Community Budget Issue Requests - Tracking Id #126 |
City of Miami Beach Stormwater Projects |
|
Requester: |
Judy Hoanshelt |
Organization: |
City of Miami Beach |
|
Project Title: |
City of Miami Beach Stormwater Projects |
Date Submitted |
1/9/2004 5:46:20 PM |
|
Sponsors: |
Margolis |
|
Statewide Interest: |
Protects public health and the environment and implements plans developed pursuant to the Surface Water Improvement and Management Act. Implements the City's Master Plan adopted by the City of Miami Beach Commission. Eliminates the need for future funding as a result of flooding. |
|
Recipient: |
City of Miami Beach |
|
Contact: |
Judy Hoanshelt |
|
|
1700 Convention Center Drive |
|
Contact Phone: |
(305) 673-7000 |
|
|
Miami Beach 33139 |
|
Contact email: |
|
|
Counties: |
Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The City's Master Plan effort identified over 160 drainage basins throughout the City of Miami Beach. Approximately 34 of these basins were identified as a priority, based upon pollutant loading, pollutant above sea level and the City's stormwater system is not capable of handling a 5-year storm event, as a result, flooding occurs in many of the basins, with even higher flooding levels during high tide. Flooding has a significant environmental, health & economic impact, causing businesses to be inaccessible to customers, and resulting in the initial cost of replacing and repairing damaged property. In addition, due to high groundwater elevation, drainage is slow, in these areas, requiring extensive periods of time to dissipate. Continuous excessive ponding over the long term has caused deterioration and then failure of paved roads, mosquito breeding areas, and other public health issues. The City has committed to improving the facilities within the 34 priority basins. Stormwater will be collected and treated through either gravity wells or exfiltration trenches, where pollutants will be filtered or treated. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
SW 20022260 |
|
Measurable Outcome Anticipated: |
Improved facilities at the 34 priority basins. Stormwater will be collected and treated through either gravity wells or exfiltration trenches, where pollutants will be filtered or treated. |
|
Amount requested from the State for this project this year: |
$5,000,000 |
|
Total cost of the project: |
$23,050,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$18,000,000 |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Unknown |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
City of Miami Beach Master Plan and Biscayne Bay Surface Water Improvement & Management (SWIM) Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City of Miami Beach Commission Meeting |
|
Hearing Meeting Date: |
11/14/2003 |