Community Budget Issue Requests - Tracking Id #1848 |
Gretna Wastewater Plant Expansion/Improvement |
|
Requester: |
Antonio Jefferson, City Manager |
Organization: |
City of Gretna |
|
Project Title: |
Gretna Wastewater Plant Expansion/Improvement |
Date Submitted |
1/3/2008 2:58:14 PM |
|
Sponsors: |
Lawson |
|
Statewide Interest: |
Addresses the critical need to expand wastewater needs to residents. |
|
Recipient: |
City of Gretna |
|
Contact: |
Antonio Jerfferson |
|
|
14615 Main Street |
|
Contact Phone: |
(850) 856-5257 |
|
|
Gretna 32332 |
|
Contact email: |
ajefferson@mygretna.net |
|
Counties: |
Gadsden |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The City of Gretna's waste water plant as the result of the 384 Bed Gadsden Correctional Facility will be within 5000 gallon of the 350,000 gallon per day design capacity. As required by Florida Administrative Code the City must now expand the facility. The City desires to design and build an expanded waste water facility capable of treating at least 1 million Gallons per day. |
|
Is this a project related to a federal or state declared disaster? |
No |
|
Measurable Outcome Anticipated: |
To build a facility capable of treating at least 1.5 million gallons per day at advance waste water treatment level to provide regional waste water services. To provide adequately treated reclaimed water to supply 3 area plant nurseries with water for farming purposes, thereby minimizing or eliminating the need to use ground water. To provide waste water services to the Highway 12 Interstate 10 intersection to support economic development for the region. |
|
Amount requested from the State for this project this year: |
$2,000,000 |
|
Total cost of the project: |
$2,700,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
None |
|
Cash Amount |
$ |
|
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
City of Gretna Wastewater Master Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City of Gretna City Commission and Gadsden County Board of County Commission |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
No |