year plan, the state land planning
28
agency may allow it to develop a plan and long-term schedule of
29
capital improvements covering up to 15 years for good and
30
sufficient cause, based on a general comparison between that
31
local government and all other similarly situated local
32
jurisdictions, using the following factors:
33
1. The extent of the backlog.
34
2. For roads, whether the backlog is on local or state
35
roads.
36
3. The cost of eliminating the backlog.
37
4. The local government's tax and other revenue-raising
38
efforts.
39
(c) The local government may issue approvals to commence
40
construction notwithstanding this section, consistent with and in
41
areas that are subject to a long-term concurrency management
42
system.
43
(d) If the local government adopts a long-term concurrency
44
management system, it must evaluate the system periodically. At a
45
minimum, the local government must assess its progress toward
46
improving levels of service within the long-term concurrency
47
management district or area in the evaluation and appraisal
48
report and determine any changes that are necessary to accelerate
49
progress in meeting acceptable levels of service.
50
(e) The Department of Transportation shall establish an
51
approved transportation methodology that recognizes that a
52
planned, sustainable development of regional impact is likely to
53
achieve an internal capture rate greater than 40 percent when
54
fully developed. The transportation methodology must use a
55
regional transportation model that incorporates professionally
56
accepted modeling techniques applicable to well-planned,
57
sustainable communities of the size, location, mix of uses, and
58
design features consistent with such communities. The adopted
59
transportation methodology shall serve as the basis for
60
sustainable development traffic impact assessments by the
61
department. The methodology review must be completed and in use
62
by December 1, 2008.
63
(12) A development of regional impact may satisfy the
64
transportation concurrency requirements of the local
65
comprehensive plan, the local government's concurrency management
66
system, and s. 380.06 by payment of a proportionate-share
67
contribution for local and regionally significant traffic
68
impacts, if:
69
(a) The development of regional impact which, based on its
70
location or mix of land uses, is designed to encourage pedestrian
71
or other nonautomotive modes of transportation;
72
(b) The proportionate-share contribution for local and
73
regionally significant traffic impacts is sufficient to pay for
74
one or more required mobility improvements that will benefit a
75
regionally significant transportation facility;
76
(c) The owner and developer of the development of regional
77
impact pays or assures payment of the proportionate-share
78
contribution; and
79
(d) If the regionally significant transportation facility
80
to be constructed or improved is under the maintenance authority
81
of a governmental entity, as defined by s. 334.03(12), other than
82
the local government with jurisdiction over the development of
83
regional impact, the developer is required to enter into a
84
binding and legally enforceable commitment to transfer funds to
85
the governmental entity having maintenance authority or to
86
otherwise assure construction or improvement of the facility.
87
88
The proportionate-share contribution may be applied to any
89
transportation facility to satisfy the provisions of this
90
subsection and the local comprehensive plan, but, for the
91
purposes of this subsection, the amount of the proportionate-
92
share contribution shall be calculated based upon the cumulative
93
number of trips from the proposed development expected to reach
94
roadways during the peak hour from the complete buildout of a
95
stage or phase being approved, divided by the change in the peak
96
hour maximum service volume of roadways resulting from
97
construction of an improvement necessary to maintain the adopted
98
level of service, multiplied by the construction cost, at the
99
time of developer payment, of the improvement necessary to
100
maintain the adopted level of service. If the number of trips
101
used in this calculation includes trips from an earlier phase of
102
development, the determination of mitigation for a subsequent
103
phase or stage of development shall account for any mitigation
104
required by the development order and provided by the developer
105
for the earlier phase or stage, calculated at present value. For
106
purposes of this subsection, the term "present value" means the
107
fair market value of right-of-way at the time of contribution or
108
the actual dollar value of the construction improvements at the
109
date of completion, adjusted by the Consumer Price Index. For
110
purposes of this subsection, "construction cost" includes all
111
associated costs of the improvement. Proportionate-share
112
mitigation shall be limited to ensure that a development of
113
regional impact meeting the requirements of this subsection
114
mitigates its impact on the transportation system but is not
115
responsible for the additional cost of reducing or eliminating
116
backlogs. For purposes of this subsection, "backlogged
117
transportation facility" is defined as one on which the adopted
118
level-of-service standard is exceeded by the existing trips plus
119
committed trips. A developer may not be required to fund or
120
construct proportionate share mitigation for any backlogged
121
transportation facility that is more extensive than mitigation
122
necessary to offset the impact of the development project in
123
question. This subsection also applies to Florida Quality
124
Developments pursuant to s. 380.061 and to detailed specific area
125
plans implementing optional sector plans pursuant to s. 163.3245.
126
127
128
129
================ T I T L E A M E N D M E N T ================
130
And the title is amended as follows:
131
On line 12, after the semicolon
132
insert:
133
amending s. 163.3180, F.S.; requiring the Department of
134
Transportation to establish a transportation methodology
135
to serve as the basis for sustainable development impact
136
assessments; defining the terms "present value" and
137
"backlogged transportation facility";
4/24/2008 10:39:00 AM TR.TA.08580
CODING: Words stricken are deletions; words underlined are additions.