The bill (Chapter 2023-22, L.O.F.) amends existing law with respect to causes of action based on improvements to real property. The bill shortens the timeframes within which a property owner may bring a cause of action against a builder for alleged construction defects. It also narrows the scope of certain statutory civil actions against builders for Florida Building Code violations.

Specifically, the bill:

  • Revises the commencement of the 4-year statute of limitations by changing the listed potential commencement dates and causing the statute to run based upon whichever date is earliest instead of latest;
  • Shortens the 10-year statute of repose to 7 years;
  • Revises the commencement of the 7-year (currently 10-year) statute of repose by changing the listed potential commencement dates and causing the statute to run based upon whichever date is earliest instead of latest;
  • Provides that if a newly constructed single-dwelling residential building is used as a model home, the time to bring a construction defect action begins to run from the date that a deed is recorded first transferring title to another party;
  • Provides that if a project involves the construction of multiple buildings, each individual building must be considered its own improvement for purposes of determining the limitations period in the bill;
  • Provides a definition for “material violations” in connection with statutory civil actions against builders for alleged Florida Building Code violations, and amends existing law to limit recovery for material violations only; and
  • Includes a savings clause to ensure that claimants having time remaining under the existing statute of limitations have at least 1 year from the effective date of the bill to initiate a construction defect action.

These provisions became law upon approval by the Governor on April 13, 2023.

Vote: Senate 31-7; House 89-8