1 | A bill to be entitled |
2 | An act relating to mining and extraction activities; |
3 | amending s. 373.414, F.S.; providing that financial |
4 | responsibility for mitigation for wetlands and other |
5 | surface waters required by a permit for activities |
6 | associated with the extraction of limestone are subject to |
7 | approval by the Department of Environmental Protection as |
8 | part of permit application review; amending s. 378.901, |
9 | F.S.; authorizing mine operators proposing to mine or |
10 | extract limestone to apply for a life-of-the-mine permit; |
11 | authorizing operators of existing mines to apply for a |
12 | life-of-the-mine permit; clarifying the authority of local |
13 | governments to approve, approve with conditions, deny, or |
14 | impose certain permit durations; providing an effective |
15 | date. |
16 |
|
17 | Be It Enacted by the Legislature of the State of Florida: |
18 |
|
19 | Section 1. Paragraph (a) of subsection (19) of section |
20 | 373.414, Florida Statutes, is amended to read: |
21 | 373.414 Additional criteria for activities in surface |
22 | waters and wetlands.- |
23 | (19)(a) Financial responsibility for mitigation for |
24 | wetlands and other surface waters required by a permit issued |
25 | pursuant to this part for activities associated with the |
26 | extraction of limestone and phosphate are subject to approval by |
27 | the department as part of permit application review. Financial |
28 | responsibility for permitted activities which will occur over a |
29 | period of 3 years or less of mining operations must be provided |
30 | to the department prior to the commencement of mining operations |
31 | and shall be in an amount equal to 110 percent of the estimated |
32 | mitigation costs for wetlands and other surface waters affected |
33 | under the permit. For permitted activities which will occur over |
34 | a period of more than 3 years of mining operations, the initial |
35 | financial responsibility demonstration shall be in an amount |
36 | equal to 110 percent of the estimated mitigation costs for |
37 | wetlands and other surface waters affected in the first 3 years |
38 | of operation under the permit; and, for each year thereafter, |
39 | the financial responsibility demonstration shall be updated, |
40 | including to provide an amount equal to 110 percent of the |
41 | estimated mitigation costs for the next year of operations under |
42 | the permit for which financial responsibility has not already |
43 | been demonstrated and to release portions of the financial |
44 | responsibility mechanisms in accordance with applicable rules. |
45 | Section 2. Subsection (2) of section 378.901, Florida |
46 | Statutes, is amended to read: |
47 | 378.901 Life-of-the-mine permit.- |
48 | (2) As an alternative to, and in lieu of, separate |
49 | applications for permits required by part IV of chapter 373 and |
50 | part IV of this chapter, each operator who proposes to mine or |
51 | extract heavy minerals, limestone, or fuller's earth clay or the |
52 | operator of an existing mine may apply to the bureau for a life- |
53 | of-the-mine permit. Nothing in this subsection limits or |
54 | restricts the authority of a local government to approve, |
55 | approve with conditions, deny, or impose a permit duration |
56 | different from the duration of a permit issued pursuant to this |
57 | section. |
58 | Section 3. This act shall take effect upon becoming a law. |