CBIRS Request 1255
 
Community Budget Issue Requests - Tracking Id #1255
Earman River Water Pipe Line Replacement
 
Requester: Jimmy Knight, Village Manager Organization: Village of North Palm Beach
 
Project Title: Earman River Water Pipe Line Replacement Date Submitted 1/3/2008 2:47:04 PM
 
Sponsors: Atwater
 
Statewide Interest:
The project will improve the conservation of water throughout the Village of North Palm Beach and the efficient use of water from the Earman River.
 
Recipient: Village of North Palm Beach   Contact: Charles Huff  
  501 U.S. Highway 1   Contact Phone: (561) 348-0697  
  North Palm Beach 33408   Contact email: chuff@village-npb.org
 
Counties: Palm Beach
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
The current water supply pipe line from the Earman River to the Village�s retention pond has numerous leaks from the failure of its joints. The Village�s engineering consultants have determined that the complete failure of this water supply line is imminent. As a result of the consultants� review, the Village will abandon the existing pipe line and replace it by the process of directional boring. The project will also include the installation of a one-piece pipe line.
 
Is this a project related to a federal or state declared disaster? No
 
Measurable Outcome Anticipated:
This project will allow the Village to avoid the complete failure of the current pipe line which would result in the lose of a water supply from the Earman River. Losing this source of water would result in damage to Village-owned properties. By utilizing directional boring, one continuous piece of pipe will be used. This one-piece pipe will greatly reducing the possibility of future leaks and their associated repair costs. This project will improve the efficiency of water use in the Village, and continue this community�s efforts in water conservation and adherence to ongoing water restrictions.
 
Amount requested from the State for this project this year: $85,000
 
Total cost of the project: $170,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local
  Cash Amount $  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   No
 
Was this project included in the Governor's Recommended Budget? No
 
Is there a documented need for this project? Yes
  Documentation: Capital Improvement Program
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: Village of North Palm Beach Council Meeting
 
Is this a water project as described in Section 403.885, Laws of Florida?   No