Senate Committee Publications
|
|
|
|
|
|
|
|
|
|
Community Budget Issue Requests - Tracking Id #1287FY0102 |
|||||||||
Improvements to CR 466A |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
William Neron, County Manager |
Organization: |
Lake County Board of Commissioners |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Improvements to CR 466A |
Date Submitted: |
1/18/2002 2:51:29 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Anna Cowin |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
Project will provide an alternate route that will include public transportation, ITS technology, and will also enhance evacuation routes in and out of the Central Florida Region.� Population growth has necessitated this expansion.� The two extra lanes will enhance economic development state-wide by providing an increased ability to move goods and services through the region. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Lake County Board of Commissioners |
|
Contact: |
Noble Olasimbo, AICP |
|
||||
|
315 West Main Street |
|
Contact Phone: |
(352) 253-4983 |
|
||||
|
|
Tavares 32778 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Lake |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Improvement will provide an alternative parallel (east-west) corridor to CR 466 in both Lake and Sumter Counties.� The two extra lanes will provide the necessary additional capacity to relieve traffic congestion as well as provide interconnection to US 27/441. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
Project will encourage, enhance, and create economic benefits in terms of the movement of goods and services on US 27/441.� The project will also enhance evacuation routes in and out of the Central Florida Region.� The project will provide an alternate route that will include public transportation and district-wide ITS Technology implementation. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$300,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$375,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
Cash Amount: |
$75,000 |
In-Kind Amount: |
$75,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Yes |
|
||||||
|
Amount: |
$5,950,000 |
|
|
|
|
|
||
|
Purpose for future year funding: |
|
Non-recurring Construction |
|
|||||
|
Will this be an annual request? |
|
|
No |
|
|
|||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Unknown |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Lake County Board of Commissioners |
|||||||
|
Meeting Date: |
8/28/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|