Community Budget Issue Requests - Tracking Id #3357 |
Wastewater Hauler Tanker Truck |
|
Requester: |
Rae Carole Armstrong |
Organization: |
City of Plantation |
|
Project Title: |
Wastewater Hauler Tanker Truck |
Date Submitted |
1/13/2006 4:23:21 PM |
|
Sponsors: |
Rich |
|
Statewide Interest: |
The City of Plantation is situated 8 miles from the Atlantic Ocean near Ft. Lauderdale, 10 miles to the west is the Everglades. It is charged with the purveyance of potable water and sanitary sewer essential to the health, safety and welfare of the community.
Hurricanes Francis, Jeanne, Katrina and Wilma demonstrated a clear need to be able to maintain the collection of sewage when electrical power is eliminated by storm damage such as wind and flooding. Further, it is necessary to reduce potable water flow to the public if the resulting sewage from that potable water flow cannot be addressed in a safe manner without risk of public contact with sewage spills.
The need for an emergency generator is identified and substantiated in the Florida Statutes, local, county, and in state emergency operations plans.
|
|
Recipient: |
City of Plantation |
|
Contact: |
Dane Keefe |
|
|
400 NW 73rd Avenue |
|
Contact Phone: |
(954) 797-2212 |
|
|
Plantation 33317 |
|
Contact email: |
dkeefe@plantation.org |
|
Counties: |
Broward |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Purchase tanker truck to relieve backups during emergency operations. |
|
Is this a project related to a federal or state declared disaster? |
Yes |
If yes, which declared disaster? |
Frances, Jeanne, Katrina & Wilma |
If yes, which year? |
2004, 2005 |
|
Measurable Outcome Anticipated: |
The procurement of a pump truck will provide short and long term tangible benefits by reducing and/or eliminating the amount of sewage that backs up into homes, businesses, hospitals and shelters during emergencies. Prevention of sewage spills during emergency operations and uninterruped waste water plant operations. |
|
Amount requested from the State for this project this year: |
$120,000 |
|
Total cost of the project: |
$120,000 |
|
Request has been made to fund: |
Operations |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
City of Plantation had almost 1/2 of its lift stations without power during emergency. |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City of Plantation - City Council |
|
Hearing Meeting Date: |
11/30/2005 |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
No |