PMCC Unit 4 Stormwater Improvements | |||||||||
Requester: | City of Palm Bay | Organization: | City of Palm Bay | ||||||
Project Title: | PMCC Unit 4 Stormwater Improvements | Date Submitted | 1/14/2003 2:17:23 PM | ||||||
Sponsors: | Futch | ||||||||
Statewide Interest: | |||||||||
This project will provide treatment for stormwater runoff which currently impacts Turkey Creek, a 303 (d) protected waterbed. | |||||||||
Recipient: | City of Palm Bay | Contact: | Bill Barrett | ||||||
120 Malabar Road SE | Contact Phone: | (321) 403-6410 | |||||||
Palm Bay 32907 | |||||||||
Counties: | Brevard | ||||||||
Gov't Entity: | Yes | Private Organization (Profit/Not for Profit): | |||||||
Project Description: | |||||||||
Upgrade of existing system to provide for treatment of stormwater runoff. | |||||||||
Is this a water project as described in Chapter 2002-291, Laws of Florida? | Yes | ||||||||
Has the project been submitted to the Department of Environmental Protection? | Yes | ||||||||
DEP Identfying Number: | SW20022029 | ||||||||
Measurable Outcome Anticipated: | |||||||||
Replacement of box culverts, widening and deepening of drainage channel to provide additional storage and treatment. | |||||||||
Amount requested from the State for this project this year: | $275,000 | ||||||||
Total cost of the project: | $325,000 | ||||||||
Request has been made to fund: | Construction | ||||||||
What type of match exists for this project? | Local | ||||||||
Cash Amount | $ | In-kind Amount | $50,000 | ||||||
Was this project previously funded by the state? | Yes | Fiscal Year: | 2000-2001 | Amount: | $99,500 | ||||
Is future-year funding likely to be requested? | No | ||||||||
Was this project included in an Agency's Budget Request? | Unknown | ||||||||
Was this project included in the Governor's Recommended Budget? | Unknown | ||||||||
Is there a documented need for this project? | Yes | ||||||||
Documentation: | SWIM Plan | ||||||||
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? | Yes | ||||||||
Hearing Body: | Brevard Legislative Delegation meeting | ||||||||
Hearing Meeting Date: | 12/04/2002 |