Senate Committee Publications
|
|
|
|
|
|
|
|
|
|
Community Budget Issue Requests - Tracking Id #305FY0102 |
|||||||||
Leon County:� Capital Circle NW/SW Airport to U.S. 90 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Colleen Roland |
Organization: |
Leon County Board of County Commissioners |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Leon County:� Capital Circle NW/SW Airport to U.S. 90 |
Date Submitted: |
1/17/2002 10:08:54 AM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Alfred Lawson, Richard Mitchell |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
The Long Range Transportation Plan to Tallahassee and Leon County indicates that this roadway needs to be widened to a four-lane facility.� This will provide a much-needed intermodal connection between the Tallahassee Regional Airport and Interstate 10, a major interstate highway connecting the west coast and east coast of the United States. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Leon County |
|
Contact: |
Colleen Roland |
|
||||
|
301 S. Monroe St. |
|
Contact Phone: |
(850) 891-8623 |
|
||||
|
|
Tallahassee 32301 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Leon |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Capital Circle, Northwest/Southwest is a regionally significant roadway from U.S 90 (Tennessee Street) to I-10 is currently under design with funding committed for right-of-way acquistion.� The remainder of this roadway form the Tallahassee Regional Airport to Tennessee Street is five miles long and is currently a two-lane road.� The project is estimated to cost apporoximateely thirty million dollars.� The cost breakdown for the various phases of this project is as followes: Project Development and Environment Study��� $2,500,000 Design��� $2,500,000 Right-of-Way Acquisition and Construction��� $25,000,000 |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
The improvement of this section would compliment the other phases of this project.� It is believed that once complete, the enhanced transportation along with scheduled airport improvements will create freight related opportunites, creating new jobs.� This improvement will also stimulate the creation of new jobs at Innovation Park, a high tech business park located west of the airport. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$30,000,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$62,000,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
Cash Amount: |
$32,800,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
Tallahassee/Leon County Comprehensive Plan, Long Range Transportation Plan and Blueprint 2000 |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Leon County Board of County Commissioners |
|||||||
|
Meeting Date: |
9/18/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|