Community Budget Issue Requests - Tracking Id #699 |
City of Miami beach Stormwater Infrastructure Improvement Project |
|
Requester: |
Jorge M. Gonzalez |
Organization: |
City of Miami Beach |
|
Project Title: |
City of Miami beach Stormwater Infrastructure Improvement Project |
Date Submitted |
12/26/2007 9:24:21 AM |
|
Sponsors: |
Margolis |
|
Statewide Interest: |
Protects public health and the environment and and implements plans developed pursuant to the Surface Water Improvement and Management Act. Implements the City's Master Plan adopted by the City of Miami Beach Commission. Eliminates the need for future funding as a result of flooding. |
|
Recipient: |
City of Miami Beach |
|
Contact: |
Judy Hoanshelt |
|
|
1700 Convention Center Drive |
|
Contact Phone: |
(305) 673-7000 |
|
|
Miami Beach 33139 |
|
Contact email: |
judyhoanshelt@miamibeachfl.gov |
|
Counties: |
Miami-Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
The City's Master Plan effort identified over 160 drainage basins in the City of Miami Beach. Approximately 34 of these basins were identified as a priority, based upon pollutant loading, pollutant concentration, flooding potential, citizen complaints, and City operational staff rankings. Many of the priority drainage basins are barely above sea level and the City's stormwater system is not capable of handling a 5-year storm event, as a result, flooding occurs in many of the basins, with even higher flooding levels during high tide. Flooding has a significant environmental, health and economic impact, causing businesses to be inaccessible to customers, and resulting in the additional cost of replacing and repairing damaged property. In addition, due to high groundwater elevtion, drainage is slow in these areas, requiring extensive periods of time to disipate. Continuous excessive ponding over the long term has caused deterioration and then failure of paved roads, mosquito breeding areas, and other public health issues. The City has committed to improving the facilites within the 34 priority basins. Stormwater will be collected and treated through either gravity wells or exfiltration trenches, where pollutants will be filtered or treated. |
|
Is this a project related to a federal or state declared disaster? |
No |
|
Measurable Outcome Anticipated: |
Anticipated improved facilites at the 34 priority basins. Stormwater will be collected and treated through either gravity wells or exfiltration trenches, where pollutants will be filtered or treated. |
|
Amount requested from the State for this project this year: |
$5,000,000 |
|
Total cost of the project: |
$65,235,206 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$48,884,541 |
|
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2006-2007 |
Amount: |
$300,000 |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$5,000,000 |
To Fund: |
Construction |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
City of Miami Beach Capital Improvements Plan |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
City of Miami Beach Mayor and City Commission (City Commission Meeting) |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
Yes |
Is the project eligible under section 403.885(2),F.S. to protect public health or the environment; and implement plans developed pursuant to the Surface Water Improvement and Management Act created in part IV of Chapter 373,F.S., other water restoration plans required by law, management plans prepared pursuant to 2.403.067,F.S., or other plans adopted by local government for water quality improvement and water restoration? |
Yes |
Is your project addressed in a state, regional or local plan (such as a SWIM Plan, Comprehensive Plan, Local Master Plan, etc.)? |
Yes |
Name the plan and cite the pages on which the project is described: |
City of Miami Beach Capital Improvements Plan- FY05 Capital Budget that outline the ROW projects are pages 85-99, 103-108, 110 |
|
Are requesting funding for a stormwater, surface water restoration, or other water management project? |
Yes |
|
In which Water Management District is your project located? |
|
South Florida Water Management District |
Have you provided at least 50% match (that is, one-half the total project cost identified in this request? |
Yes |
|
Match Amount: |
48884541 |
|
Match Source: |
2000 Water and Sewer Bond Funds |
|
Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? |
Yes |
|
Name of water body: |
Bisycane Bay |
|
Describe, specifically, how it will reduce loadings, identify anticipated load reductions for total suspended solids, total nitrogen, total phosphorus, and other contaminants, and specify the practices that will be used to reduce loadings: |
Stormwater will be collected and treated through either gravity wells or exfiltatration trenches, where pollutants will be filtered or treated. |
Is the project under construction? |
Yes |
|
Are you requesting funding for a wastewater project? |
No |
|
Are you requesting funding for a drinking water project? |
No |