| Community Budget Issue Requests - Tracking Id #1930 |
| Canal Dredging |
| |
| Requester: |
Helen Gray |
Organization: |
City of Pompano Beach |
| |
| Project Title: |
Canal Dredging |
Date Submitted |
1/13/2006 11:53:47 AM |
| |
| Sponsors: |
Atwater |
| |
| Statewide Interest: |
| Improve navigable waterways for boats and improve the management of storm water |
| |
| Recipient: |
City of Pompano Beach |
|
Contact: |
Brian Donovan, Budget Officer |
|
| |
100 West Atlantic Boulevard |
|
Contact Phone: |
(954) 786-4607 |
|
| |
Pompano Beach 33060 |
|
Contact email: |
brian.donovan@copbfl.com |
| |
| Counties: |
Broward |
| |
| Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
| |
| Project Description: |
| This is an annual project to dredge canals throughout the City. The City has over 26 miles of navigable canals and 5 tidal lakes. Preliminary bathymetric surveys of all City owned canals indicates that approximately 20% of the canals have shoaled areas that impair navigation. This program includes mechanically dredging impaired canals to a minimum depth of 5 feet at Mean Low Water. The dreding occurs only in the center 40 feet of the canal, which is the area shared by all boaters using the canal. |
| |
| Is this a project related to a federal or state declared disaster? |
No |
| |
| Measurable Outcome Anticipated: |
| Pre and post bathymetric surveys are performed to insure compliance with minimum channel depths. Vessel safety and boating activities are improved for a critical Broward County industry. |
| |
| Amount requested from the State for this project this year: |
$250,000 |
| |
| Total cost of the project: |
$500,000 |
| |
| Request has been made to fund: |
Construction |
| |
| What type of match exists for this project? |
Local |
| |
Cash Amount |
$250,000 |
|
| |
| Was this project previously funded by the state? |
|
No |
| |
| Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$250,000 |
To Fund: |
Construction |
| |
| Was this project included in an Agency's Budget Request? |
|
No |
| |
| Was this project included in the Governor's Recommended Budget? |
No |
| |
| Is there a documented need for this project? |
Yes |
| |
Documentation: |
Bathymetric Surveys, Associated Report and Master Plan reevaluated annually |
| |
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
| |
Hearing Body: |
City of Pompano Beach City Commission |
| |
Hearing Meeting Date: |
07/12/2005 |
| |
| Is this a water project as described in Section 403.885, Laws of Florida? |
|
No |