Skip to Navigation | Skip to Main Content | Skip to Site Map

MyFloridaHouse.gov | Mobile Site

Senate Tracker: Sign Up | Login

The Florida Senate

Senate Committee Publications

CBIRS Request 876
 
Community Budget Issue Requests - Tracking Id #876
Hartwood Marsh Road Improvement Phase 2 from two lanes to four lanes
 
Requester: Welton G. Cadwell, Chairman Organization: Lake County Board of County Commissioners
 
Project Title: Hartwood Marsh Road Improvement Phase 2 from two lanes to four lanes Date Submitted 1/13/2003 11:13:39 AM
 
Sponsors: Cowin
 
Statewide Interest:
This project will encourage, enhance and create economic benefits in terms of the movement of goods and services on SR 50 and US 27. The project will enhance evacuation routes in and out of the Central Florida Region. Will relieve congestion before and after the six-lane improvement is completed on SR 50. The project will provide and alternate route that will include public transportation.
 
Recipient: Lake County Board of County Commissioners   Contact: Noble Olasimbo  
  315 W. Main Street   Contact Phone: (352) 253-4983  
  Tavares 32778
 
Counties: Lake
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
This improvement calls for adding two lanes as well as rehabilitation the two existing lanes. Will provide an alternative parallel (east-west) corridor to SR 50 in both Lake and Orange Counties.
 
Is this a water project as described in Chapter 2002-291, Laws of Florida? No
 
Measurable Outcome Anticipated:
Fixed Capitol Outlay Economic Development Transportation Project
 
Amount requested from the State for this project this year: $2,567,500
 
Total cost of the project: $5,135,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local
  Cash Amount $267,500  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   Unknown
 
Was this project included in an Agency's Budget Request?   Unknown
 
Was this project included in the Governor's Recommended Budget? Unknown
 
Is there a documented need for this project? Yes
  Documentation: 2020 Long Term Transportation Plan
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: Lake County Legislative Delegation
  Hearing Meeting Date: 12/04/2002