Community Budget Issue Requests - Tracking Id #11 |
City of Bradenton-Wares Creek |
|
Requester: |
Mayor Wayne Poston |
Organization: |
City of Bradenton |
|
Project Title: |
City of Bradenton-Wares Creek |
Date Submitted |
1/5/2004 8:55:09 AM |
|
Sponsors: |
Miller |
|
Statewide Interest: |
This project is regional in scope and will address two areas of concern that are regulated by the state: stormwater treatment and surface quarter quality restoration. |
|
Recipient: |
City of Bradenton |
|
Contact: |
John W. Cummings |
|
|
101 Old Main St. |
|
Contact Phone: |
(941) 708-6300 |
|
|
Bradenton, FL 34205 |
|
Contact email: |
|
|
Counties: |
Manatee |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The project is an integral companion to the $16,000,000 Army Corp of Engineers (ACOE) Cedar Hammock (Wares Creek) Flood Control Channel improvements projects, in which the ACOE will dredge and widen Wares Creek for flood control. By rule, the ACOE will not participate in the replacement of the city's bridges or improvements to the city's existing stormwater systems. The city is responsible for this critical part of the overall project. The project involves:
1. Replacement of undersized bridges that cross Wares Creek within the City of Bradenton with structures that provide improved water flow characteristics. Bridge replacements will reduce the flooding of Master Sewage Pump Station 14 and private residences. The bridges to be replaced are the 9th Avenue West Bridge, the 12th Avenue West Bridge, the 14th Avenue West Bridge, and the 17th Avenue West Bridge.
2. Improvements to exisiting stormwater facilities that drain into Wares Creek in the vicinity of the bridges to enhance stormwater treatment and conveyance. The project will cost $4,480,000 and will be constructed over a four-year period. This project has been submitted to DEP as an "HB 851" project, under Chapter 2002.291 of Florida Statutes. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
SWR20023030 |
|
Measurable Outcome Anticipated: |
A. Reduced flooding and resulting property damage. B. Improved water quality in Wares Creek and Manatee River.
C. Improve ability of emergency response vehicles to respond to emergencies by eliminating flooding of bridges and roads. |
|
Amount requested from the State for this project this year: |
$525,000 |
|
Total cost of the project: |
$1,050,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$525,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$1,715,000 |
To Fund: |
Construction |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Rev. to Oct '81 Comphrensive Storm Water Mgmt Study, Cedar Hammock Final Detailed Proj.Rpt. |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Manatee County Legislative Delegation |
|
Hearing Meeting Date: |
10/08/2003 |