Community Budget Issue Requests - Tracking Id #980 |
SR528/SR15 Interchange Improvements Project |
|
Requester: |
Mayor Glenda Hood |
Organization: |
City of Orlando |
|
Project Title: |
SR528/SR15 Interchange Improvements Project |
Date Submitted |
1/13/2003 4:37:42 PM |
|
Sponsors: |
Webster |
|
Statewide Interest: |
The interchange improvements are necessary to improve conditions at all the interchange locations and will accommodate the 8-laning of SR 528 and the 4-laning of SR 15 to meet regional transportation needs. The project is located at the SR 528/SR15 interchange at the northeast corner of the Orlando International Airport. These improvements will also improve SR528's operations as part of the State's hurricane evacuation system. The project is supported by the Orlando Orange County Expressway Authority, the Greater Orlando Aviation Authority, and the Canaveral Port Authority. |
|
Recipient: |
City of Orlando |
|
Contact: |
Kathy Russell |
|
|
400 S. Orange Avenue |
|
Contact Phone: |
(407) 246-3094 |
|
|
Orlando 328044990 |
|
Counties: |
Orange |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
he improvement associated with this request is approximately .30 miles long and will include structural improvements to the SR 528 mainline, SR 15 underpass, includes ramp improvements and will widen SR 15 from its current terminus at SR 528 northward to McCoy Road. The improvement will include re-construction of two-lane roadway to add two travel lanes, sidewalks, transit accommodations and bike lanes. The bike lanes will connect into the City's 160 miles of existing bikeways. |
|
Is this a water project as described in Chapter 2002-291, Laws of Florida? |
No |
|
Measurable Outcome Anticipated: |
Higher per capita income levels, sustained economic vitality, increased direct and indirect jobs, improved roadway level of service. |
|
Amount requested from the State for this project this year: |
$5,415,254 |
|
Total cost of the project: |
$5,415,254 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$11,304,000 |
|
|
Was this project previously funded by the state? |
|
Yes |
|
Fiscal Year: |
2002 |
Amount: |
$1,500,000 |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$5,000,000 |
To Fund: |
Construction |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
Unknown |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Five year work program |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
No |