Stormwater System Improvements
 
Requester: Ron E. Williams Organization: Village of Palmetto Bay
 
Project Title: Stormwater System Improvements Date Submitted 1/4/2008 11:39:52 AM
 
Sponsors: Bullard
 
Statewide Interest:
Reduces flooding and resulting hazardous conditions which pose a threat to the public health and safety, property and the environment.
 
Recipient: Village of Palmetto Bay   Contact: Olga Cadaval  
  8950 SW 152nd Street   Contact Phone: (305) 259-1234  
  Palmetto Bay 33157   Contact email: ocadaval@palmettobay-fl.gov
 
Counties: Miami-Dade
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
The construction of catch basins and exfiltration trenches at low points of the roadway swales of the sub-basins and connect to drainage wells at various locations throughout the Village. This will be done at various strategic locations to control flooding and other hazards associated with stormwater surges. The project will reduce pollutant loadings to Biscayne Bay.
 
Is this a project related to a federal or state declared disaster? Yes
If yes, which declared disaster? Hurricane Frances, Hurricane Katrina, Tropical Storm Rita and Hurricane Wilma
If yes, which year? 2004 & 2005
 
Measurable Outcome Anticipated:
Safeguard life and property, improve disaster response capabilities, and reduce pollutant loadings to Biscayne Bay.
 
Amount requested from the State for this project this year: $1,000,000
 
Total cost of the project: $2,000,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local
  Cash Amount $1,000,000  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   No
 
Was this project included in the Governor's Recommended Budget? Unknown
 
Is there a documented need for this project? Yes
  Documentation: Village of Palmetto Bay Stormwater Master Plan
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: Village of Palmetto Bay Council
 
Is this a water project as described in Section 403.885, Laws of Florida?   Yes
Is the project eligible under section 403.885(2),F.S. to protect public health or the environment; and implement plans developed pursuant to the Surface Water Improvement and Management Act created in part IV of Chapter 373,F.S., other water restoration plans required by law, management plans prepared pursuant to 2.403.067,F.S., or other plans adopted by local government for water quality improvement and water restoration? Yes
Is your project addressed in a state, regional or local plan (such as a SWIM Plan, Comprehensive Plan, Local Master Plan, etc.)? Yes
Name the plan and cite the pages on which the project is described:
Stormwater Master Plan; addendum identifying additional areas of localized flooding.
 
Are requesting funding for a stormwater, surface water restoration, or other water management project?
Yes
 
In which Water Management District is your project located?
  South Florida Water Management District
Have you provided at least 50% match (that is, one-half the total project cost identified in this request? Yes
  Match Amount: 1000000
  Match Source: SFWMD
 
Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? Yes
  Name of water body: Biscayne Bay
 
Describe, specifically, how it will reduce loadings, identify anticipated load reductions for total suspended solids, total nitrogen, total phosphorus, and other contaminants, and specify the practices that will be used to reduce loadings:
Reduction Factors Calculation Inlet Trap + Baffle Box + Exfiltration Trench (to treat 0.5" runoff) Phosphorus 100*(0.853)+(100-100*(0.853))*0.50=92.65% Nitrogen 100*(0.79)+(100-100*(0.79))*0.50=89.50% TSS 100*(0.811)+(100-100*(0.811))*0.50=90.55%
Is the project under construction? No
 
Are you requesting funding for a wastewater project? No
 
Are you requesting funding for a drinking water project? No