Community Budget Issue Requests - Tracking Id #1010 |
DeSoto County Water Project |
|
Requester: |
Mary Dougherty-Slapp |
Organization: |
DeSoto County |
|
Project Title: |
DeSoto County Water Project |
Date Submitted |
1/15/2004 11:27:50 AM |
|
Sponsors: |
Alexander |
|
Statewide Interest: |
Capital outlay for regional water supply_in an area identified as a Rural Area of Critical Economic Concern.__ |
|
Recipient: |
DeSoto County |
|
Contact: |
Mary Dougherty-Slapp |
|
|
201 E. Oak St. Suite 201 |
|
Contact Phone: |
(863) 993-4800 |
|
|
Arcadia_ 34266 |
|
Contact email: |
|
|
Counties: |
DeSoto |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Construction of a potable water main from the Peace River Manasota Regional Water Supply Authority, connecting to the DeSoto County Utility Water pipeline and continuing along the proposed construction route providing water distribution to residents and businesses within the County. Reducing reliance on groundwater contaminated with Radium and protecting the watershed in an area identified as being within the Southern Water Use Caution Area by the Southwest Florida Water Management District. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
DW20022156 |
|
Measurable Outcome Anticipated: |
number of miles of transmission line constructed |
|
Amount requested from the State for this project this year: |
$2,000,000 |
|
Total cost of the project: |
$9,827,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local, Federal |
|
Cash Amount |
$9,827,000 |
|
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2002 |
Amount: |
$2,000,000 |
|
Is future-year funding likely to be requested? |
|
Unknown |
|
Was this project included in an Agency's Budget Request? |
|
Unknown |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Hartman and Assoc. Water/Wastewater Design Report, Southwest Florida Water Management District Regio |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
DeSoto County Board of County Commissioners |
|
Hearing Meeting Date: |
10/28/2003 |