Community Budget Issue Requests - Tracking Id #159 |
City of DeFuniak Springs Lift Station Replacement and Rehabilitation |
|
Requester: |
Michael G. Standley |
Organization: |
City of Defuniak Springs |
|
Project Title: |
City of DeFuniak Springs Lift Station Replacement and Rehabilitation |
Date Submitted |
1/15/2004 5:15:52 PM |
|
Sponsors: |
Peaden |
|
Statewide Interest: |
Environmental Protection |
|
Recipient: |
City of DeFuniak Springs |
|
Contact: |
Michael G. Standley |
|
|
71 US Highway 90 W |
|
Contact Phone: |
(850) 892-8500 |
|
|
DeFuniak Springs 32433 |
|
Contact email: |
cityofdfs@gdsys.net |
|
Counties: |
Walton |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The project will include rehabilitation to the City's existing wastewater collection system by retrofitting five (5) sewage lift stations. The lift stations are L.S. #3, #5, #6, #10, and #16. Lift Station #3 is located on Orange Avenue at 16th Street; #5 is located on South 25th Street at West DeFuniak Elementary School; #6 is located on North 1st Street at Burdick Avenue; #10 is located at Lake Stanley park on Shoemaker Drive, and #16 is located on North 12th Street. These five (5) lift stations are main stations that serve critical faciliteis and 3 of the 5 serve as repumping stations. These five (5)lift stationsa re important to the overall operation of the sytem. Lift Stations #3, #5, and #6 will be replaced with newly constructed stations. The new stations will consist of new well, pumps, valving with bypass connections, valave box, control panel with emergency generator receptacle and associated mechanical equipment. The other two lift stations, #10 and #16 would be rehabilitated. The rehabilitation of these two stations would include the replacement of the existing vacuum-primed pumps, valves, piping, controls and control panels, wetwell concrete top with aluminum hatch, valve box with bypass connection and modification to the existing wetwells. Engineer's Opinion of Probable Const: L.S. #3 $92,400; L.S. #5 $92,400; L.S. #6 $163,900; L.S. #10 $106,150; L.S. #16 $106,120; Estimated Engineering Services $32,353; Estimated Resident Observation Services $14,672; Total Project Costs $608,025. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
WW20022205 |
|
Measurable Outcome Anticipated: |
Immedicate relief of potential health hazards. |
|
Amount requested from the State for this project this year: |
$609,000 |
|
Total cost of the project: |
$609,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Unknown |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City of Defuniak Springs |
|
Hearing Meeting Date: |
11/12/2002 |