Community Budget Issue Requests - Tracking Id #950 |
Stormwater System Improvements |
|
Requester: |
Ron E. Williams |
Organization: |
Village of Palmetto Bay |
|
Project Title: |
Stormwater System Improvements |
Date Submitted |
1/4/2008 11:39:52 AM |
|
Sponsors: |
Bullard |
|
Statewide Interest: |
Reduces flooding and resulting hazardous conditions which pose a threat to the public health and safety, property and the environment. |
|
Recipient: |
Village of Palmetto Bay |
|
Contact: |
Olga Cadaval |
|
|
8950 SW 152nd Street |
|
Contact Phone: |
(305) 259-1234 |
|
|
Palmetto Bay 33157 |
|
Contact email: |
ocadaval@palmettobay-fl.gov |
|
Counties: |
Miami-Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The construction of catch basins and exfiltration trenches at low points of the roadway swales of the sub-basins and connect to drainage wells at various locations throughout the Village. This will be done at various strategic locations to control flooding and other hazards associated with stormwater surges. The project will reduce pollutant loadings to Biscayne Bay. |
|
Is this a project related to a federal or state declared disaster? |
Yes |
If yes, which declared disaster? |
Hurricane Frances, Hurricane Katrina, Tropical Storm Rita and Hurricane Wilma |
If yes, which year? |
2004 & 2005 |
|
Measurable Outcome Anticipated: |
Safeguard life and property, improve disaster response capabilities, and reduce pollutant loadings to Biscayne Bay. |
|
Amount requested from the State for this project this year: |
$1,000,000 |
|
Total cost of the project: |
$2,000,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$1,000,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Village of Palmetto Bay Stormwater Master Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Village of Palmetto Bay Council |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
Yes |
Is the project eligible under section 403.885(2),F.S. to protect public health or the environment; and implement plans developed pursuant to the Surface Water Improvement and Management Act created in part IV of Chapter 373,F.S., other water restoration plans required by law, management plans prepared pursuant to 2.403.067,F.S., or other plans adopted by local government for water quality improvement and water restoration? |
Yes |
Is your project addressed in a state, regional or local plan (such as a SWIM Plan, Comprehensive Plan, Local Master Plan, etc.)? |
Yes |
Name the plan and cite the pages on which the project is described: |
Stormwater Master Plan; addendum identifying additional areas of localized flooding. |
|
Are requesting funding for a stormwater, surface water restoration, or other water management project? |
Yes |
|
In which Water Management District is your project located? |
|
South Florida Water Management District |
Have you provided at least 50% match (that is, one-half the total project cost identified in this request? |
Yes |
|
Match Amount: |
1000000 |
|
Match Source: |
SFWMD |
|
Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? |
Yes |
|
Name of water body: |
Biscayne Bay |
|
Describe, specifically, how it will reduce loadings, identify anticipated load reductions for total suspended solids, total nitrogen, total phosphorus, and other contaminants, and specify the practices that will be used to reduce loadings: |
Reduction Factors Calculation
Inlet Trap + Baffle Box + Exfiltration Trench (to treat 0.5" runoff)
Phosphorus 100*(0.853)+(100-100*(0.853))*0.50=92.65%
Nitrogen 100*(0.79)+(100-100*(0.79))*0.50=89.50%
TSS 100*(0.811)+(100-100*(0.811))*0.50=90.55%
|
Is the project under construction? |
No |
|
Are you requesting funding for a wastewater project? |
No |
|
Are you requesting funding for a drinking water project? |
No |