| Community Budget Issue Requests - Tracking Id #253 |
| Homosassa Wastewater Collection System Project - Phase 5 |
| |
| Requester: |
Richard Wm. Wesch, Esq. - County Adminstrator |
Organization: |
Citrus County Board of County Commissioners |
| |
| Project Title: |
Homosassa Wastewater Collection System Project - Phase 5 |
Date Submitted |
12/30/2003 12:38:19 PM |
| |
| Sponsors: |
Argenziano, Fasano |
| |
| Statewide Interest: |
| This project will improve the water quality of the Homosassa River by elimination of septic tanks from areas adjacent to the surface waters of the Homosassa River. |
| |
| Recipient: |
Citrus County Board of County Commissioners |
|
Contact: |
J. Kenneth Clark |
|
| |
111 West Main Street |
|
Contact Phone: |
(352) 527-5450 |
|
| |
Inverness 34450 |
|
Contact email: |
|
| |
| Counties: |
Citrus |
| |
| Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
| |
| Project Description: |
| Design and construct new wastewater collection facilities to serve existing development adjacent to the Homosassa River, an Outstanding Florida Waterway. |
| |
| Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
| Has the project been submitted to the Department of Environmental Protection? |
Yes |
| DEP Identfying Number: |
2002007 |
| |
| Measurable Outcome Anticipated: |
| Elimination of approximately 80 septic tanks in the Homosassa area. |
| |
| Amount requested from the State for this project this year: |
$2,000,000 |
| |
| Total cost of the project: |
$2,000,000 |
| |
| Request has been made to fund: |
Construction |
| |
| What type of match exists for this project? |
None |
| |
Cash Amount |
$ |
|
| |
| Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2001-2002 |
Amount: |
$750,000 |
| |
| Is future-year funding likely to be requested? |
|
No |
| |
| Was this project included in an Agency's Budget Request? |
|
No |
| |
| Was this project included in the Governor's Recommended Budget? |
No |
| |
| Is there a documented need for this project? |
Yes |
| |
Documentation: |
Homosassa River Water Quality Study |
| |
| Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
| |
Hearing Body: |
Citrus County Board of County Commissioners |
| |
Hearing Meeting Date: |
10/14/2003 |