Community Budget Issue Requests - Tracking Id #910FY0102

Ezell Water Line Extension/City of Graceville

 

 

 

 

 

 

 

 

 

 

Requester:

Eugene Adams

Organization:

City of Graceville

 

 

 

 

 

 

 

 

 

 

Project Title:

Ezell Water Line Extension/City of Graceville

Date Submitted:

1/17/2002 12:11:17 PM

 

 

 

 

 

 

 

 

 

 

Sponsors:

Alfred Lawson

 

 

 

 

 

 

 

 

 

 

Statewide Interest:

 

 

 

 

 

 

 

The City of Graceville growth issues as it relates water needs

 

 

 

 

 

 

 

 

 

 

Recipient:

City of Graceville

 

Contact:

Eugene Adams

 

 

5348 Cliff Street

 

Contact Phone:

(850) 263-3691

 

 

 

Graceville 32440

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Counties:

Jackson

 

 

 

 

 

 

 

 

 

 

Gov't Entity:

Yes

Private Organization (Profit/Not for Profit):

 

 

 

 

 

 

 

 

 

 

 

 

Project Description:

 

 

 

 

 

 

 

The city of Graceville proposes the establishment of a waterline from an existing pump located at the Graceville Work Camp site.Establishment of this line will enable the City of Graceville to maintain an acceptable fire suppression capability.Due to a previous consent order, the City of Graceville carried out waterline improvement project in order to bring fire suppression up to acceptable standards.These improvements were carried out at the City's expense.Due to economic growth and proposed projects within the city, itis projected that an estimated 32 residences will be established within the next 6 months with more extensive growth projected over the next 1-5 years.The current water system as configured will simply not support the considerable consumption that these residences will require and maintain adequate fire suppression capabilities at the Jackson Convalescence Center and the Campbellton/Graceville Hospital

 

 

 

 

 

 

 

 

 

 

Measurable Outcome Anticipated:

 

 

 

 

 

Establishment of the proposed water supply line would eliminate the pressure placed on the pump and waterlines currently being used by the City residents. Establishment will also enable the City to maintain current mandated fire suppression capabilities at the Campbellton/Graceville Hospital and Convalescence Center.

 

 

 

 

 

 

 

 

 

 

Amount requested from the State for this project this year:

$225,000

 

 

 

 

 

 

 

 

 

 

Total cost of the project:

$225,000

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Request has been made to fund:

Construction

 

 

 

 

 

 

 

 

 

 

 

 

 

What type of match exists for this project?

None

 

 

 

 

 

 

 

 

 

 

 

Was this project previously funded by the State?

 

No

 

 

 

 

 

 

 

 

 

 

 

Is future-year funding likely to be requested?

 

No

 

 

 

 

 

 

 

 

 

 

 

Was this project included in an Agency's Budget Request?

 

No

 

 

 

 

 

 

 

 

 

 

 

Was this project included in the Governor's Recommended Budget?

No

 

 

 

 

 

 

 

 

 

 

 

Is there a documented need for this project?

 

Yes

 

 

Documentation:

Fire Marshall Mandate/Consent Order

 

 

 

 

 

 

 

 

 

 

Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?

No