| Community Budget Issue Requests - Tracking Id #2852 |
| City of Chiefland Wellfield |
| |
| Requester: |
Sunshine Baynard, Mayor |
Organization: |
City of Chiefland Commission |
| |
| Project Title: |
City of Chiefland Wellfield |
Date Submitted |
1/14/2005 3:48:54 PM |
| |
| Sponsors: |
Rod Smith |
| |
| Statewide Interest: |
| Improved services by relocating city wells from sinkhole prone area to newly purchased lands. |
| |
| Recipient: |
City of Chiefland |
|
Contact: |
Edwin L. Smith |
|
| |
214 East Park Avenue |
|
Contact Phone: |
(352) 493-6711 |
|
| |
Chiefland 32626 |
|
Contact email: |
ed@chieflandfla.com |
| |
| Counties: |
Levy |
| |
| Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
| |
| Project Description: |
| The City of Chiefland is in the process of obtaining approximately 160 acres to use as a future wellfield site for the city. The city has experienced sinkhole problems at the current wellfield where Wells #3 and #4 are located. Our goal is to run lines from the new wellfield site back to the city and tie into our current system. |
| |
| Is this a project related to 2004 hurricane damage? |
Yes |
| Have you applied for financial assistance from FEMA? |
No |
| |
| Measurable Outcome Anticipated: |
| Relocation of wells to new lands which are not subject to sinkholes. |
| |
| Amount requested from the State for this project this year: |
$1,084,000 |
| |
| Total cost of the project: |
$1,084,000 |
| |
| Request has been made to fund: |
Construction |
| |
| What type of match exists for this project? |
None |
| |
Cash Amount |
$ |
|
| |
| Was this project previously funded by the state? |
|
No |
| |
| Is future-year funding likely to be requested? |
|
No |
| |
| Was this project included in an Agency's Budget Request? |
|
No |
| |
| Was this project included in the Governor's Recommended Budget? |
No |
| |
| Is there a documented need for this project? |
Yes |
| |
Documentation: |
Water Facility Study |
| |
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
| |
Hearing Body: |
City of Chiefland Commission meeting |
| |
Hearing Meeting Date: |
01/20/2005 |
| |
| Is this a water project as described in Section 403.885, Laws of Florida? |
|
Yes |
| Has the project been submitted to the Department of Environmental Protection? |
No |
| Is this project eligible under section 403.885(5) F.S.? |
No |
| |
| Is your project addressed in a state, regional or local plan (such as a SWIM plan, Comprehensive Plan, local master plan, etc.)? |
No |
| |
| If you are requesting funding for a stormwater or surface water restoration project: |
| |
| Which Water Management District has the jurisdiction of your project? |
| |
Suwannee River Water Management District |
| Have you provided at least 50% match? |
No |
| |
| Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? |
No |
| |
| If you are requesting funding for a wastewater project: |
| |
| Does your project qualify for funding from DEP's 'Small Community Wastewater Treatment Grant Program' under section 403.1838 F.S.? |
No |
| |
| Other wastewater projects: |
| |
| Have you received previous legislative funding for this project? |
No |
| |
| Is the project under construction? |
No |
| |
| Have you provided at least a 25% local match? |
No |