Florida Senate - 2023                        COMMITTEE AMENDMENT
       Bill No. SB 346
       
       
       
       
       
       
                                Ì524380ÉÎ524380                         
       
                              LEGISLATIVE ACTION                        
                    Senate             .             House              
                  Comm: RCS            .                                
                  03/17/2023           .                                
                                       .                                
                                       .                                
                                       .                                
       —————————————————————————————————————————————————————————————————




       —————————————————————————————————————————————————————————————————
       The Committee on Community Affairs (DiCeglie) recommended the
       following:
       
    1         Senate Amendment (with title amendment)
    2  
    3         Delete lines 48 - 272
    4  and insert:
    5         Section 1. Subsection (7) and paragraph (c) of subsection
    6  (8) of section 218.735, Florida Statutes, are amended to read:
    7         218.735 Timely payment for purchases of construction
    8  services.—
    9         (7) Each contract for construction services between a local
   10  governmental entity and a contractor must provide for the
   11  development of a single list of items required to render
   12  complete, satisfactory, and acceptable the construction services
   13  purchased by the local governmental entity, which must include a
   14  dollar valuation, as reasonably determined by the contractor as
   15  a portion of the contract value, of the estimated cost to
   16  complete each item on the list.
   17         (a) The contract must specify the process for developing
   18  the list, including the responsibilities of the local
   19  governmental entity and the contractor in developing and
   20  reviewing the list and a reasonable time for developing the
   21  list:
   22         1. For construction projects having an estimated cost of
   23  less than $10 million, within 30 calendar days after reaching
   24  substantial completion of the construction services purchased as
   25  defined in the contract, or, if not defined in the contract,
   26  upon reaching beneficial occupancy or use; or
   27         2. For construction projects having an estimated cost of
   28  $10 million or more, within 30 calendar days, or, if extended by
   29  contract, up to 60 calendar days after reaching substantial
   30  completion of the construction services purchased as defined in
   31  the contract, or, if not defined in the contract, upon reaching
   32  beneficial occupancy or use.
   33  
   34  The contract must also specify a date for the delivery of the
   35  list of items, not to exceed 5 days after the list of items has
   36  been developed and reviewed in accordance with the time periods
   37  set forth in subparagraphs 1. and 2.
   38         (b) If the contract between the local governmental entity
   39  and the contractor relates to the purchase of construction
   40  services on more than one building or structure, or involves a
   41  multiphased project, the contract must provide for the
   42  development of a list of items required to render complete,
   43  satisfactory, and acceptable all the construction services
   44  purchased pursuant to the contract for each building, structure,
   45  or phase of the project within the time limitations provided in
   46  paragraph (a).
   47         (c) The final contract completion date must be at least 30
   48  days after the delivery of the list of items. If the list is not
   49  provided to the contractor by the agreed upon date for delivery
   50  of the list, the contract time for completion must be extended
   51  by the number of days the local governmental entity exceeded the
   52  delivery date. Damages may not be assessed against a contractor
   53  for failing to complete a project within the time required by
   54  the contract, unless the contractor failed to complete the
   55  project within the contract period as extended under this
   56  paragraph.
   57         (d) The failure to include any corrective work or pending
   58  items not yet completed on the list does not alter the
   59  responsibility of the contractor to complete all the
   60  construction services purchased pursuant to the contract.
   61         (e) Within 20 days after the date the list is created, the
   62  local governmental entity must pay the contractor the remaining
   63  contract balance that includes all retainage previously withheld
   64  by the local governmental entity. The remaining contract balance
   65  does not include the estimated costs to complete the items
   66  included on the list.
   67         (f) Upon completion of all items on the list, the
   68  contractor may submit a payment request for all remaining
   69  contract sums retainage withheld by the local governmental
   70  entity pursuant to this section. If a good faith dispute exists
   71  as to whether one or more items identified on the list have been
   72  completed pursuant to the contract, the local governmental
   73  entity may continue to withhold up to 150 percent of the total
   74  costs to complete such items.
   75         (g)(f) All items that require correction under the contract
   76  which and that are identified after the preparation and delivery
   77  of the list remain the obligation of the contractor as defined
   78  by the contract.
   79         (h)(g) Warranty items or items not included in the list of
   80  items required under paragraph (a) may not affect the final
   81  payment of retainage as provided in paragraph (e) this section
   82  or as provided in the contract between the contractor and its
   83  subcontractors and suppliers.
   84         (i)(h) Retainage may not be held by a local governmental
   85  entity or a contractor to secure payment of insurance premiums
   86  under a consolidated insurance program or series of insurance
   87  policies issued to a local governmental entity or a contractor
   88  for a project or group of projects, and the final payment of
   89  retainage as provided in paragraph (e) this section may not be
   90  delayed pending a final audit by the local governmental entity’s
   91  or contractor’s insurance provider.
   92         (j)(i) If a local governmental entity fails to comply with
   93  its responsibilities to develop the list required under
   94  paragraph (a) or paragraph (b) within the time limitations
   95  provided in paragraph (a), the contractor may submit a payment
   96  request for all remaining unpaid contract sums, including
   97  retainage withheld by the local governmental entity, and the
   98  local governmental entity must pay the contractor all remaining
   99  contract sums pursuant to this section; and payment of any
  100  remaining undisputed contract amount, less any amount withheld
  101  pursuant to the contract for incomplete or uncorrected work,
  102  must be paid within 20 business days after receipt of a proper
  103  invoice or payment request. If the local governmental entity has
  104  provided written notice to the contractor specifying the failure
  105  of the contractor to meet contract requirements in the
  106  development of the list of items to be completed, the local
  107  governmental entity must pay the contractor the remaining
  108  contract balance that includes retainage previously withheld by
  109  the local governmental entity. The remaining contract balance
  110  does not include 150 percent of the estimated costs to complete
  111  the items that the local governmental entity has included on its
  112  version of the list need not pay or process any payment request
  113  for retainage if the contractor has, in whole or in part, failed
  114  to cooperate with the local governmental entity in the
  115  development of the list or to perform its contractual
  116  responsibilities, if any, with regard to the development of the
  117  list or if paragraph (8)(c) applies.
  118         (8)
  119         (c) This section does not require the local governmental
  120  entity to pay or release any amounts that are the subject of a
  121  good faith dispute or, the subject of a claim brought pursuant
  122  to s. 255.05, or otherwise the subject of a claim or demand by
  123  the local governmental entity or contractor.
  124         Section 2. Paragraph (a) of subsection (2) of section
  125  218.76, Florida Statutes, is amended to read:
  126         218.76 Improper payment request or invoice; resolution of
  127  disputes.—
  128         (2)(a) If a dispute arises between a vendor and a local
  129  governmental entity concerning payment of a payment request or
  130  an invoice, the dispute must shall be finally determined by the
  131  local governmental entity pursuant to a dispute resolution
  132  procedure established by the local governmental entity. Such
  133  procedure must provide that proceedings to resolve the dispute
  134  commence are commenced within 30 45 days after the date the
  135  payment request or proper invoice was received by the local
  136  governmental entity and conclude concluded by final decision of
  137  the local governmental entity within 45 60 days after the date
  138  the payment request or proper invoice was received by the local
  139  governmental entity. Such procedures are not subject to chapter
  140  120 and do not constitute an administrative proceeding that
  141  prohibits a court from deciding de novo any action arising out
  142  of the dispute. If the dispute is resolved in favor of the local
  143  governmental entity, interest charges begin to accrue 15 days
  144  after the local governmental entity’s final decision. If the
  145  dispute is resolved in favor of the vendor, interest begins to
  146  accrue as of the original date the payment became due.
  147         Section 3. Subsection (2) of section 255.073, Florida
  148  Statutes, is amended to read:
  149         255.073 Timely payment for purchases of construction
  150  services.—
  151         (2) If a public entity disputes a portion of a payment
  152  request, the undisputed portion must be timely paid within the
  153  time required under the contract or within 20 days, whichever is
  154  earlier.
  155         Section 4. Subsection (3) of section 255.074, Florida
  156  Statutes, is amended to read:
  157         255.074 Procedures for calculation of payment due dates.—
  158         (3) A public entity must submit a payment request to the
  159  Chief Financial Officer for payment no later more than 14 20
  160  days after receipt of the payment request.
  161         Section 5. Present subsections (4) through (8) of section
  162  255.077, Florida Statutes, are redesignated as subsections (5)
  163  through (9), respectively, a new subsection (4) is added to that
  164  section, and subsection (1) and present subsection (8) of that
  165  section are amended, to read:
  166         255.077 Project closeout and payment of retainage.—
  167         (1) Each contract for construction services between a
  168  public entity and a contractor must provide for the development
  169  of a list of items required to render complete, satisfactory,
  170  and acceptable the construction services purchased by the public
  171  entity. The list must include a dollar valuation, as reasonably
  172  determined by the contractor as a portion of the contract value,
  173  of the estimated cost to complete the items included on the
  174  list. The contract must specify the process for the development
  175  of the list, including responsibilities of the public entity and
  176  the contractor in developing and reviewing the list and a
  177  reasonable time for developing the list, as follows:
  178         (a) For construction projects having an estimated cost of
  179  less than $10 million, within 30 calendar days after reaching
  180  substantial completion of the construction services purchased as
  181  defined in the contract, or, if not defined in the contract,
  182  upon reaching beneficial occupancy or use; or
  183         (b) For construction projects having an estimated cost of
  184  $10 million or more, within 30 calendar days, unless otherwise
  185  extended by contract not to exceed 60 calendar days, after
  186  reaching substantial completion of the construction services
  187  purchased as defined in the contract, or, if not defined in the
  188  contract, upon reaching beneficial occupancy or use.
  189         (4) Within 20 days after the date the list is created, the
  190  public entity must pay the contractor the remaining contract
  191  balance that includes all retainage previously withheld by the
  192  public entity. The remaining contract balance does not include
  193  the costs to complete the items included on the list.
  194         (9)(8) If a public entity fails to comply with its
  195  responsibilities to develop the list required under subsection
  196  (1) or subsection (2), as defined in the contract, within the
  197  time limitations provided in subsection (1), the contractor may
  198  submit a payment request for all remaining retainage withheld by
  199  the public entity pursuant to s. 255.078 and the public entity
  200  must pay the contractor all remaining retainage previously
  201  withheld within 20 days after receipt of the payment request.
  202  The public entity is not required to need not pay or process any
  203  payment request for retainage if the contractor has, in whole or
  204  in part, failed to cooperate with the public entity in the
  205  development of the list or failed to perform its contractual
  206  responsibilities, if any, with regard to the development of the
  207  list or if s. 255.078(3) applies.
  208         Section 6. Subsection (3) of section 255.078, Florida
  209  Statutes, is amended to read:
  210         255.078 Public construction retainage.—
  211         (3) This section and s. 255.077 do not require the public
  212  entity to pay or release any amounts that are the subject of a
  213  good faith dispute or, the subject of a claim brought pursuant
  214  to s. 255.05, or otherwise the subject of a claim or demand by
  215  the public entity or contractor.
  216         Section 7. Paragraph (b) of subsection (1) of section
  217  255.0992, Florida Statutes, is amended to read:
  218         255.0992 Public works projects; prohibited governmental
  219  actions.—
  220         (1) As used in this section, the term:
  221         (b) “Public works project” means an activity exceeding
  222  $350,000 $1 million in value that is paid for with any local or
  223  state-
  224  
  225  ================= T I T L E  A M E N D M E N T ================
  226  And the title is amended as follows:
  227         Delete lines 3 - 35
  228  and insert:
  229         218.735, F.S.; requiring that a certain list include a
  230         dollar valuation, as reasonably determined by the
  231         contractor as a portion of the contract value, of the
  232         estimated cost to complete each item on the list;
  233         deleting a provision authorizing an extension by
  234         contract for construction projects of less than $10
  235         million; requiring a local governmental entity to pay
  236         a contractor the remaining contract balance within a
  237         specified timeframe; revising the conditions that
  238         would require a local governmental entity to pay
  239         unpaid contract sums to a contractor if a specified
  240         list is not developed; requiring a local governmental
  241         entity to pay the remaining contract balance if the
  242         local governmental entity provided a certain written
  243         notice to the contractor; revising the conditions that
  244         require a local governmental entity to pay or release
  245         amounts subject to certain disputes or claims;
  246         amending s. 218.76, F.S.; revising the timeframe
  247         within which proceedings must commence to resolve
  248         disputes between vendors and local governmental
  249         entities; revising the timeframe for such proceedings
  250         to conclude; amending s. 255.073, F.S.; requiring that
  251         undisputed portions of payment requests be paid within
  252         a specified timeframe; amending s. 255.074, F.S.;
  253         revising the timeframe for a public entity to submit a
  254         payment request to the Chief Financial Officer;
  255         amending s. 255.077, F.S.; requiring that a certain
  256         list include a dollar valuation, as determined by the
  257         contractor as a portion of the contract value, to
  258         complete each item on the list; requiring the public