Belleview Wastewater Utilities Improvements
 
Requester: Sandi McKamey, City Clerk Administrator Organization: City of Belleview
 
Project Title: Belleview Wastewater Utilities Improvements Date Submitted 1/10/2003 2:37:32 PM
 
Sponsors: Lynn
 
Statewide Interest:
In adequate capacity coupled with inflow/infiltration issues represents a potential threat to the enjvironment. The implementation of this project will help protect the environment by ensuring that raw sewage is properly collected and treated. Odor control and equipment noise issues exsist and the current treatment facility. The proposed improvements will be designed to minimize noise and odor. Improvements necessary are anticipated to provide at aleast Class B level sludge product, which is also an improvement over the current situation.
 
Recipient: City of Belleview   Contact: Dennis Monroe, Director of Public Works  
  5343 S.E. Abshier Blvd.   Contact Phone: (352) 245-7021  
  Belleview 34420
 
Counties: Marion
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
this project includes the plannning, administration, engineering and construiction of improvement to the wastewater collection, treatment and reuse system within the Vity of Belleview. The City's treatment capacity is not sufficent. The planning associated with this request will allow the City to properly identify a solution for capacity and level of treatment that is environmentally sound, technically feasible, cost effective, and able to be implemented and permitted. this project will ensure that the City of Belleview can provide adequate wastewater collection and treatment facilities in the community.
 
Is this a water project as described in Chapter 2002-291, Laws of Florida? Yes
Has the project been submitted to the Department of Environmental Protection? Yes
DEP Identfying Number: WW20022093
 
Measurable Outcome Anticipated:
A groundwater analysis identified exceedance of Maximum Contaminant Levels for turbidity present in all of the monitoring wells. The improvements included in this project will include reliability and other features to minimize or eliminate the potential for future MCL exceedance issues.
 
Amount requested from the State for this project this year: $1,500,000
 
Total cost of the project: $8,600,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? None
  Cash Amount $  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   Yes
  Amount: $7,400,000 To Fund: Construction
 
Was this project included in an Agency's Budget Request?   Yes
  Agency Environmental Protection, Department Of
 
Was this project included in the Governor's Recommended Budget? Unknown
 
Is there a documented need for this project? Yes
  Documentation: The City of Belleview Wastewater Management Plan, Long Range Plan
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: The City Commission of the City of Belleview
  Hearing Meeting Date: 10/30/2002