Senate Committee Publications
|
|
|
|
|
|
|
|
|
|
Community Budget Issue Requests - Tracking Id #306FY0102 |
|||||||||
Renovations of County Courthouse Calhoun County |
|||||||||
|
|
|
|
|
|
|
|
|
|
Requester: |
Ruth Attaway |
Organization: |
Clerk of Courty |
||||||
|
|
|
|
|
|
|
|
|
|
Project Title: |
Renovations of County Courthouse Calhoun County |
Date Submitted: |
1/11/2002 1:05:42 PM |
||||||
|
|
|
|
|
|
|
|
|
|
Sponsors: |
Alfred Lawson |
||||||||
|
|
|
|
|
|
|
|
|
|
Statewide Interest: |
|
|
|
|
|
|
|
||
Meets ADA requirements and will provide facilities for the judicial needs of the county and will provide a meeting room for the community |
|||||||||
|
|
|
|
|
|
|
|
|
|
Recipient: |
Calhoun County Clerk of Court |
|
Contact: |
Ruth Attaway |
|
||||
|
20859 SE Central Avenue E. |
|
Contact Phone: |
(850) 674-4545 |
|
||||
|
|
Blountstown 32424 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
|
|
Counties: |
Calhoun |
||||||||
|
|
|
|
|
|
|
|
|
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
|||||
|
|
|
|
|
|
|
|
|
|
Project Description: |
|
|
|
|
|
|
|
||
Provides for increase in parking facilities, includes paving and relocating the parking closer to the courthouse complex that will better accomodate the elderly. Also will� provide for the installation of a new sprinkler system,� The existing courthouse facility was constructed prior to the requirement of sprinkler systems for fire protection.� The courthouse has four stories and to install such a system will be a major construction project.� Finally the elevator in the existing courthouse was installed in 1971 before additional safety requirements were in law.� THe life fo the elevator system's hydraulic system is 25-30 years.� The elevator must be completely rebuilt.� there are also some ADA issues that must be met as well |
|||||||||
|
|
|
|
|
|
|
|
|
|
Measurable Outcome Anticipated: |
|
|
|
|
|
||||
The Court/Community AnnexBuilding will allow access to all citizens and visitors.� This buidling will be used on a monthly basis for minimum of two public county commission meetins and any court proceedings.� It will also be used for subcommittee meetings as directed by the Board as well as other meetings held by community or government entities.� In addition, staff space is being factored into the renovation of the building so that future growth needs will be more cost effectively met. Parking will benefit each of these functions.� The sprinkler system and the renovation of the elevator will mean a high degree of confidence in the safety of all our citizens usiing these facilities |
|||||||||
|
|
|
|
|
|
|
|
|
|
Amount requested from the State for this project this year: |
$265,000 |
||||||||
|
|
|
|
|
|
|
|
|
|
Total cost of the project: |
$240,000 |
|
|
|
|
||||
|
|
|
|
|
|
|
|
|
|
Request has been made to fund: |
Operations and Construction |
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
What type of match exists for this project? |
Local |
|
|||||||
|
|
|
In-Kind Amount: |
$25,000 |
|
||||
|
|
|
|
|
|
|
|
|
|
Was this project previously funded by the State? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Is future-year funding likely to be requested? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in an Agency's Budget Request? |
|
No |
|
||||||
|
|
|
|
|
|
|
|
|
|
Was this project included in the Governor's Recommended Budget? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|
Is there a documented need for this project? |
|
Yes |
|
||||||
|
Documentation: |
ADA compliance requirements |
|||||||
|
|
|
|
|
|
|
|
|
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
No |
|
|||||||
|
|
|
|
|
|
|
|
|
|