(1)(a) A local government must approve, approve with conditions, or deny a building permit application after receipt of a completed and sufficient application within the following timeframes, unless the applicant waives such timeframes in writing:1. Within 30 business days after receiving a complete and sufficient application, for an applicant using a local government plans reviewer to obtain the following building permits if the structure is less than 7,500 square feet: residential units, including a single-family residential unit or a single-family residential dwelling, accessory structure, alarm, electrical, irrigation, landscaping, mechanical, plumbing, or roofing.
2. Within 60 business days after receiving a complete and sufficient application, for an applicant using a local government plans reviewer to obtain the following building permits if the structure is 7,500 square feet or more: residential units, including a single-family residential unit or a single-family residential dwelling, accessory structure, alarm, electrical, irrigation, landscaping, mechanical, plumbing, or roofing.
3. Within 60 business days after receiving a complete and sufficient application, for an applicant using a local government plans reviewer to obtain the following building permits: signs or nonresidential buildings that are less than 25,000 square feet.
4. Within 60 business days after receiving a complete and sufficient application, for an applicant using a local government plans reviewer to obtain the following building permits: multifamily residential, not exceeding 50 units; site-plan approvals and subdivision plats not requiring public hearing or public notice; and lot grading and site alteration.
5. Within 12 business days after receiving a complete and sufficient application, for an applicant using a master building permit consistent with s. 553.794 to obtain a site-specific building permit. 6. Within 10 business days after receiving a complete and sufficient application, for an applicant for a single-family residential dwelling applied for by a contractor licensed in this state on behalf of a property owner who participates in a Community Development Block Grant-Disaster Recovery program administered by the Department of Commerce, unless the permit application fails to satisfy the Florida Building Code or the enforcing agency’s laws or ordinances.
However, the local government may not require the waiver of the timeframes in this section as a condition precedent to reviewing an applicant’s building permit application.