1 | A bill to be entitled |
2 | An act relating to the Local Government Prompt Payment |
3 | Act; amending s. 218.72, F.S.; revising definitions; |
4 | amending s. 218.735, F.S.; revising provisions relating to |
5 | the timely payment for purchases of construction services; |
6 | requiring that a dispute be resolved according to |
7 | procedures in the contract; prohibiting the assessment of |
8 | damages against a contractor if the list of items |
9 | remaining to complete is not timely provided to the |
10 | contractor; amending s. 218.76, F.S.; revising provisions |
11 | relating to the resolution of disputes concerning an |
12 | improper payment request or invoice; providing that a |
13 | local governmental entity waives its objection in a |
14 | payment dispute if it fails to commence the dispute |
15 | resolution procedure within the time required; providing |
16 | an effective date. |
17 |
|
18 | Be It Enacted by the Legislature of the State of Florida: |
19 |
|
20 | Section 1. Section 218.72, Florida Statutes, is amended to |
21 | read: |
22 | 218.72 Definitions.-As used in this part, the term: |
23 | (1)(9) "Agent" means the project architect, project |
24 | engineer, or any other agency or person acting on behalf of the |
25 | local governmental entity. The agent who is required to review |
26 | invoices or payment requests must be identified in accordance |
27 | with s. 218.735(1). |
28 | (2)(7) "Construction services" means all labor, services, |
29 | and materials provided in connection with the construction, |
30 | alteration, repair, demolition, reconstruction, or any other |
31 | improvements to real property. |
32 | (3)(10) "Contractor" or "provider of construction |
33 | services" means the any person who contracts directly with a |
34 | local governmental entity to provide construction services. |
35 | (4)(3) "County" means a political subdivision of the state |
36 | established pursuant to s. 1, Art. VIII of the State |
37 | Constitution. |
38 | (5)(2) "Local governmental entity" means a county or |
39 | municipal government, school board, school district, authority, |
40 | special taxing district, other political subdivision, or any |
41 | office, board, bureau, commission, department, branch, division, |
42 | or institution thereof. |
43 | (6)(4) "Municipality" means a municipality created |
44 | pursuant to general or special law and metropolitan and |
45 | consolidated governments as provided in s. 6(e) and (f), Art. |
46 | VIII of the State Constitution. |
47 | (7)(8) "Payment request" means a request for payment for |
48 | construction services which conforms with all statutory |
49 | requirements and with all requirements specified by the local |
50 | governmental entity to which the payment request is submitted. |
51 | Such requirements must be included in the contract for the |
52 | project for which payment is requested. |
53 | (8)(1) "Proper invoice" means an invoice that which |
54 | conforms with all statutory requirements and with all |
55 | requirements that have been specified by the local governmental |
56 | entity to which the invoice is submitted. Such requirements must |
57 | be included in the contract for the project for which the |
58 | invoice is submitted. |
59 | (9)(5) "Purchase" means the purchase of goods, services, |
60 | or construction services; the purchase or lease of personal |
61 | property; or the lease of real property by a local governmental |
62 | entity. |
63 | (10)(6) "Vendor" means any person who sells goods or |
64 | services, sells or leases personal property, or leases real |
65 | property directly to a local governmental entity. The term |
66 | includes any person who provides waste hauling services to |
67 | residents or businesses located within the boundaries of a local |
68 | government pursuant to a contract or local ordinance. |
69 | Section 2. Subsections (1) through (7) of section 218.735, |
70 | Florida Statutes, are amended to read: |
71 | 218.735 Timely payment for purchases of construction |
72 | services.- |
73 | (1) The due date for payment for the purchase of |
74 | construction services by a local governmental entity is |
75 | determined as follows: |
76 | (a) If an agent must approve the payment request or |
77 | invoice before prior to the payment request or invoice is being |
78 | submitted to the local governmental entity, payment is due 25 |
79 | business days after the date on which the payment request or |
80 | invoice is stamped as received as provided in s. 218.74(1). The |
81 | contractor may send the local government an overdue notice. If |
82 | the payment request or invoice is not rejected within 4 business |
83 | days after delivery of the overdue notice, the payment request |
84 | or invoice shall be deemed accepted, except for any portion of |
85 | the payment request or invoice that is fraudulent or misleading. |
86 | (b) If an agent need not approve the payment request or |
87 | invoice which is submitted by the contractor, payment is due 20 |
88 | business days after the date on which the payment request or |
89 | invoice is stamped as received as provided in s. 218.74(1). |
90 |
|
91 | A local governmental entity shall identify the agent or employee |
92 | of the local governmental entity, or the facility or office, to |
93 | which the contractor may submit its payment request or invoice. |
94 | This requirement shall be included in the contract between the |
95 | local governmental entity and contractor, or shall be provided |
96 | by the local governmental entity through a separate written |
97 | notice, as required under the contract, no later than 10 days |
98 | after the contract award or notice to proceed. A contractor's |
99 | submission of a payment request or invoice to the identified |
100 | agent, employee, facility, or office of the local governmental |
101 | entity shall be stamped as received as provided in s. 218.74(1) |
102 | and shall commence the time periods for payment or rejection of |
103 | a payment request or invoice as provided in this subsection and |
104 | subsection (2). |
105 | (2) If a payment request or invoice does not meet the |
106 | contract requirements, the local governmental entity must may |
107 | reject the payment request or invoice within 20 business days |
108 | after the date on which the payment request or invoice is |
109 | stamped as received as provided in s. 218.74(1). The rejection |
110 | must be written and must specify the deficiency in the payment |
111 | request or invoice and the action necessary to make the payment |
112 | request or invoice proper. |
113 | (3) If a payment request or an invoice is rejected under |
114 | subsection (2) and the contractor submits a corrected payment |
115 | request or invoice that which corrects the deficiency specified |
116 | in writing by the local governmental entity, the corrected |
117 | payment request or invoice must be paid or rejected on the later |
118 | of: |
119 | (a) Ten business days after the date the corrected payment |
120 | request or invoice is stamped as received as provided in s. |
121 | 218.74(1); or |
122 | (b) If the local governmental entity governing body is |
123 | required by ordinance, charter, or other law to approve or |
124 | reject the corrected payment request or invoice, the first |
125 | business day after the next regularly scheduled meeting of the |
126 | local governmental entity governing body held after the |
127 | corrected payment request or invoice is stamped as received as |
128 | provided in s. 218.74(1). |
129 | (4) If a dispute between the local governmental entity and |
130 | the contractor cannot be resolved by the procedure in subsection |
131 | (3), the dispute must be resolved in accordance with the dispute |
132 | resolution procedure prescribed in the construction contract or |
133 | in any applicable ordinance, which shall be referenced in the |
134 | contract. In the absence of a prescribed procedure, the dispute |
135 | must be resolved by the procedure specified in s. 218.76(2). |
136 | (5) If a local governmental entity disputes a portion of a |
137 | payment request or an invoice, the undisputed portion shall be |
138 | paid timely, in accordance with subsection (1). |
139 | (6) If When a contractor receives payment from a local |
140 | governmental entity for labor, services, or materials furnished |
141 | by subcontractors and suppliers hired by the contractor, the |
142 | contractor must shall remit payment due to those subcontractors |
143 | and suppliers within 10 days after the contractor's receipt of |
144 | payment. If When a subcontractor receives payment from a |
145 | contractor for labor, services, or materials furnished by |
146 | subcontractors and suppliers hired by the subcontractor, the |
147 | subcontractor must shall remit payment due to those |
148 | subcontractors and suppliers within 7 days after the |
149 | subcontractor's receipt of payment. This subsection does not |
150 | Nothing herein shall prohibit a contractor or subcontractor from |
151 | disputing, pursuant to the terms of the relevant contract, all |
152 | or any portion of a payment alleged to be due to another party |
153 | if the contractor or subcontractor notifies the party whose |
154 | payment is disputed, in writing, of the amount in dispute and |
155 | the actions required to cure the dispute. The contractor or |
156 | subcontractor must pay all undisputed amounts due within the |
157 | time limits imposed by this section. |
158 | (7)(a) Each contract for construction services between a |
159 | local governmental entity and a contractor must provide for the |
160 | development of a single list of items required to render |
161 | complete, satisfactory, and acceptable the construction services |
162 | purchased by the local governmental entity. |
163 | (a) The contract must specify the process for developing |
164 | the development of the list, including the responsibilities of |
165 | the local governmental entity and the contractor in developing |
166 | and reviewing the list and a reasonable time for developing the |
167 | list, as follows: |
168 | 1. For construction projects having an estimated cost of |
169 | Less than $10 million, within 30 calendar days after reaching |
170 | substantial completion of the construction services purchased as |
171 | defined in the contract, or, if not defined in the contract, |
172 | upon reaching beneficial occupancy or use; or |
173 | 2. For construction projects having an estimated cost of |
174 | $10 million or more, within 30 calendar days, or, if unless |
175 | otherwise extended by contract, up to not to exceed 60 calendar |
176 | days, after reaching substantial completion of the construction |
177 | services purchased as defined in the contract, or, if not |
178 | defined in the contract, upon reaching beneficial occupancy or |
179 | use. |
180 |
|
181 | The contract must also specify a date for the delivery of the |
182 | list of items, not to exceed 5 days after the list of items has |
183 | been developed and reviewed in accordance with the time periods |
184 | set forth in subparagraphs 1. and 2. |
185 | (b) If the contract between the local governmental entity |
186 | and the contractor relates to the purchase of construction |
187 | services on more than one building or structure, or involves a |
188 | multiphased project, the contract must provide for the |
189 | development of a list of items required to render complete, |
190 | satisfactory, and acceptable all the construction services |
191 | purchased pursuant to the contract for each building, structure, |
192 | or phase of the project within the time limitations provided in |
193 | paragraph (a). |
194 | (c) The final contract completion date must be at least 30 |
195 | days after the delivery of the list of items. If the list is not |
196 | provided to the contractor by the agreed upon date for delivery |
197 | of the list, the contract time for completion must be extended |
198 | by the number of days the local governmental entity exceeded the |
199 | delivery date. Damages may not be assessed against a contractor |
200 | for failing to complete a project within the time required by |
201 | the contract, unless the contractor failed to complete the |
202 | project within the contract period as extended under this |
203 | paragraph. |
204 | (d)(c) The failure to include any corrective work or |
205 | pending items not yet completed on the list developed pursuant |
206 | to this subsection does not alter the responsibility of the |
207 | contractor to complete all the construction services purchased |
208 | pursuant to the contract. |
209 | (e)(d) Upon completion of all items on the list, the |
210 | contractor may submit a payment request for all remaining |
211 | retainage withheld by the local governmental entity pursuant to |
212 | this section. If a good faith dispute exists as to whether one |
213 | or more items identified on the list have been completed |
214 | pursuant to the contract, the local governmental entity may |
215 | continue to withhold up to an amount not to exceed 150 percent |
216 | of the total costs to complete such items. |
217 | (f)(e) All items that require correction under the |
218 | contract and that are identified after the preparation and |
219 | delivery of the list remain the obligation of the contractor as |
220 | defined by the contract. |
221 | (g)(f) Warranty items or items not included in the list of |
222 | items required under paragraph (a) may not affect the final |
223 | payment of retainage as provided in this section or as provided |
224 | in the contract between the contractor and its subcontractors |
225 | and suppliers. |
226 | (h)(g) Retainage may not be held by a local governmental |
227 | entity or a contractor to secure payment of insurance premiums |
228 | under a consolidated insurance program or series of insurance |
229 | policies issued to a local governmental entity or a contractor |
230 | for a project or group of projects, and the final payment of |
231 | retainage as provided in this section may not be delayed pending |
232 | a final audit by the local governmental entity's or contractor's |
233 | insurance provider. |
234 | (i)(h) If a local governmental entity fails to comply with |
235 | its responsibilities to develop the list required under |
236 | paragraph (a) or paragraph (b), as defined in the contract, |
237 | within the time limitations provided in paragraph (a), the |
238 | contractor may submit a payment request for all remaining |
239 | retainage withheld by the local governmental entity pursuant to |
240 | this section and payment of any remaining undisputed contract |
241 | amount, less any amount withheld pursuant to the contract for |
242 | incomplete or uncorrected work, must be paid within 20 business |
243 | days after receipt of a proper invoice or payment request. If |
244 | the local governmental entity has provided written notice to the |
245 | contractor specifying the failure of the contractor to meet |
246 | contract requirements in the development of the list of items to |
247 | be completed, the local governmental entity need not pay or |
248 | process any payment request for retainage if the contractor has, |
249 | in whole or in part, failed to cooperate with the local |
250 | governmental entity in the development of the list or failed to |
251 | perform its contractual responsibilities, if any, with regard to |
252 | the development of the list or if paragraph (8)(f) applies. |
253 | Section 3. Section 218.76, Florida Statutes, is amended to |
254 | read: |
255 | 218.76 Improper payment request or invoice; resolution of |
256 | disputes.- |
257 | (1) If In any case in which an improper payment request or |
258 | invoice is submitted by a vendor, the local governmental entity |
259 | shall, within 10 days after the improper payment request or |
260 | invoice is received by it, notify the vendor, in writing, that |
261 | the payment request or invoice is improper and indicate what |
262 | corrective action on the part of the vendor is needed to make |
263 | the payment request or invoice proper. |
264 | (2)(a) If In the event a dispute arises occurs between a |
265 | vendor and a local governmental entity concerning payment of a |
266 | payment request or an invoice, the dispute such disagreement |
267 | shall be finally determined by the local governmental entity |
268 | pursuant to as provided in this section. Each local governmental |
269 | entity shall establish a dispute resolution procedure |
270 | established to be followed by the local governmental entity in |
271 | cases of such disputes. Such procedure must shall provide that |
272 | proceedings to resolve the dispute are shall be commenced within |
273 | not later than 45 days after the date on which the payment |
274 | request or proper invoice was received by the local governmental |
275 | entity and shall be concluded by final decision of the local |
276 | governmental entity within not later than 60 days after the date |
277 | on which the payment request or proper invoice was received by |
278 | the local governmental entity. Such procedures are shall not be |
279 | subject to chapter 120, and do such procedures shall not |
280 | constitute an administrative proceeding that which prohibits a |
281 | court from deciding de novo any action arising out of the |
282 | dispute. If the dispute is resolved in favor of the local |
283 | governmental entity, then interest charges shall begin to accrue |
284 | 15 days after the local governmental entity's final decision. If |
285 | the dispute is resolved in favor of the vendor, then interest |
286 | begins shall begin to accrue as of the original date the payment |
287 | became due. |
288 | (b) If the local governmental entity does not commence the |
289 | dispute resolution procedure within the time required, a |
290 | contractor may give written notice to the local governmental |
291 | entity of the failure to timely commence its dispute resolution |
292 | procedure. If the local governmental entity fails to commence |
293 | the dispute resolution procedure within 4 business days after |
294 | such notice, any amounts resolved in the contractor's favor |
295 | shall bear mandatory interest, as set forth in s. 218.735(9), |
296 | from the date the payment request or invoice containing the |
297 | disputed amounts was submitted to the local governmental entity. |
298 | If the dispute resolution procedure is not commenced within 4 |
299 | business days after the notice, the objection to the payment |
300 | request or invoice shall be deemed waived. The waiver of an |
301 | objection pursuant to this paragraph does not relieve a |
302 | contractor of its contractual obligations. |
303 | (3) In an action to recover amounts due under this part |
304 | ss. 218.70-218.80, the court shall award court costs and |
305 | reasonable attorney's fees, including fees incurred through any |
306 | appeal, to the prevailing party, if the court finds that the |
307 | nonprevailing party withheld any portion of the payment that is |
308 | the subject of the action without any reasonable basis in law or |
309 | fact to dispute the prevailing party's claim to those amounts. |
310 | Section 4. This act shall take effect October 1, 2010. |