Community Budget Issue Requests - Tracking Id #713FY0102 |
|||||||||
Widening West SR 50 from FL Turnpike to Pine Hills Rd |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Richard T Crotty |
Organization: |
Orange County Government |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Widening West SR 50 from FL Turnpike to Pine Hills Rd |
Date Submitted: |
1/15/2002 6:41:51 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Daniel Webster |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
The segment of West SR 50 from Florida's Turnpike interchnage (east of the Lake county line) to CR 431 (Pine Hills Road) serves as one of the major east-west corridors in Central Florida. This 12.8 mile segment of SR 50 is classified as a four-lane divided principal arterial and is located in west Orange County. SR 50 serves local trips as well as trips with destinations outside of Orange County. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Orange County Government |
|
Contact: |
Renzo Nastasi |
|
||||
|
201 S. Rosalind Avenue |
|
Contact Phone: |
(407) 836-8072 |
|
||||
|
|
Orlando 32801 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Orange |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Project length is 12. 8 miles. Widening from 4-6 lanes. Orange County & FDOT have entered into a Joint Participation Agreement for this project. Aditionally the project will analyze the realignment of Beulah Road, near the Western Beltway. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
By providing increased capacity to west SR 50, additional development will be able to occur fostering economic growth for the cities of Oakland, Winter Garden, and Ocoee. In addition, improvements will create better access to the villages of Horizon West development for residents from downtown Orlando. |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$2,100,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$30,000,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
Cash Amount: |
$2,300,000 |
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
Yes |
|
||||||
|
Fiscal Year: |
20002001 |
Amount: |
$2,100,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
Yes |
|
||||||
|
Amount: |
$2,300,000 |
|
|
|
|
|
||
|
Purpose for future year funding: |
|
Non-recurring Construction |
|
|||||
|
Will this be an annual request? |
|
|
No |
|
|
|||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
Yes |
|
||||||
|
Agency: |
Transportation, Department Of |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
Yes |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
SR 50 is a fast growing corridor and the existing four lanes are not sufficient to handle the tarffi |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
Yes |
|
|||||||
|
Hearing Body: |
Transportation Outreach Program Advisory Group |
|||||||
|
Meeting Date: |
10/11/2001 |
|||||||
|
|
|
|
|
|
|
|
|
|