Community Budget Issue Requests - Tracking Id #955 |
143rd Street Stormwater Drainage and Street Improvements |
|
Requester: |
Jannie R. Beverly |
Organization: |
City of Opa Locka |
|
Project Title: |
143rd Street Stormwater Drainage and Street Improvements |
Date Submitted |
12/28/2007 10:21:13 AM |
|
Sponsors: |
Wilson |
|
Statewide Interest: |
This project furthers the statewide interest by reducing the nuisance and damages due to flooding. It provides for a more efficient reduction of surface water pollution, decreases potential for bacterial and mosquitoes growth from standing water and is consistent with (ch373, F.S. & ch 403,F.S.). |
|
Recipient: |
City of Opa Locka |
|
Contact: |
Jannie R. Beverly |
|
|
780 Fisherman Street, Suite 335 |
|
Contact Phone: |
(305) 953-2821 |
|
|
Miami 33054 |
|
Contact email: |
city_manager@opalockafl.gov |
|
Counties: |
Miami-Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The existing street has no functional drainage system. Past rainy events have resulted major flooding and disaster-like conditions. The standing water takes days to recede creating a breeding ground for mosquitoes, liter and possible contamination from flooded sanitary sewer water. In addition to the extreme nuisance, this adverse condition impacts traffic safety and the economy local small business . |
|
Is this a project related to a federal or state declared disaster? |
No |
|
Measurable Outcome Anticipated: |
Improved level of service and mititgated flooding. |
|
Amount requested from the State for this project this year: |
$620,000 |
|
Total cost of the project: |
$620,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2005-2006 |
Amount: |
$192,500 |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Flood Mitigation Strategy Project |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Miami- Dade County Legislative Delegation 2006 Public Hearing |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
No |