Community Budget Issue Requests - Tracking Id #169 |
Town of Bay Harbor Islands Community Enhancements Program Phase II and III Stormwater Component |
|
Requester: |
Greg Tindle, Town Manager |
Organization: |
Town of Bay Harbor Islands |
|
Project Title: |
Town of Bay Harbor Islands Community Enhancements Program Phase II and III Stormwater Component |
Date Submitted |
12/30/2003 10:49:19 AM |
|
Sponsors: |
Margolis |
|
Statewide Interest: |
General interests for stormwater clean-up and water quality improvements to Biscayne Bay. |
|
Recipient: |
Town of Bay Harbor Islands |
|
Contact: |
J.C. Jiminez, Assistant to the Town Manager |
|
|
9665 Bay Harbor Terrace |
|
Contact Phone: |
(305) 866-6241 |
|
|
Bay Harbor Islands 33154 |
|
Contact email: |
bayharbor@the-beach.net |
|
Counties: |
Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Upgrading drainage system to meet National Pollutant Discharde Elimination System (NPDES) and Department of Environmental Resource Management (DERM) requirements. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
PENDING |
|
Measurable Outcome Anticipated: |
Reduced flood levels and stormwater treatment. |
|
Amount requested from the State for this project this year: |
$2,580,000 |
|
Total cost of the project: |
$5,160,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$2,580,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$1,245,000 |
To Fund: |
Construction, Future Phase IV Construction |
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Town of Bay Harbor Islands Stormwater Master Plan, 1996; National Pollutant Discharge Elimitaion Sy |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Bay Harbor Islands Town Council; Miami Dade Delegation |
|
Hearing Meeting Date: |
11/13/2002 |