| Community Budget Issue Requests - Tracking Id #969 |
| Orlando Sanford International Airport Entrance Roadway Enhancements |
| |
| Requester: |
Victor D. White |
Organization: |
Orlando Sanford International Airport |
| |
| Project Title: |
Orlando Sanford International Airport Entrance Roadway Enhancements |
Date Submitted |
1/14/2003 4:41:37 PM |
| |
| Sponsors: |
Constantine |
| |
| Statewide Interest: |
| A safer and more efficient roadway entrance to the airport will result, as well as a more attractive path in an out of the facility. |
| |
| Recipient: |
Orlando Sanford International Airport |
|
Contact: |
Victor D. White |
|
| |
One Red Cleveland Blvd, Ste. 1200 |
|
Contact Phone: |
(407) 585-4004 |
|
| |
Sanford 32773 |
| |
| Counties: |
Seminole |
| |
| Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
| |
| Project Description: |
| This project will provide for the construction of anew 4-lane divided highway entrance to the airport, as well as a signalized intersection with the new East Lake Mary Boulevard divided highway that is connecting to S.R. 415. The project will also provide for underground electric utilities, stormwater improvements , landscaping, and a new welcoming sign at the entrance to the airport. |
| |
| Is this a water project as described in Chapter 2002-291, Laws of Florida? |
No |
| |
| Measurable Outcome Anticipated: |
| A safer and more efficient roadway entrance to the airport will result, as well as a more attractive path in an out of the facility. |
| |
| Amount requested from the State for this project this year: |
$250,000 |
| |
| Total cost of the project: |
$4,375,000 |
| |
| Request has been made to fund: |
Construction |
| |
| What type of match exists for this project? |
Local, Federal |
| |
Cash Amount |
$4,125,000 |
|
| |
| Was this project previously funded by the state? |
|
No |
| |
| Is future-year funding likely to be requested? |
|
No |
| |
| Was this project included in an Agency's Budget Request? |
|
No |
| |
| Was this project included in the Governor's Recommended Budget? |
No |
| |
| Is there a documented need for this project? |
Yes |
| |
Documentation: |
FDOT funded Wilbur Smith Study of roadway accessto the airport, Seminole Co Study |
| |
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
| |
Hearing Body: |
Sanford Airport Authority Board of Directors |
| |
Hearing Meeting Date: |
01/07/2003 |