CS for CS for SB 1472                            First Engrossed
       
       
       
       
       
       
       
       
       20131472e1
       
    1                        A bill to be entitled                      
    2         An act relating to nuclear and integrated gasification
    3         combined cycle power plants; amending s. 366.93, F.S.;
    4         modifying an alternative cost recovery mechanism for
    5         the recovery of costs for the siting, design,
    6         licensing, and construction of nuclear and integrated
    7         gasification combined cycle power plants; establishing
    8         a procedure and requirements for cost recovery based
    9         on preconstruction and construction phases; providing
   10         that the commission may not determine that a utility
   11         intends to complete construction of a power plant
   12         unless the utility proves its efforts by a
   13         preponderance of the evidence; providing that a
   14         utility that elects not to complete construction of a
   15         nuclear power plant may not recover or retain any rate
   16         of return for related costs; exempting certain actions
   17         taken before this act takes effect; providing an
   18         effective date.
   19  
   20  Be It Enacted by the Legislature of the State of Florida:
   21  
   22         Section 1. Subsections (1), (2), (3), and (6) of section
   23  366.93, Florida Statutes, are amended to read:
   24         366.93 Cost recovery for the siting, design, licensing, and
   25  construction of nuclear and integrated gasification combined
   26  cycle power plants.—
   27         (1) As used in this section, the term:
   28         (a) “Cost” includes, but is not limited to, all capital
   29  investments, including rate of return, any applicable taxes, and
   30  all expenses, including operation and maintenance expenses,
   31  related to or resulting from the siting, licensing, design,
   32  construction, or operation of the nuclear power plant, including
   33  new, expanded, or relocated electrical transmission lines or
   34  facilities of any size which that are necessary thereto, or of
   35  the integrated gasification combined cycle power plant.
   36         (b) “Electric utility” or “utility” has the same meaning as
   37  that provided in s. 366.8255(1)(a).
   38         (c) “Integrated gasification combined cycle power plant” or
   39  “plant” means an electrical power plant as defined in s.
   40  403.503(14) which that uses synthesis gas produced by integrated
   41  gasification technology.
   42         (d) “Nuclear power plant” or “plant” means an electrical
   43  power plant as defined in s. 403.503(14) which that uses nuclear
   44  materials for fuel.
   45         (e) “Power plant” or “plant” means a nuclear power plant or
   46  an integrated gasification combined cycle power plant.
   47         (f) “Preconstruction” is that period of time after a site,
   48  including any related electrical transmission lines or
   49  facilities, has been selected through and including the date the
   50  utility completes site clearing work. Preconstruction costs must
   51  shall be afforded deferred accounting treatment and shall accrue
   52  a carrying charge equal to the utility’s allowance for funds
   53  during construction (AFUDC) rate until recovered in rates.
   54         (2) Within 6 months after the enactment of this act, the
   55  commission shall establish, by rule, alternative cost recovery
   56  mechanisms for the recovery of costs incurred in the siting,
   57  design, licensing, and construction of a nuclear power plant,
   58  including new, expanded, or relocated electrical transmission
   59  lines and facilities that are necessary thereto, or of an
   60  integrated gasification combined cycle power plant. Such
   61  mechanisms must shall be designed to promote utility investment
   62  in nuclear or integrated gasification combined cycle power
   63  plants and allow for the recovery in rates of all prudently
   64  incurred costs, including and shall include, but not be limited
   65  to:
   66         (a) Recovery through the capacity cost recovery clause of
   67  any preconstruction costs.
   68         (b) Recovery through an incremental increase in the
   69  utility’s capacity cost recovery clause rates of the carrying
   70  costs on the utility’s projected construction cost balance
   71  associated with the nuclear or integrated gasification combined
   72  cycle power plant. To encourage investment and provide
   73  certainty, for nuclear or integrated gasification combined cycle
   74  power plant need petitions submitted on or before December 31,
   75  2010, associated carrying costs must shall be equal to the most
   76  recently approved pretax AFUDC at the time an increment of cost
   77  recovery is sought in effect upon this act becoming law. For
   78  nuclear or integrated gasification combined cycle power plants
   79  for which need petitions are submitted after December 31, 2010,
   80  the utility’s existing pretax AFUDC rate is presumed to be
   81  appropriate unless determined otherwise by the commission in the
   82  determination of need for the nuclear or integrated gasification
   83  combined cycle power plant.
   84         (3)(a) After a petition for determination of need is
   85  granted, a utility may petition the commission for cost recovery
   86  as permitted by this section and commission rules.
   87         (b)During the time that a utility seeks to obtain a
   88  combined license from the Nuclear Regulatory Commission for a
   89  nuclear power plant or a certification for an integrated
   90  gasification combined cycle power plant, the utility may recover
   91  only costs related to, or necessary for, obtaining such
   92  licensing or certification.
   93         (c) After a utility obtains a license or certification, it
   94  must petition the commission for approval before proceeding with
   95  preconstruction work beyond those activities necessary to obtain
   96  or maintain a license or certificate.
   97         1. The only costs that a utility that has obtained a
   98  license or certification may recover before obtaining commission
   99  approval are those that are previously approved or necessary to
  100  maintain the license or certification.
  101         2. In order for the commission to approve preconstruction
  102  work on a plant, it must determine that:
  103         a. The plant remains feasible; and
  104         b. The projected costs for the plant are reasonable.
  105         (d) After a utility obtains approval to proceed with
  106  postlicensure or postcertification preconstruction work, it must
  107  petition the commission for approval of any preconstruction
  108  materials or equipment purchases that exceed 1 percent of the
  109  total projected cost for the project. Such petition shall be
  110  reviewed and completed in the annual Nuclear Cost Recovery
  111  Clause proceeding in which it is filed or in a separate
  112  proceeding by the utility.
  113         (e) A utility must petition the commission for approval
  114  before beginning the construction phase.
  115         1. The only costs that a utility that has obtained
  116  commission approval may recover before beginning construction
  117  work are those that are previously approved or necessary to
  118  maintain the license or certification.
  119         2. In order for the commission to approve proceeding with
  120  construction on a plant, it must determine that:
  121         a. The plant remains feasible; and
  122         b. The projected costs for the plant are reasonable.
  123         (f)1. If a utility has not begun construction of a plant
  124  within:
  125         a. Ten years after the date on which the utility obtains a
  126  combined license from the Nuclear Regulatory Commission for a
  127  nuclear power plant or a certification for an integrated
  128  gasification combined cycle power plant, the utility must
  129  petition the commission to preserve the opportunity for future
  130  recovery under this section for costs relating to that plant.
  131  The commission must determine whether the utility remains intent
  132  on building the plant.
  133         (I) If the commission finds that the utility remains intent
  134  on building the plant, the utility may continue to recover costs
  135  under this section.
  136         (II) If the commission finds a lack of such intent, it may
  137  enter an order prohibiting recovery of any future costs relating
  138  to the plant under this section.
  139         b. Twenty years after the date on which the utility obtains
  140  a combined license from the Nuclear Regulatory Commission for a
  141  nuclear power plant or a certification for an integrated
  142  gasification combined cycle power plant, the utility may not,
  143  under this section, recover future costs relating to that plant.
  144         2. Consistent with subsection (4), nothing in this section
  145  shall preclude a utility from recovering the full revenue
  146  requirements of the nuclear power plant or integrated
  147  gasification combined cycle power plant in base rates upon the
  148  commercial in-service date.
  149         3. Beginning January 1, 2014, in making its determination
  150  for any cost recovery under this paragraph, the commission may
  151  find that a utility intends to construct a nuclear or integrated
  152  gasification combined cycle power plant only if the utility
  153  proves by a preponderance of the evidence that it has committed
  154  sufficient, meaningful, and available resources to enable the
  155  project to be completed and that its intent is realistic and
  156  practical.
  157         (6) If the utility does elects not to complete or is
  158  precluded from completing construction of the nuclear power
  159  plant, including new, expanded, or relocated electrical
  160  transmission lines or facilities necessary thereto, or of the
  161  integrated gasification combined cycle power plant, the utility
  162  shall be allowed to recover all prudent preconstruction and
  163  construction costs incurred following the commission’s issuance
  164  of a final order granting a determination of need for the
  165  nuclear power plant and electrical transmission lines and
  166  facilities necessary thereto or for the integrated gasification
  167  combined cycle power plant. The utility shall recover such costs
  168  through the capacity cost recovery clause over a period equal to
  169  the period during which the costs were incurred or 5 years,
  170  whichever is greater. The unrecovered balance during the
  171  recovery period will accrue interest at the utility’s weighted
  172  average cost of capital as reported in the commission’s earnings
  173  surveillance reporting requirement for the prior year. However,
  174  if the utility elects not to complete construction of the
  175  nuclear power plant, rather than being precluded from completing
  176  such construction, the utility may not recover or retain any
  177  rate of return under this section. Any cost recovery after the
  178  date of the decision not to complete construction of the plant
  179  may not include a rate of return. A utility that elects not to
  180  complete construction shall refund to its customers the costs
  181  recovered before the date of the decision which are attributable
  182  to a recovery of a rate of return.
  183         Section 2. This act does not apply to costs incurred, or
  184  contracts or settlement agreements entered into, before July 1,
  185  2013. It also does not apply if, on or before that date, the
  186  Public Service Commission receives written notice that a utility
  187  has elected not to complete construction of a power plant.
  188         Section 3. This act shall take effect July 1, 2013.