1 | A bill to be entitled |
2 | An act relating to cost recovery for the siting, design, |
3 | licensing, and construction of nuclear and integrated |
4 | gasification combined cycle power plants; amending s. |
5 | 366.93, F.S.; revising provisions for the recovery of |
6 | costs; authorizing a utility to recover costs through |
7 | rates upon a determination by the Public Service |
8 | Commission that the costs are prudent; providing that |
9 | approved rates shall not become effective prior to a |
10 | certain date; providing for adjustment of rates approved |
11 | without a determination that the costs are prudent; |
12 | providing for refunds to customers; removing a provision |
13 | for recovery of the net value of displaced generating |
14 | plants; removing provisions that allowed recovery of |
15 | certain costs when the utility elects not to complete |
16 | construction of a nuclear power plant or integrated |
17 | gasification combined cycle power plant; requiring refunds |
18 | to customers of amounts recovered for an abandoned project |
19 | and specifying manner of refunds; providing an effective |
20 | date. |
21 |
|
22 | Be It Enacted by the Legislature of the State of Florida: |
23 |
|
24 | Section 1. Section 366.93, Florida Statutes, is amended to |
25 | read: |
26 | 366.93 Cost recovery for the siting, design, licensing, |
27 | and construction of nuclear and integrated gasification combined |
28 | cycle power plants.-- |
29 | (1) As used in this section, the term: |
30 | (a) "Cost" includes, but is not limited to, all capital |
31 | investments, including rate of return, any applicable taxes, and |
32 | all expenses, including operation and maintenance expenses, |
33 | related to or resulting from the siting, licensing, design, |
34 | construction, or operation of the nuclear power plant, including |
35 | new, expanded, or relocated electrical transmission lines or |
36 | facilities of any size that are necessary thereto, or of the |
37 | integrated gasification combined cycle power plant. |
38 | (b) "Electric utility" or "utility" has the same meaning |
39 | as that provided in s. 366.8255(1)(a). |
40 | (c) "Integrated gasification combined cycle power plant" |
41 | or "plant" means an electrical power plant as defined in s. |
42 | 403.503(14) that uses synthesis gas produced by integrated |
43 | gasification technology. |
44 | (d) "Nuclear power plant" or "plant" means an electrical |
45 | power plant as defined in s. 403.503(14) that uses nuclear |
46 | materials for fuel. |
47 | (e) "Power plant" or "plant" means a nuclear power plant |
48 | or an integrated gasification combined cycle power plant. |
49 | (f) "Preconstruction" is that period of time after a site, |
50 | including any related electrical transmission lines or |
51 | facilities, has been selected through and including the date the |
52 | utility completes site clearing work. Preconstruction costs |
53 | shall be afforded deferred accounting treatment and shall accrue |
54 | a carrying charge equal to the utility's allowance for funds |
55 | during construction (AFUDC) rate until recovered in rates. |
56 | (2) Within 6 months after the enactment of this act, the |
57 | commission shall establish, by rule, alternative cost recovery |
58 | mechanisms for the recovery of costs incurred in the siting, |
59 | design, licensing, and construction of a nuclear power plant, |
60 | including new, expanded, or relocated electrical transmission |
61 | lines and facilities that are necessary thereto, or of an |
62 | integrated gasification combined cycle power plant. Such |
63 | mechanisms shall be designed to promote utility investment in |
64 | nuclear or integrated gasification combined cycle power plants |
65 | and allow for the recovery in rates of all prudently incurred |
66 | costs and shall include, but not be limited to: |
67 | (a) Recovery through the capacity cost recovery clause of |
68 | any preconstruction costs. |
69 | (b) Recovery through an incremental increase in the |
70 | utility's capacity cost recovery clause rates of the carrying |
71 | costs on the utility's projected construction cost balance |
72 | associated with the nuclear or integrated gasification combined |
73 | cycle power plant. To encourage investment and provide |
74 | certainty, for nuclear or integrated gasification combined cycle |
75 | power plant need petitions submitted on or before December 31, |
76 | 2010, associated carrying costs shall be equal to the pretax |
77 | AFUDC in effect upon this act becoming law. For nuclear or |
78 | integrated gasification combined cycle power plants for which |
79 | need petitions are submitted after December 31, 2010, the |
80 | utility's existing pretax AFUDC rate is presumed to be |
81 | appropriate unless determined otherwise by the commission in the |
82 | determination of need for the nuclear or integrated gasification |
83 | combined cycle power plant. |
84 | (3) After a petition for determination of need is granted, |
85 | a utility may petition the commission for cost recovery of |
86 | prudently incurred costs as permitted by this section and |
87 | commission rules. The utility may begin recovery of such costs |
88 | through rates upon a determination by the commission that the |
89 | costs are prudent, provided that the approved rates shall not |
90 | become effective prior to January 1, 2011. Any rate currently in |
91 | effect that permits recovery of costs subject to this section |
92 | that the commission has not deemed prudent shall be adjusted to |
93 | remove the impact of such costs, and the utility shall refund to |
94 | its customers an amount equal to the costs removed, plus |
95 | appropriate interest, through a credit on customer bills. |
96 | (4) When the nuclear or integrated gasification combined |
97 | cycle power plant is placed in commercial service, the utility |
98 | shall be allowed to increase its base rate charges by the |
99 | projected annual revenue requirements of the nuclear or |
100 | integrated gasification combined cycle power plant based on the |
101 | jurisdictional annual revenue requirements of the plant for the |
102 | first 12 months of operation. The rate of return on capital |
103 | investments shall be calculated using the utility's rate of |
104 | return last approved by the commission prior to the commercial |
105 | inservice date of the nuclear or integrated gasification |
106 | combined cycle power plant. If any existing generating plant is |
107 | retired as a result of operation of the nuclear or integrated |
108 | gasification combined cycle power plant, the commission shall |
109 | allow for the recovery, through an increase in base rate |
110 | charges, of the net book value of the retired plant over a |
111 | period not to exceed 5 years. |
112 | (5) The utility shall report to the commission annually |
113 | the budgeted and actual costs as compared to the estimated |
114 | inservice cost of the nuclear or integrated gasification |
115 | combined cycle power plant provided by the utility pursuant to |
116 | s. 403.519(4), until the commercial operation of the nuclear or |
117 | integrated gasification combined cycle power plant. The utility |
118 | shall provide such information on an annual basis following the |
119 | final order by the commission approving the determination of |
120 | need for the nuclear or integrated gasification combined cycle |
121 | power plant, with the understanding that some costs may be |
122 | higher than estimated and other costs may be lower. |
123 | (6) If the utility elects not to complete or is precluded |
124 | from completing construction of the nuclear power plant, |
125 | including new, expanded, or relocated electrical transmission |
126 | lines or facilities necessary thereto, or of the integrated |
127 | gasification combined cycle power plant, the commission shall |
128 | terminate the rates approved pursuant to this section with |
129 | respect to the abandoned project and order the utility to refund |
130 | to customers, as credits on customer bills, all amounts |
131 | recovered for the abandoned project. Credits shall be provided |
132 | in the same manner, at the same rate, and over the same period |
133 | of time in which the amounts were recovered. shall be allowed to |
134 | recover all prudent preconstruction and construction costs |
135 | incurred following the commission's issuance of a final order |
136 | granting a determination of need for the nuclear power plant and |
137 | electrical transmission lines and facilities necessary thereto |
138 | or for the integrated gasification combined cycle power plant. |
139 | The utility shall recover such costs through the capacity cost |
140 | recovery clause over a period equal to the period during which |
141 | the costs were incurred or 5 years, whichever is greater. The |
142 | unrecovered balance during the recovery period will accrue |
143 | interest at the utility's weighted average cost of capital as |
144 | reported in the commission's earnings surveillance reporting |
145 | requirement for the prior year. |
146 | Section 2. This act shall take effect July 1, 2009. |