| Community Budget Issue Requests - Tracking Id #797 |
| Construction and Post-Construction Sampling - Wagner Creek Dredging Phases IV and V (B-5643, B-5644) |
| |
| Requester: |
Joe Arriola |
Organization: |
City of Miami |
| |
| Project Title: |
Construction and Post-Construction Sampling - Wagner Creek Dredging Phases IV and V (B-5643, B-5644) |
Date Submitted |
1/13/2004 2:36:14 PM |
| |
| Sponsors: |
Wilson |
| |
| Statewide Interest: |
| Preservation of Biscayne Bay and Miami River |
| |
| Recipient: |
City of Miami Department of Capital Improvements |
|
Contact: |
Jose L. Lago, P.E. / Ignacio Ortiz-Petit |
|
| |
444 SW 2nd Avenue, 8th Floor |
|
Contact Phone: |
(305) 416-1252 |
|
| |
Miami 33130 |
|
Contact email: |
Iortiz-Petit@ci.miami.fl.us |
| |
| Counties: |
Dade |
| |
| Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
| |
| Project Description: |
| Dredging of Wagner Creek and removal of contaminants. |
| |
| Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
| Has the project been submitted to the Department of Environmental Protection? |
Yes |
| DEP Identfying Number: |
SW 20032047 |
| |
| Measurable Outcome Anticipated: |
| The project will clean Wagner Creek and greatly reduce the amount of contaminants entering the Miami River and ultimately Biscayne Bay. |
| |
| Amount requested from the State for this project this year: |
$1,350,000 |
| |
| Total cost of the project: |
$4,350,000 |
| |
| Request has been made to fund: |
Construction |
| |
| What type of match exists for this project? |
Local |
| |
Cash Amount |
$3,050,000 |
|
| |
| Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2004 |
Amount: |
$1,000,000 |
| |
| Is future-year funding likely to be requested? |
|
No |
| |
| Was this project included in an Agency's Budget Request? |
|
No |
| |
| Was this project included in the Governor's Recommended Budget? |
Unknown |
| |
| Is there a documented need for this project? |
Yes |
| |
Documentation: |
Local Flood Mitigation Plan |
| |
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
| |
Hearing Body: |
City of Miami Commission |
| |
Hearing Meeting Date: |
11/23/2003 |