Quick Links
- General Laws Conversion Table (2024) [PDF]
- Florida Statutes Definitions Index (2024) [PDF]
- Table of Section Changes (2024) [PDF]
- Preface to the Florida Statutes (2024) [PDF]
- Table Tracing Session Laws to Florida Statutes (2024) [PDF]
- Index to Special and Local Laws (1971-2024) [PDF]
- Index to Special and Local Laws (1845-1970) [PDF]
- Statute Search Tips
2000 Florida Statutes
Final disposition of application.
403.509 Final disposition of application.--
(1) Within 60 days after receipt of the designated administrative law judge's recommended order, the board shall act upon the application by written order, approving certification or denying the issuance of a certificate, in accordance with the terms of this act, and stating the reasons for issuance or denial. If the certificate is denied, the board shall set forth in writing the action the applicant would have to take to secure the board's approval of the application.
(2) The issues that may be raised in any hearing before the board shall be limited to those matters raised in the certification proceeding before the administrative law judge or raised in the recommended order. All parties, or their representatives, or persons who appear before the board shall be subject to the provisions of s. 120.66.
(3) Within 30 days after issuance of the certification, the department shall issue and forward to the United States Environmental Protection Agency a proposed operation permit for a major source of air pollution and must issue or deny any other license required pursuant to any federally delegated or approved permit program. The department's action on the license and its action on the proposed operation permit for a major source of air pollution shall be based upon the record and recommended order of the certification hearing. The department's actions on a federally required new source review or prevention of significant deterioration permit shall be based on the record and recommended order of the certification hearing and of any other proceeding held in connection with the application for a new source review or prevention of significant deterioration permit, on timely public comments received with respect to the application or preliminary determination for such permit, and on the provisions of the state implementation plan. The department's action on a federally required new source review or prevention of significant deterioration permit shall differ from the actions taken by the siting board regarding the certification if the federally approved state implementation plan requires such a different action to be taken by the department. Nothing in this part shall be construed to displace the department's authority as the final permitting entity under the federally approved permit program. Nothing in this part shall be construed to authorize the issuance of a new source review or prevention of significant deterioration permit which does not conform to the requirements of the federally approved state implementation plan. Any final operation permit for a major source of air pollution must be issued in accordance with the provisions of s. 403.0872. Unless the federally delegated or approved permit program provides otherwise, licenses issued by the department under this subsection shall be effective for the term of the certification issued by the board. If renewal of any license issued by the department pursuant to a federally delegated or approved permit program is required, such renewal shall not affect the certification issued by the board, except as necessary to resolve inconsistencies pursuant to s. 403.516(1)(a).
(4) In regard to the properties and works of any agency which is a party to the certification hearing, the board shall have the authority to decide issues relating to the use, the connection thereto, or the crossing thereof, for the electrical power plant and site and to direct any such agency to execute, within 30 days after the entry of certification, the necessary license or easement for such use, connection, or crossing, subject only to the conditions set forth in such certification.
(5) Except for the issuance of any operation permit for a major source of air pollution pursuant to s. 403.0872, the issuance or denial of the certification by the board and the issuance or denial of any related department license required pursuant to any federally delegated or approved permit program shall be the final administrative action required as to that application.
(6) All certified electrical power plants must apply for and obtain a major source air-operation permit pursuant to s. 403.0872. Major source air-operation permit applications for certified electrical power plants must be submitted pursuant to a schedule developed by the department. To the extent that any conflicting provision, limitation, or restriction under any rule, regulation, or ordinance imposed by any political subdivision of the state, or by any local pollution control program, was superseded during the certification process pursuant to s. 403.510(1), such rule, regulation, or ordinance shall continue to be superseded for purposes of the major source air-operation permit program under s. 403.0872.
History.--s. 1, ch. 73-33; s. 7, ch. 76-76; s. 141, ch. 77-104; s. 27, ch. 86-186; s. 12, ch. 90-331; s. 8, ch. 92-132; s. 10, ch. 93-94; s. 4, ch. 94-321; s. 141, ch. 96-410.