Community Budget Issue Requests - Tracking Id #27 |
Belleview Wastewater Utilities Improvements |
|
Requester: |
Sandi McKamey |
Organization: |
City of Belleview |
|
Project Title: |
Belleview Wastewater Utilities Improvements |
Date Submitted |
12/19/2003 9:45:00 AM |
|
Sponsors: |
Cowin |
|
Statewide Interest: |
Inadequate capacity coupled with inflow/infiltration issues represent a potential threat to the environment.The implementation of this project will help protect the environment by ensuring that raw sewage is properly collected and treated. Odor control and equipment noise issues exist in the current treatment facility. The proposed improvements will be designed to minimize noise and odor. Improvements necessary are anticipated to provide at least class B level sludge product, which is also an improvement over the current situation |
|
Recipient: |
City of Belleview |
|
Contact: |
Dennis Monroe |
|
|
5343 Abshier Blvd. |
|
Contact Phone: |
(352) 245-7021 |
|
|
Belleview 34420 |
|
Contact email: |
|
|
Counties: |
Marion |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The project includes planning,administration, engineering and construction of improvements to the wastewater collection, treatment and reuse system of the City of Belleview. The City 's treatment capacity is not sufficient. The planning associated with this request will allow the City to properly identify a solution for capacity and level of treatment that is environmentally sound,technically feasible, cost effective and able to be implemented and permitted. This project will ensure that the City of Belleview can provide adequate wastewater collection and treatment facilities for the community. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
Yes |
Has the project been submitted to the Department of Environmental Protection? |
Yes |
DEP Identfying Number: |
WW20022093 |
|
Measurable Outcome Anticipated: |
A grondwater analysis identified exeedances of Maximum Contaminant Levels(MCL)for turbitity present in all monitering wells. The improvements included in this project will include reliability and other features tomminimize or eliminate the potetial for future MCL exeedance issues. This project will minimize or eleminate the potential for backup of sewage into homes. An adequately sized sewer collection, treatment and reuse system will ensure that wastewater is properly collected, treated and disposed, which provides public health protection. |
|
Amount requested from the State for this project this year: |
$1,500,000 |
|
Total cost of the project: |
$8,600,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$7,400,000 |
To Fund: |
Construction |
|
Was this project included in an Agency's Budget Request? |
|
Yes |
|
Agency |
Environmental Protection, Department Of |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
City of Belleview Masterplan(1996)City Comprehensive Plan and Capital Improvement Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City Council of Belleview |
|
Hearing Meeting Date: |
10/30/2002 |